€03? AMI ENERGY REQUIREMEMS 0F SLUDGE HANDLING AND ULTIMATE LAND DISPGSAL METHODS Tkests for II“ Degree of M. S. MICHIGAN STATE UNIVERSITY Charles R. BristoI W75 ‘ 25:53“. V“) x 0< I x 7‘0 V\ ABSTRACT CA COST AND ENERGY REQUIREMENTS OF SLUDGE HANDLING AND ULTIMATE LAND DISPOSAL METHODS by Charles R. Bristol A sequential decision model known as dynamic programming was used to analyze cost and energy consumption for 15 processes involved in sewage sludge treatment. Three conditions were con— sidered: (l) the economic Optimum using capital costs, operating power, and labor; (2) the optimum for an energy poor future using capital costs and operating power and; (3) the energy optimum using capital and operating energy. For the first case dissolved-air flotation, aerobic digestion and lagooning was found to be the best treatment scheme at a flow of 1 million gallons per day (MGD). For 10 MGD and 100 MGD the best treatment scheme was found to be gravity thickening, anaerobic digestion and lagooning. No change was found in these treatment schemes for case 2. For case 3, the best treatment scheme was found to be gravity thickening, anaerobic digestion and lagooning for all 3 design flows. COST AND ENERGY REQUIREMENTS OF SLUDGE HANDLING AND ULTIMATE LAND DISPOSAL METHODS by Charles R. Bristol A THESIS Submitted to Michigan State University in partial fulfillment of the requirements for the degree of MASTER OF SCIENCE Department of Civil and Sanitary Engineering 1975 ACKNOWLEDGEMENT This work was sponsored through a research assistantship from the Institute of Water Research as part of a grant from the Rockefeller Foundation. This assistance is greatly acknowledged. In addition, the author extends his appreciation to Dr. Mackenzie L. Davis of the Department of Civil Engineering, Dr. George Coulman of the Department of Chemical Engineering and Dr. Frank Hatfield, Director, Cooperative Education -- Engineering, for their kind advise and guidance. INTRODUCTION . LITERATURE REVIEW Thickening . Stabilization. Conditioning. Dewatering . Reduction Final Disposal . METHODS . . . . . RESULTS Thickening . Stabilization Conditioning . . Dewatering Reduction .' . . Final Disposal . CONCLUSION. . . APPENDICES » Appendix A . . Appendix B . Appendix C . Appendix D . Appendix E . Appendix F . Appendix G . REFERENCES CITED. TABLE OF CON TENTS iii Page 24 35 40 47 56 57 58 58 59 . 61 80 81 82 84 . 9O . 97 . 102 . 111 .115 .122 Table 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. L15 T OF TABLES Gravity Thickener Power Consumption . . . Dissolved Air Flotation Thickening Costs . . Dissolved Air Flotation Thickening Power Consumption. . . . . . . . . . . Digester Tank Sizes . . . . . . . . . . Sludge Heating Units . . . . . . . . . . Installed Hp and Electrical Power . . . . . Chemical Costs . . . . . . . . . . . . Thermal Sludge Conditioning . . . . . . . Uses of Dewatered Sludge . . . . . . Vacuum Filter Costs . . . . . . . . . . Centrifuge Costs . . . . . . . . . . Centrifuge Performance and Operating Costs . Centrifuge Power Requirements . . . . . Pressure Filter Costs . . . . . . . . . Capital Incinerator Costs . . . . . . . . Land Spreading of Sludges . . . . . . . Sludge Quantity Assumptions . . . . . . . Design Parameters . . . . . . . . . Sewerage Construction Cost Index . . . . . Sludge Quantities . . . . . . . . . Thickening . . . . . . . . . . . . . Stabilization . . . . . . . . . . . '. . Conditioning . . . ' . . . . . . . . . Dewatering Power and Labor. . . . . . . Dewatering Costs and Energy. . . . . . . Reduction.............. FinalDisposal. . . . . . . . . . . iv 28. 29. 30. Proccs 5 Limitations . Step 6 Combinations . Final Treatment Schemes . 62 65 78 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. LIST OF FIGURES Gravity Thickening Capital Costs . Costs of Gravity Thickening . Gravity Thickening Labor Requirements . Dissolved-Air Flotation Capital Costs . Dissolved -Air Flotation Labor Requirements . Aerobic Digestion Capital Costs . Aeration Basin Structure Construction Costs . Aerobic Digestion Labor, Requirements . Unit Anaerobic Digestion Costs . Anaerobic Digestion Labor Requirements . Sludge Lagoon Construction Costs . Sludge Lagoon Labor Requirements . . Sludge Lagoon Material and Supply Costs . Vacuum Filter Construction Costs . Vacuum Filter Labor Requirements . Centrifugation Construction Costs . Centrifugation Labor Requirements . Drying Beds Construction Costs . Drying Bed Labor Requirements . Multiple Hearth Incineration Costs . Incineration Labor Requirements . Incineration Material and Supply Costs . High Pressure Oxidation Costs . Low Pressure Oxidation Costs . Transportation Costs for Liquid Sludge . Sanitary Landfill Costs . . . Sludge Handling Process Flowsheet . Example Process Flowsheet . Flow - 1.0 MGD for Case 1 . vi 10 12 13 15 16 18 19 20 21 26 27 29 32 33 34. 37 38 39 41 42 44 45 54 64 68 30. 31. 32. 33. 34. 35. 36. 37. Flow Flow Flow Flow Flow Flow Flow Flow 1.0 MGD for Case 2 . 1.0 MGD for Case 3 . 10.0 MGD for Case I . 10.0 MGD for Case 2 . 10.0 MGD for Case 3 . 100.0 MGD for Case 1 . 100.0 MGD for Case 2 . 100.0 MGD for Case 3 . vii 69 TO 72 73 74 75 76 77 IN TRODUC TION Most methods of municipal wastewater treatment have an end pro - duct of large quantities of sewage sludge. This amounts to some 4.2 million tons per year in the United States alone. 1 It comprises about 50% of the total treatment cost and 90% of the operators headaches. The characteristics of the sludge vary both with source (i.e.: industrial or municipal), and with the sewage treatment process employed (i. e.: physical, chemical, or biological). These variations dictate the choice of sludge treatment. 2 The choice of sludge treatment must be made with regards to costs and energy requirements. The ultimate goal of any well managed community is to use the treatment scheme that will have the best cost- performance ratio and also the lowest energy consumption. Energy con- sumption not only includes the operating energy, but also the amount of energy needed for materials fabrication used in treatment facilities (herein termed "capital energy" because of the analogy to capital costs). Energy is considered separately in order to investigate design decisions that would be made if the price of energy increases dramatically to become the dominant cost. It is the purpose of this paper to present a comparative cost analysis of specific processes involved in sewage sludge treatment, and also to present a comparative energy consumption analysis of these same processes. The analysis is done under three conditions which are (l) the economical optimum for now and in the future, (2) the optimum for an energy affluent present with an energy poor future and (3) the energy optimum for now and the future. The processes considered in this research are gravity thicken- ing and dissolved -air flotation in the thickening step of sludge handling; anaerobic digestion, aerobic digestion and sludge lagooning in the sta- bilization stage of treatment; chemical conditioning, heat treatment 2 and freezing in the conditioning process; vacuum filtration, centrifu- gation, filter pressing and sand bed drying in the dewatering stage; incineration and wet -air oxidation in the reduction of sludges; and landfilling, land application for soil conditioning, and lagooning in the final disposal step. The sludge used in the above processes is a mixture of primary sludge (settled sewage from the primary sedimentation tanks) and activated sludge (wasted, biologically active solids from the secondary settling tanks). LITERATURE RE VIEW THICKENING Thickening or concentration is defined as removing water from sludge after its initial separation from wastewater. 3 The objective is to reduce the volume of liquid sludge to be handled in subsequent pro- cesses. Common types of thickening are gravity thickening, dissolved -. air flotation, and centrifugation. Centrifugation is covered later under dewatering. Gravity thickeners use natural gravity and gentle raking mech- anisms to settle the sludge to the bottom of the tanks and thicken it. Costs, power, and labor requirements depend on the size of the thickening tanks, which in turn are dependent on the flow into the plant. The cost of the installed thickener, which includes price of thickener, erection, site preparation, pumps, piping, steel, instrumentation, electrical, paint and indirect costs has been depicted as a function of tank diameter. 4 The cost of an installed thickener increases as the tank size increases as seen in Figure l. The operating and maintenance (O and M) costs decrease with the increase in dry solids or flow. Generally, O and M costs for gra- vity thickeners at large plants are about $ 2. 00 per ton of dry solids.3 The construction costs, however, increase as the dry solids increase as shown in Figure 2. The raking mechanisms are the only part of the thickener that requires power. Table 1 shows the electrical power requirements for a one million gallon per day (MGD), 10 MGD and 100 MGD plant thickening primary and activated sludge. 6 ) INSTALLED BASE COST (1972 DOLLARS .9 OOO’OOO l 1 l l lllll | l lllllj 100,000.. A I : L- .. - -I " a 10,000 I l I llllll l 1 J l Ill 10 100 1,000 DIAMETER (FEET) Figure 1. Gravity thickening capital cost [4] COSTS (.$/DRY TON) l lfillllll II IIITIIH I I TIIII K. 10 9009 :1. .0 -I 090 j ‘9‘" d 0" _ 00 I. —4 F- . d 1... = 1 E ’ 0a 2: 0d "' : a. 1 '5 A l IIIIIIII LI 1111111! 11 11111 .01 1 10 100 1,000 DRY SOLIDS (TON/DAY) Notes: 1. mph-DON Index of 1827. Figure 2. Amortization at 7% for 20 years. Labor rate of $6.25 per hour. No chemicals. Influent sludge with a solids content of 0.5%. Costs of gravity thickening [5] Minneapolis. Mar. 1972. ENR Construction Cost CONSTRUCTION COST (MILLIONS OF DOLLARS) TABLE 1 POWER CONSUMPTION PLANT SIZE PRIMARY=1= AC T1VATED>:<>:= (MGD) (KWH/day) (KWHLday) 1 10. 2 10. 2 10 20.4 20.4 100 30. 6 . 40.8 *10ading rate = 16 poundséday/square foot (lb/d/ftz) **loading rate = 8 lb/d/ft The labor requirement of a gravity thickener increases as the flow increases as shown in Figure 3.7 Operational hours increase faster than the required maintenance hours. In comparison to gravity thickeners, dissolved -air flotation (DAF) is cheaper initially but requires large amounts of power and chemicals. Dissolved -air flotation uses small air bubbles to raise all the sludge to the surface and collects it there and usually works best with waste activated sludge. 8 The installed cost of a D.A. F. unit is based on the size of the pressure tank, which is dependent on the solids loading and sludge characteristics. 5 Figure 4 shows the comparison between the installed base cost and the tank capacity.4 The machine has a lower capital cost than the gravity thickener but the expected lifetime is only half that of a gravity thickener.4 The process costs fOr the D.A.F. machine are given in Table 2 for various plant sizes. TABLE 2 D.A. F. THICKENING COST PLANT SIZE COST (DOLLARS/TON DRY SOLIDS)* (MGD) o and M AMORTIZATION TOTAL 1 9.00 ' 17. 00 26. 00 10 1.20 2. 80 4. 00 100 0.50 1.50 2.00 *Costs are based on: 1972 dollars, amortization at 7 % for 20 years, labor rate of $ 6. ZS/hr, power cost of $ 0. Ol/KWH, no chemicals and a surface loading rate of 14.4 lb/day/ftz. ANNUAL HOURS I I I I I l I I l I I I 1000 r— Operation 500 - .. Maintenance / / / 100.. // .1 / 50— L 10 I 1 L J l l 4 1 L 1 1 0.5 l 1.5 2 3 4 5 6 810 15 2025 100 PLANT DESIGN FLOW (MGD) Figure 3. Gravity thickening labor requirements [7] INSTALLED BASE COST (1972 DOLLARS) 1,000,000 IIII 100,000 Tj IIIIII I 10,000 1,000 II I IIIIIIII rlIIIIII Illllll I llllll l 11111111 11111111 10 Figure 4. 100 1,000 CAPACITY (CUBIC FEET) Dis solved-air flotation capital costs [4] The O and M and total costs decrease rapidly as the plant size increases. Chemicals would add another $ 2. 00 to $7. 00 per ton to the total cost. 5 Even though the operating costs are high, the rate at which the sludge can be thickened is greater than the rate of a gravity thickener. 3 The installed horsepower (Hp) of a D.A. F. unit is a function of thickener surface area. The electrical power consumption varies with the use of chemical thickening aids. Table 3 shows the electrical power used for various size plants with and without chemical aids. TABLE 3 D.A. F. POWER CONSUMPTION Plant Size Work Required Power (KWH/day) (MGD) Week Hp W/Chemicals* w/o Chemicals** 1 4o 14. 5 70 242 10 100' 50.0 608 1800 100 168 230. o 4692 18800 *loading rate = 2 lb/hr/ft2 2 ' **loading rate = 0. 5 lb/hr/ft The number of manhours required for using the D.A.F. is approximately twice that needed for the gravity thickener. Figure 5 4 shows that the operational hours increase faster than the maintenance hours as the design flow increases. STA BILIZA TION The principle purposes of stabilization are to make the treated sludge less odorous and less putrescible, and to reduce the pathogenic organism population. The selection of a stabilization method depends primarily on the final disposal procedure planned for the sludge. If the sludge is to be dewatered and incinerated, frequently no stabilization procedure is employed. 5 However, common types of stabilization used are aerobic digestion, anaerobic digestion, and lagooning. All three methods result in substantial decreases in the amount of suspended sludge solids in the system. . Aerobic digestion is the separate aeration of sludges. Cost depends primarily on the size of the tanks which is a function of waste ANNUAL HOURS 10 I I l l I T I I I I I I 5000 - Operation / 1000*- .. Maintenance 500 .I 100.. .. 50" - 10 1 l l l I I I 4 I I 14 0.5 1 1.5 2 3 4 5 6 8 10 15 20 25 100 PLANT DESIGN FLOW (MGD) Figure 5. Dissolved-air flotation labor requirements [7] 11 sludge volume. Aerobic digestion tanks are normally uncovered and unheated, and are much cheaper to construct than covered, insulated, and heated anaerobic digestion tanks. 3 Figure 6 shows the capital costs of aerobic digestion as a func- tion of tons of dry solids per day. 5 In terms of liquid volume the con- struction costs of the basins for the digestion tanks are shown in Figure 7.9 The construction cost of the basins increases at the same rate as the construction costs Of the entire system as shown in Figure ,6. The choice of aeration system, whether mechanical or diffused air, will change the amount of the initial cost. Dorr-Oliver, in 1968, developed cost equations for the acti- vated sludge process from available equipment information. These costs are similar to the capital cost of an aerobic digester with blowers. The equations are:10 Tank Capital Cost: LOG(COST) = (0.806)LOG(V) + 0.306 where COST = thousands of dollars and V = volume, 1000 ft3. Blower Capital Cost: COST = 3. 58(CAP) + 2. 53 where COST = thousands of dollars and CAP 2 capacity in 1000 standard cubic feet per minute (SCFM). Blower Operating Cost: COST = 0. 68 (CAP) + 0.14 where COST = dollars per hour and CAP 2 capacity in 1000 SCFM. Mechanical Aerator Operating Cost: COST 2 l.42(V/100, 000) where COST = dollars per hour and V = volume in ft3. The operating costs for the aerobic digesters are quite similar to the operating costs of the activated sludge tank. The major factor in the high operating costs of the aerobic digestion process is the power used in the blowers. About ten brake horsepower (BHp) per 10, 000 population is required for aeration. The labor required for the operation and maintenance of aerobic digestion is shown in Figure 8. The operational hours are about five times the maintenance hours needed due to the air equipment. Anaerobic digestion has a higher capital cost than aerobic diges - tion due to the heaters required and tank coverings. Digestion tank volume requirements, to which construction costs are related, depend AMORTIZED COST (SB/DRY TON) 100 10 12 I III IIIIIII Fl llllllll llIl [Hi-10 : 112%.; : 1 : ed : Z 21 = 1 E : 1' I )- .- IIIIIIIIIII IIIIIIIIIII Illlllllll.01 1 10 100 1000 DRY SOLIDS (TON/DAY) Notes: 1. Minneapolis. Mar. 1972. ENR Construction Cost Index of 1827. 2. Amortization at 7% for 20 years. 3. Influent sludge of 38% primary and 62% waste activated sludge with a solids content of 3.5%. 20 day volumetric displacement time. Figure 6. Aerobic digestion capital cost [5] 1 CONSTRUCTION COST (MILLIONS OF DOLLARS) :3 mumoo sofiosuumsoo ensuedfim Emma. coflmneau. Emma OHmOO coo; .mEOqO> OBOE .n 0.3th OOOJ CA: OH H _ :A_7___ _ _~_j___ _ __A_____ _ T .1. I I H. H 3 LI I T «moo HNOOH I I L m H I H _ _C__F_._ _ :_____— _ _:L__ _ _ 0H OCH COO; ‘1803 NOIIODHISNOO 000‘I$ 14 on temperature, sludge characteristics, storage requirements, quan- tity of sludge and the degree of digestion. Dorr -Oliver developed a capital cost equation for anaerobic - digestion which includes all heating, mixing and gas requirements, sludge pumps, concrete tank requirements and a digester cover. . . 10 The equation is: LOG(COST) = 1/(o.31 LOG(V) + 0.37) where COST 2 tenths of dollars per cubic foot and v = volume in 1000 R3. The volume of the tank depends on the type of sludge to be digested. Table 4 shows the comparison of tank volumes as a func - tion of flow and sludge type. 6 TABLE 4 DIGESTER TANK SIZES PLANT SIZE VOLUME (FT3) (MGD) PRIMARY ACTIVATED 1 8125 15,400 10 81,250 154,000 100 812,500 1,540,000 Activated sludge required about twice the tank volume of primary sludge. Operating costs for anaerobic digestion vary between $ 2. 00 and $4. 00 per ton of sludge treated.3 Figure 9 shows the O and M costs as they decrease when the digester volume increases, but over about 100, 000 ft3 the Operating costs remain constant. 5 Energy is consumed in anaerobic digestion by (l) heating the incoming sludge and holding the temperature at 95 degrees and (2) mixing the contents (gas recirculation). Table 5 shows the power needed for the sludge heating units in terms of plant size. ANNUAL HOURS 1000 500 15 Operation Maintenance / / / 100 / _ / / / / ‘50 / / / / / / / / / / 10/ IILIIIIIIIII 0.5 1 1.52 3 456810152025 100 PLANT DESIGN FLOW (MGD) Figure 8. Aerobic digestion labor requirements [7] COSTS (5/1,000 CUBIC FEET/DAY) 10 0.01 1.0 16 T IIII' FTII III] IIIIII I I I IITIIIIII I II I IIIIIIIII IIIIIIIj:10O : 10 : Nmortized _ —1 — —I :1.0 _ ——1 I IJIIIIII I I I I I IIIlIIII I IIIIIIIO. 10 DH 100 1,000 10,000 100,00 DIGESTER VOLUME (1,000 CUBIC FEET) Notes: I . 42.90?» Minneapolis. Mar. 1972. ENR Construction (final Intlvx ol I837. Amortization (II 7% for 20 years. Labor I'ilI‘I‘ oI $6.25 ])(‘I' hour. Sludge healing, circulating and control equipment. and rontrol building inc I ll(I(‘(I. Figure ‘1. Unit anaerobic digestion costs [5] CONSTRUCTION COST (MILLIONS OF DOLLARS) 17 TABLE 5 SLUDGE HEATING UNITS PLANT SIZE POWER NEEDED(BTU/HR) (MGD) PRIMARY ACTIVATED 1 1 unit at 129,000 1 unit at 223,920 10 2 " 645,000 2 .. 1,119, 600 100 3 .. 4,300,000 3 .. 4,47§,_4oo Table 6 shows the installed horsepower required and the electri- cal power consumption for the anaerobic digesters operating 75% of the time . 6 TABLE 6 INSTALLED Hp AND ELECTRICAL POWER PLANT SIZE No. of UNITS AND POWER (KWH/day) (MGD) PRIMARY ACTIVATED 1 1 unit at 6.0 Hp-100.8 1 unit at 6.4 Hp- 123.6 10 2 .. 8.3 " 307.0 2 .. 12.2 .. 456.4 100 3 H 21.3" 1146 5 .. 21.3" 1910 Tables 5 and 6 shows that activated sludge requires more energy than primary sludge, but the detention time or time required for diges - tion of the activated sludge is less than that of the primary sludge. This means the activated sludge can be processed faster than primary sludge. The manpower required to operate and maintain the equipment involved in anaerobic digestion is approximately double that needed for aerobic digestion. Figure 10 shows higher operational hours than maintenance hours in relation to plant flow.7 Sludge lagoons can be used for either digestion, drying or both processes consequently. Construction costs of sludge lagoons are directly related to volume and the initial capital cost is dependent on local land rates. Figure 11 shows these construction costs and how they increase as the volume increases with no apparent economy of scale. The principle factor affecting the O and M costs of the lagoons is the quantity of material handled each year. Figures 12 and 13 ANNUAL HOURS 5000 I I I I I I I I I j I I 1000 Operation / 500 / .— / / 100)- / _ / 50— / — / / 10 I I I I I II I I I I I 0.5 l 1.5 2 3 4 5 6 810 15 2025 18 PLANT DESIGN F LOW (MG D) Figure 10. Anaerobic digestion labor requirements [7] 100 19 :: mLmOO cofiosfimcoO coomfl empgm .: Ousmfih HMMM OHQDO coo; .MEDJO.» HOQOJW 80.2 coo; OS 2 _:Z:_ I _:_____ _ IZJLN _ L T I 1 I IIIIII I IIIIII OH I umOU HQHOH. I I I I I IIIII IlIIl OOH I I I I I IIIII IIIII _:_____ _ :LPPP__ r _::__.L _ coo; I)II}I.I.SNOI) ' .I.SOI) NO] .I. 000‘ I?» ANNUAL PAYROLL MAN- HOURS 20 I 1,000 I IIIII I 7 IIIIIII I I IIIIIII I II Maintenanc e labor \ LI IIIII 100 : __ \Operation labor _ (based on but not including _ sludge removal by contract) d 10 l IIIIIIII I I IIIIIII I II 100 1,000 10,000 Figure 12. DRY SOLIDS APPLIED, TONS PER YEAR Sludge lagoon labor requirements [11] $1,000 ANNUAL COST, 1,000 100 10 21 I fl I II—IIII I IIIWI IIIIIII l I l IIIIIII I IIIIIIII I II IIIII IIIIIL I I Includes cost of sludge removal by contract __ IIIIII IIIIIII L IIIJILIJ I ll 1,000 10,000 DRY SOLIDS APPLIED, TONS PER YEAR Figure 13. Sludge lagoons material and supply costs [11] 22 show the labor requirements and supply requirements and how they increase steadily as the volume of solids handled per year increases. The energy requirements of the sludge lagoon are very small as it uses power only for pumping; no heating, aeration, or coverings are required. Costs and power are kept at a minimum with the only major disadvantage being the time required to hold the sludge. It ranges anywhere from 3 to 5 years. 11 CONDITIONING Conditioning is the pretreatment of sludge to facilitate de- watering. Two basic types of conditioning are chemical and physical. Chemical conditioning can use both organic and inorganic chemicals and physical conditioning can be accomplished using freezing or heat treatment. Chemical conditioning is a coagulation and flocculation process. Inorganic chemicals such as ferric chloride, lime and aluminum sul- fate, as well as organic polyelectrolytes, primarily the cationic and anionic polymers, have been effective in reducing the resistance to dewatering of the sludges. Z The polyelectrolytes increase the dewatering rate more than inorganic chemicals, but the cost of the polyelectrolytes is very high. Table 7 presents the daily cost Of chemicals for conditioning. TABLE 7 CHEMICAL COSTS Avg. Dose Flow Cost Usage Daily Chemical (mgll) (MGD) ($ /day) (1b [day) Cost Ferric Chloride 110.0 4 0.066 918.0 242.36 Cationic Polymer 1.35 4 1.45 11.3 65.56 Anionic Polymer 0.75 4 1.35 6.25 33.76 If chemical conditioning is used, the capital, operating and maintenance costs will be the same regardless of type of chemical. The only choice affecting costs is in the type of chemicals used. There are many conditioning chemicals from which to choose. 23 Freezing is a very unusual process to be used in sewage treatment but it is a very effective sludge conditioner. 3 Costs of this process are very high and include power, flocculants (if needed), and expensive refrigerating fluids. It takes about 170 BTU's to freeze one pound of sludge. 3 Capital costs of the freezing process include tanks, stirrers, buildings, automatic controls and the freezing plant. 13 Capital costs vary about a mean of $17, 000 per 1000 gallons of sludge processed. 14 Operating costs are in the range of $4.75 to $49. 50 per 1000 gallons depending on the type of sludge. 3'14_15 The power required for this process is very high ranging from 180 to 230 KWH per 1000 gallons. 1‘4 Very high operating costs and energy requirements have been the major factors in keeping freezing from becoming a widely used process. This process would be very effective in a cold climate. On the opposite end of the scale, heat treatment uses tempera- tures between 300 and 500 degrees F and pressures of 150 to 400 psig5 to condition sludge. Heat treatment improves the dewaterability of sludges ten times better than chemical conditioning. It also has the advantages of having no Odors, not requiring chemicals and reducing the pathogens to zero. The wet oxidation process Operated at low pressures can be used for heat treatment. The operating costs would be less than wet oxidation due to lower pressures and temperatures. Power require- ments are high because of the higher than normal temperatures and pressures. Table 8 shows the operating costs for thermal conditioning in Kalamazoo, Michigan. 16 TABLE 8 THERMAL SLUDGE CONDITIONING ITEMS ACTUAL COSTS PREDIC TED COSTS Maintenance 8 3. 12 /MG 8 2. OO/MG Power* $1.4l/MG $1. oo/MG Fue1=:<=:< $ 1. 27/MG $ 2. ZOA/MG *electrical rate : $ 0.01/KWH =:=>I= fuel costs = $ 1. O/million BTU 24 DEWATERING Sludge conditioning by either a chemical or physical condi- tioner is used primarily with the dewatering step of sludge treatment. The primary Objective of dewatering is to reduce the sludge moisture content to a degree allowing ultimate disposal. The main methods of dewatering consist of vacuum filteration, centrifugation, pressure fil- tration and sand bed drying. Table 9 shows the relationship of dewatering to other sludge treatment processes for typical municipal sludges. 5 TABLE 9 Normal Use of Sludge Cake Pretreatment Land Land Heat In cine r _ Method Thick en Condition Fill Spread D rving an‘ on Vac. Filter yes yes yes yes yes yes Centrifuge yes yes yes yes yes yes ' Filt. Press yes yes yes. variable ' no yes Drying Bed variable no yes yes no no Capital and construction costs of vacuum vilters, associated equipment and structures are related to the filter surface area. The filters themselves cost $ 95. 00 to $ 275. 00 per square foot.3 The buildings usually double the cost. An equation developed by Dorr-Oliver shows the relation between costs and filter area. The equationis:l LOG(COST) = 0. 65-0. 66(LOG(A)) where COST = hundred dollars per ft2 and A 2 area in 100 square feet. Equipment used in vacuum filters includes the filter, vacuum receiver, vacuum pump, filtrate pump, chemical feed tanks, sludge pump and sludge flocculator. Table 10 shows capital costs of vacuum filters with their respective building areas. 25 TABLE 10 VACUUM FILTER COSTS (1972) Filter Bldg* Const** Total Type Size Cost Cost Cost Cost Rotary lO'dia -l7 'face 58100 6000 20700 85, 800 Convent. 6' " - 6' " 30000 3000 10500 43, 500 Rotary 10' " -l4' " 53500 5000 18600 76,600 *assumed to be $ 10. 00 per sq. ft. of building ** assumed to be 35% Of the equipment cost Figure 14‘ shows the steady rise in construction costs as the size of filter increases. 11 Operation and maintenance costs depend on chemicals (49 %), direct labor (20 %), supervisory and maintenance labor (20%), power (9%) and supplies (2 %). 17 Power costs are directly proportional to the filter area. This is shown in the following equation:10 COST = 0. 15 (A) where A = area in sq. ft. and COST = cents per hour (includes power cost of 1. 551’ per KWH) The labor required for operation and maintenance of the vacuum filter are shown in Figure 15. The operational labor for hauling the sludge to a landfill is higher than that of conveying the sludge to an incinerator. 1 Centrifugation has some advantages over vacuum filtration. It is simple, compact, totally enclosed, flexible, and costs are moder- ate. 3 Centrifugation uses less power and requires less maintenance than vacuum filters. Capital costs of centrifuges vary with the size of centrifuge purchased, which is dependent on the flow. Table 11 shows the capital costs of the Sharples SP-6500 centrifuges together with the building 0 O 15 requlrements and construction costs. #mentioned product does not imply endorsement 26 :3 mumoo GOSOsnumcoo non—E «5533/ J; madmflh HHHLH HM .mH ousmmh M mmm mZOH .DHmHHdHh mQHJOm VmD 000.2: ooo.oH . coo.” 00H I I IIIII I 44d~___ — _____—fi_ a _:—L___ _ .8an Does: OOGHOE T I nonmfi I .coflmuomO I I l I I Loudness”: 23923 O» O» pe>o> empgm HOME I 1:00 ewpsfim I I l n ... I I _L__r_ _ :_:__ _ L %:___L_ _ I on: coo; ooo.o~ 000.2: SHHOH "NVW 'I'TO‘cIAVd rIVIlNNV 28 TABLE 11 CENTRIFUGE COSTS (1972) No. of Unit B1dg='-< Const** Total Units Cost(§) Cost($) Cost($) Cost 5 55,000 10,000 96,300 381,300 10 55, 000 20,000 192,500 762,500 2 55,000 4,000 38,500 152,500 >I‘assumed to be $ 10.00 per sq. ft. ** assumed to be 35% of the equipment cost The capital cost of $ 55, 000 per unit remains constant, and the construction costs and building size required are directly proportional to the number of centrifuges employed. The equation developed by Dorr -Oliver for the capital cost of centrifuges is: ' LOG(COST) = 2. 5 - 0.193LOG(I.F.) where COST = dollars per pound and I.F. = influent flow in lb dry solids/hour. This equation involves only the cost of the centrifuges and does not include any accessories or construction costs. Figure 16 shows how the construction costs of centrifugation increases as the capacity . 11 increases. 0 and M costs depend on the power used, the chemicals used, and the amount of labor required. Table 12 shows the operating cost in terms of maintenance, operating labor, energy, amortization and chemicals . 29 :3 mumoo Gofluoshumsoo GoflmmsfinuCOO g: 0.3th 2&0 .VHHOAQVoneaO Emfim 000; 2: 0H III I I II ___ _ _ _ _ _ _ __ q— _ _ _ _ _ OOH coo; umOU HNHOH. I _ _; p _ b _ _ _ b- __ _ _ b _ _ 000.0H 000 ‘ NS ‘1303 NOIIOBHISNOO 30 TABLE 12 CENTRIFUGE PERFORMANCE AND OPERATING COST Plant No. Mach. Op. Maint. Labor Energy Amort* Total** 1 Flow of Size Hrs ($) ($) ($) ($) ($) (M GD) Units (IN) ka ton ton ton ton ten 18 1 24-38 168 2.53 2.71 0.70 1.30 16.54 1 24-38 9 1. 75 0.94 0.39 13.20 16.28 3.8 1 24-60 21 2.63 7.17 0.49 7.65 30.74 8 2 24-38 35 1.74 1.00 0.35 3.23 6.32 45 2 24-60 60 1.90 2.50 1.39 7.65 13.44 6 2 18-42 48 2.73 1.53 0.59 4.32 14.89 1.5 1 18-42 7.5 0.97 7.40 1.33 71.70 92.60 1.7 1 18-42 30 1.36 9.00 1.58 20.30 44.55 1.2 1 24-38 3 0.24 12. 70 0.83 100.00 113. 77 20 3 24-60 40 2.16 1.05 0.31 3.10 14.62 7 1 24-60 40 3.66 3.20 0. 70 5.50 17.62 7. 5 2 24-60 168 4.32 3.26 1.65 3.65 26.818 *amortization based on 6% interest over 25 years ** includes chemicals at various costs and various dosages As shown in Table 12, the components of the operating costs vary with flow and hours of Operation per'week. Small plants running for just a few hours a week spend more money on the process than do the larger plants. The power requirements of a centrifuge depend on the bowl size and the Speed at which the machine is run. Table 13 shows the power used in centrifugation in relation to plant flow. TABLE 13 CENTRIFUGE POWER REQUIREMENTS Plant Size Power Needed (KWH/day) (MGD) Primary Activated 1 28. 0 90. 0 10 256. 0 435. 0 100 1400. 0 4348. 0 Centrifuges use approximately the same amount of power that vacuum filters use. 31 The labor requirements of centrifugation depend on the ser- vice required to operate and maintain the high solids removal charac- teristics. Figure 17 shows the annual payroll hours needed for main- tenance and operating labor. 11 The operational labor is more than maintenance and is about the same as the labor requirements of vacuum filtration. Over six thousand wastewater treatment plants in the United States use the method Of sand drying beds for dewatering sludges. 3 These plants, however, are older plants and the drying beds are becoming obsolete as plants become larger and new dewatering tech— niques are developed. Construction costs are related to surface area requirements which depend on the quantity and quality of sludge, local climate, and whether or not the beds will be covered. 11 Figure 18 presents the construction costs of twenty -two actual uncovered drying bed installa- tions. 11 The cost rises with increasing surface area. The capital cost of the beds can double if mechanical lifting and conveying equip- ment is employed. The O and M costs of drying beds are primarily due to the loading and hauling of the dried sludge, and keeping the beds in proper operating condition. Operating costs have been determined to range between $ 1. 00 and $ 10. 00 per ton of dry solids. 3 The wide range is due to the different techniques of loading and unloading the sludge from the bed. The labor required to keep the drying beds operational is shown in Figure 19. 11 The required operational labor is more than the main- tenance labor due to the loading and unloading technique used. The last method of dewatering in use today is pressure filtration or filter presses. Pressure filtration is a batch process and requires a great deal of labor, but it produces higher solids concentration and reduced chemical consumption. Capital costs of pressure filters vary with size of filter used. Cost of the filters includes the cost of presses, plate shifters, feed pumps, precoat equipment, buildings, and installation. Table 14 presepgs the cost breakdown of four pressure filters in Virginia, 1972. ANNUAL PAYROLL MAN-HOURS 32 100:000- I I IIIIFIT I I TIIIIII I I I ITII r- .. r- _ I— — Haul sludge tolandfill 10 000— Sludge con- __ , : veyed to : _ incinerator a T" "I — Operation labor -( 1,000 : Maintenance labor 100 I I IIIIIII I I lllllll I IIIIIIL 100 1,000 10,000 100,000 DRY SOLIDS APPLIED, TONS PER YEAR Figure 17. Centrifugation labor requirements [11] $1,000 COXST RUCTION COST , 33 10.000 l IIIIIIIF I TIIIIIIT I I IIFII I I I 1,000 IIIIII I I VTotal cost I 100 IIIIII I I 10 I I I I 11111 I I .LI 11111 1 I I TII I IIII I I IIIIII I I IIIIII I L I 1111 10 100 1,000 SURFACE AREA, 1, 000 SQUARE FEET Figure 18. Drying beds construction cost [11] 10,000 34 :2 muceaonwsqeu .8an mpen mcffip prgm .0.“ 0.3th macaw? mam mZOH .Qmfiqmnmaoa mQHAOm .WMQ 80.2 08; . 2: S 1:. a _ _:I_7_ _ 22:4. _ 2: I I Honda Docmseucfimz IIIIII 1111111 000; I I h .8an :Oflmnomo I I IIIIII LIIII I 000;: _____E_ ___h_____ _________ SHHOH'NVW rIrIO‘dAVd 'IVIINNV 35 TABLE 14 PRESSURE FILTER COSTS No. of Size Bldg Cost (X1000 $) Units (In.) Area Press Shift Prect Bldg=I< Inst** Total*** 4 48 3200 80 9. 6 20 32 38.7 181.2 3 48 2100 69 6.9 15 21 32.1 144.9 1 48 1200 21 2.7 5 12 10.4 52.0 3 48 18000 67.5 6.6 18 18 31.5 139.5 *based on $10. 00/sq. ft. >:<>I< based on 35 % of total equipment ::=>'.<>:< includes a $900- 00 feed pump The initial cost of the filters ranges between $ 20, 000 and $ 22, 500 each and the total costs vary accordingly. 15 Operating cost of pressure filters depends on the labor required (about 2 men per filter), the chemicals required, and the power used (about 270 KWH/day for a 48" filter). Operating costs without chemicals have been determined to be about $4. 69/ton, and the chemicals add another $7. 29/ton. 5 Using chemicals with filter presses increases the solids recovery, with a consequent increase in the solids concentration. REDUCTION Sludge reduction processes are thermal processes. They pro- vide a major reduction in the sludge solids. Common established pro- cesses of reduction are incineration and the wet -air oxidation, or Zimpro*, process. Sludge incineration is generally more expensive than other sludge disposal methods. The capital cost of incineration systems depends on the type of incinerator, and whether or not pollution control equipment is required. If the deoderizer is installed with the incinerator, the capital cost increases about 3 %, and the operating cost increases about 50%. Table 15 shows the capital costs of incinerators according 19 to manufacturer's 1968 prices. *mentioned product does not imply endorsement 36 TABLE 15 CAPITAL INCINERATOR COSTS Type Size (lb/hr) - Cost ($) Fluid Solid 200 180, 000 400 300, 000 1000 550, 000 2000 825, 000 Multiple Hearth 500 300, 000 ' 2000 550,000 4000 700, 000 6000 850, 000 Cyclo -burner 130 70, 000 The multiple hearth furnace is the most commonly used incinerator in the United States today, and the prices and sizes show why. The reported operating costs of multiple hearth furnaces vary substan— tially due to moisture content of the sludge, labor, power and auximilary fuel. Rochester, New York, reports operating costs of $ 24. 55/ton for incineration while South Lake Tahoe reports an operating cost of $ 12.71 per ten. 5 Figure 20 shows the decreasing costs for Operating a multiple hearth furnace as the solids per day increases. The labor associated with incinerators is included in the opera- tion and maintenance of conveyors, ash handling equipment, control centers and the building enclosing the furnace. Figure 21 shows the annual payroll hours required for incineration as a function of dry solids burned per year. The power requirements are due to the electrical power and auxiliary fuel needed to maintain adequate temperatures within the furnace. Raw primary sludge with 70 % volatile solids has a fuel value of about 7800 BTU/lb of dry solids and will burn without fuel once combustion has started. 20 The auxiliary fuel unit cost decreases as the cake solids concentration from the dewatering process increases. A solids concentration of over 30 to 35% will support combustion with- out auxiliary fuel. Figure 22 shows the annual cost of electrical power and fuel cost for an incinerator. COSTS ($/DRY TON) 1000 100 10 1.0 37 L. I I I IIIIII I I IITIIII l I IIIII':-_~10O L'. I -- -I Z : 10 I x, '— I— = P- 0 -l -o F' 06° 7 _ 91g; - 00° TotaI t ‘ reatment COst - . O and M Z — mOrtized _. l LIIIIJJI I IIIILIII l I 111111 0.1‘ 1 10 100 ~ 1000 DRY SOLIDS (TON/DAY) Notes: 1. Minneapolis. Mar. 1972. ENR Construction Cost Index of 1827. 2. Amortization at 7% for 20 years. 3. Labor rate of $6.25 per hour. 4. Exhaust gas scrubber and enclosing structure included. 5. Costs do not include deodorization of gases: where required, add $4 to $10/dry ton. Figure 20. Multiple hearth incineration costs [5] CONSTRUCTION COST (MILLIONS OF DOLLARS) ANNUAL PAYROLL MAN- HOURS 100,000 38 IITIIII I 10,000 IIIIII I 1 ,000 100 I I ITIIIII I I ITIIIII l Operation labor Maintenance labor I IIILLIII I IIIIIIII 1 LI [Iii I IIIIIL 441 ILIIIIJI 100 1,000 10,000 DRY SOLIDS INCINERATED, TONS PER YEAR Figure 21. Incineration labor requirements [11] ANNUAL COST , DOLLARS 100,000 39 III I I 10,000 1,000 - b — )— _ p— h— 100 I I Electric power and fuel costs I J IIIIITI. I I INIIIII I [j Other material and supply costs IIIIIII I IIIllIII I II I I L1 1 IIIIIL I I IIIIII I I 100 1,000 10,000 DRY SOLIDS INCINERATED, TONS PER YEAR Figure 22. Incineration material and supply costs [11] 40 Operating costs for fluidized bed incinerators have been esti- mated by the East Cliff Sanitary District, California. The costs were reported to‘be $ 25. 32 per ton which includes $ 2. 50 per ton for fuel, $4.47 per ton for power and $18.35 per ton for labor.3 Wet -air oxidation refers to the oxidation of sludge solids in water by applying heat and pressure. Basic equipment is a reactor, air compressor, heat exchanger, and a high pressure sludge pump. The process can be run at both high and low pressures, with the high pressure costing more. The economy of both processes depends on recovery of heat. Figure 23 shows the installed cost and the Operating cost of the high pressure oxidation (HPO) system as a function of the capa- city. 21 Figure 24 shows the same costs for a low pressure oxidation (LPO) process. 21 The installed cost for the HPO system is 4 to 5 times the installed cost of the LPO system. The operating cost of HPO is double the Operating costs of LPO. HPO costs more, but it reduces twice the volume of insoluble volatiles than the LPO system. At Wheeling, West Virginia, in 1965 a 5. 6 ton/day Zimpro process was installed for $ 284,000. The operating costs were found to be about $ 19.90 per ton processed. This includes power at $ 6.11/ton (31%), chemicals at $4. 13/ton (21%), fuel at $ 1. 65/ton (8 %), maintenance at $1.17/ton (6%) and labor at $ 6.91/ton (34%). Power and labor are quite high in this process and make it uninviting 3-5 to an energy minded community. FINAL DISPOSAL No matter what thickening, stabilization, conditioning, de- watering, or combustion process is employed, provision must be made to dispose of the inevitable end product. Common methods of final disposal include land spreading for fertilizer or soil conditioning, lagooning and landfilling. Using dewatered, digested sludge as a fertilizer and soil condi- tioner is becoming a popular alternative to combustion and landfill. The best sludge to be used for fertilizer is waste activated sludge that has been vacuum filtered and heat dried. The high nitrogen content of the sludge has not been destroyed by digestion. [Prices for nitrogen, 41 NOI. GBSSBOOHd/S 'ISOC) ONIIVHBdO :2 mumoO cofimpflxo augmmOuQ swam .mm 0.5me aims .wfiofifiao 89. 8mm Sea 08... . coo... 82 82 com o a — d . _ a — _ o l J N. .I.- In Rama? do» w I I oI cam . I . .~ 6 O oom coca 00mm ooom OOmN lISOD CIEI'I'IVISNI OOOIX$ 42 NOT Gassa DO‘dd/ISOO DNIIVHEIdO :NL mumOO cofimpwxo wusmmoum Bod .vN Ousmwh mm\mq ooov comm Sam 83 ooow com; 82 com o a I 1 com N I I com 0% m I 626 I 08. 862/ a. U I oom Cam. . e . e o m I I ooe _ p _ L r b _ 0001 X 1303 (IEI'I'IVISNI 43 phosphorus, and potash in 1968 were 20 .7, 10 9’. and 5 g! per lb, respectively. This makes the activated sludge worth $ 20. 00/ton, and digested primary sludge worth $ 11. OO/ton. 3 The only cost involved in using sludge as a fertilizer is hauling to the farmland. ‘ Various locations around the country are using the land for final disposal of sludge. Table 16 shows various cities that spread sludge on the soil for many reasons and the costs that they incur during the process. TABLE 16 LAND SPREADING OF SLUDGES ‘ Plant Size Cost Location (MGD) . ($ /Ton) New York City --— ll. 89 Chicago 1300 26. 02 San Diego 90 10. 57 St. Marys, Pa. . 1.3 19.92 Little Miami, Ohio 1. 3 22. 00 Piqua, Ohio 3. 8 l7. 5 to 30. 00 Franklin, Ohio 4. 5 5. 00 f If there is not a market for sludge then it can be sent to lagoons. The area required for lagoons requires from 1.0 sq. ft. per capita with primary digested sludge in an arid climate, to as high as 4 sq. ft. per capita for activated sludge plants in rainy areas. The Operating and capital cost Of the lagoons depends on the method of transportation used. Figure 25 shows the transportation cost for liquid organic sludges as a function of distance to the disposal site. 5 A pipeline has lower costs from 40 to 200 miles away. Beyond 200 miles, rail shipping becomes cheaper. If combustion is used then provisions must be made to dispose of the ash that results. Sometimes pressure filters are used in con- junction with incineration so the ash from the furnaces can be used as a precoat for the filter, Ash, and even dewatered sludge, is sometimes dumped into a landfill area mixed with municipal refuse. Figure 26 shows the capital and O and M costs for sanitary landfills excluding 44 600 400 I- 200 - 100 IW'I T 0‘ 0 II I II TRANSPORTATION COST (DOLLARS/TON DRY SOLIDS BASIS) 20 Tank truck \ Railroad tank car 4 III] Pipeline I IIIIIIII I I 20 Figure 25. 4o 60 100 200 400 DISTANCE To DISPOSAL POINT (MILES) Transportation costs for liquid sludges [5] COSTS (SE/WET TON) 45 : I I IIIIIIF I I IIIIIII I I IIIIII: 6 E I: 4 " 5\ .. _. x99 _ 2 — 539% \9 1 +0 \8 10 : e°° : .. 00 .. 6 : 9“" : L. Ota CO _ St 2 _ (6x01 _ 1.0 : Z _ J 4 I" _. 2 " .a 0.1 I I LIlIlIl I IIIJIIII I I IIJJI 10 2 4 6 100 2 4 6 1,000 2 4 6 10, QUANTITY (WET TON/DAY) Notes: 1. Minneapolis. Mar. 1972. ENR Construction Cost Index of 1872. 2. Amortization of 7% for 20 years. 3. Labor rate of $6.25 per hour. 4. Quantity assumes 6-day work week. 5. Wet Sludge must be considered for cost per ton. Figure 26. Sanitary landfills costs [5] 1.0 0.1 CONSTRUCTION COST (MILLIONS OF DOLLARS) 46 the. cost of the land. The costs are soon to be relatively low and the problems of the landfill are minimal in cmnparison with other methods. Ocean di3posa1 of the final sludge product is used by some seacost cities at a very low cost, but environmental legislation has stopped the granting of new ocean disposal facilities until further studies are done . Capital energy, as defined earlier, has not been found in any of the literature reviewed. 47 METHODS The first step in this analysis was the estimation of the amount of mixed primary and activated sludge produced per million gallons of wastewater treated. Each unit process was designed to handle the estimated amount of sludge. Then the amount of materials (steel and concrete) involved in the production or construction of each unit process was determined to calculate the capital energy involved. The capital and operating costs were obtained from values reported in the available literature and together with the capital and operating energy were compared to determine the optimum treatment scheme with regard to energy and costs. Three sizes of treatment plants were chosen to include most treatment plants in the United States. These sizes are 1. 0 MGD, 10. O MGD, and 100. 0 MGD. The wastewater in these plants was assumed to be of typical values for influent biological demand (BOD) and influent suspended solids (SS) are 200 milligrams per liter (mg/1) and 200 mg/l, respectively. Assumptions used in calculating the quantity of sludge are shown in Table 17. 24 TABLE I7 SLUDGE QUANTITY ASSUMPTIONS Raw Primary Sludge removal efficiency of clarifier --------- 60% SS; 30% BOD solids concentration ---------- 5 % Waste Activated Sludge effluent BOD ------ 10% ; solids yield ------ 50 % solids concentration ------ 0. 7 5 % Each process was designed according to Federal regulations utilizing the estimated sludge generation rates. Table 18 lists the basic criteria followed for each process designed. 48 TABLE 18 DESIGN PARAMETERS PROCESS PARAME TER Gravity thickenerZS-26 ----- Limiting solids flux rate = 6 lb per sq. ft. /day Influent solids concentration 2 1. 3 % Underflow solids concentration = 6 % Depth = 15. 0 feet Wall width = l. 0 feet Dissolved -air flotation5 ----- Solids loading = 2' lb/ftz/hr Solids recovery = 50 to 80% Maximum hydraulic loading = 0.80 gpm/sq. ft. Volume of sludge = 56 ft3/mi11ion gallons Detention time = 30 minutes Anaerobic digestion2 ------ Solids loading = 30 to 100 1b volatiles/1000 cu. ft. Detention time = 30 days Temperature = 85 to 95 deg. F Tank diameter = 20 to 115 feet Water depth : 25 feet Freeboard = 2. 0 feet Well insulated covers Waste efficiency = 0.75 Net growth rate = 526 lb/day Aerobic digestion26 5 ------ Detention time = 20 days Solids loading 2 0.1 to 0. 2 lb volatile solids/cu. ft./day 49 TABLE 18 (continueQ DESIGN PARAMETERS PROCESS 26 —5 Aerobic digestion ------ Chemical conditioning26 - - - - Heat treatment 5‘24 -26 _--- Drying bed326--. .......... Vacuum filtration5 — —————— 19-26 Centrifugation ........ PARAMETER Hydraulic detention time = 20 days Air requirements = 25 SCFM/1000 ft3 Blower efficiency = 70 % Contact time = 30 minutes FeCl2 dosage = 2% (raw); 3% (dig.) Motor efficiency = 80% Pressure = 180 to 210 psig Residence time = 30 minutes Temperature = 350 to 390 deg. F Solids loading = 15 lb/ftZ/yr Open beds in northern climate Bed slope = 5% Application = 6 to 12 inch layers Partitioned into 20 foot wide by 20 to 100 foot long sections Loader efficiency = 80% Yield = 4 lb/ftz/hr Feed solids = 5% Effluent solids = 20 to 30% Feed solids : 2% Effluent solids = 15 to 40% Length/Diameter ratio = 3 Solids recovery = 80 to 95% Bowl speeds = 3000 to 7000 rpm Force = 2500 to 6000 G's 5O TABLE 18 (continued) PROCESS PARAMETER . . 26-28 . Pressure Filtration -—--Pressure = 60 to 225 p31 Detention time = 2 hours Sludge cake thickness = l. 5" Effluent solids = 30 to 50% Cake volume = 3. 0 ft3/chamber Cake density 105 lb/cu. ft. Incinerationé’26 ........... solids loading = 2 lb/ftz/hr Temperature = 1400 to 1700 deg. F Capacity = 200 to 8000 lb/hr Combustibles = 60% of sewage Efficiency = 100% of combustibles Wet oxidation5 ------------- Pressure = 1000 to 1750 psi Temperature = 250 to 700 deg. F Detention time = 30 minutes Combustibles = 60% of sewage Fertilizer and Soil5 -------- Solids loading = 15 tons dry solids per Conditioner acre/year Liquid application rate = 5000 gal/acre/day (MAX) Truck working efficiency = 80% Hp operating efficiency = 60% Lagoons5 ------------------ Depth = 5 feet Bottom must be 18 inches above water table Solids loading : 2. 2 lb/ft3/yr 51 TABLE 18 (continued) PROCESS PARAMETER Landfills ------------------ Waste layers = 2. 0 feet Compacted layers = 2. 0 feet Spreading on soil5 ---------- Same as fertilizer 52 Once the size of the individual process was determined for all three design flows, the capital costs, operating costs, operating energy and capital energy we re determined. Capital costs were taken from data gathered from professional literature and from manufac- turers' data. Operating costs were considered to be entirely composed of annual manhours needed for maintenance and operation based on a labor rate of $ 7. 10 per hour for skilled labor. 2'7 Operating power was calculated as a separate item. The Sewerage Construction Cost Index (SCCI) determined by the Environmental Protection Agency was used to adjust all capital cost data to a base data of January, 197 5. Table 19 shows the Detroit cost index which was used in this study. The base index of 100 is for the period 1957-59. TABLE 19 S.C.C. INDEX Year Detroit 1969‘ 138.7 1970 ‘ 153.2 1971 163.4 1972 180.7 1973 188.9 1974 200.4 1975 . 239.6 1 Power, like money, can be expressed in both operating and capital terms. Capital energy, like capital cost, is the initial amount of energy used to produce a piece of treatment equipment .or construct a unit process. In this study capital energy was taken to be the energy required to produce the steel and concrete involved in the equipment or process. This is, of course, only a first approximation as transportation energy and construction energy also contributes to the capital energy. The total weight of steel and volume of concrete used in the production or construction of a sludge process were used to compute the capital energy for each unit process. 53 Both operating and capital energy can be expressed in dollars. Once converted to dollars, capital energy can be amortized in the same manner as capital cost at 8% interest over a standard design life of 20 years. In order to make energy costs comparable, it was assumed that all the energy used in the production of the steel and concrete was electrical power. This results in an average dollar value for the capi- tal energy. A local energy cost of $ 0. 03 per KWH was used. Knowing the operating and capital costs and the operating and capital energy a decision as to the best treatment scheme can be made by applying a sequential decision model known as dynamic programming. Dynamic programming is applicable to the optimization of system-s posesgsing a serial structure with no recycle. Figure 27 shows the framework of sludge handling processes. This flow chart is a typical serial structure with no recycle. For example, whatever happens in the stabilization step influences the events of the dewatering step but has no effect upon the thickening step. Dynamic programming compares the independent variable of each process with special regard to the limitations and determine the optimum selection for sludge handling. In this work the optimum selection was made for three different assumptions regarding energy and cost for all three design flows mentioned earlier. The conditions used were as follows: 1. Economic optimum - 1975 and future 2. Energy affluent present with energy poor future 3. Energy optimum - 1975 and future Case one, the economical optimum, was calculated using only operating and capital costs without separation of the energy component. This case assumes that the energy costs will inflate at the same rate as the equipment costs. Case two, the energy poor future, was cal- culated using 1975 capital costs and considering operating energy in the future. Case three, the energy optimum, was evaluated utilizing only the capital energy and operating energy without consideration of other costs. This leads to a limiting case involving only energy and will be applicable if the energy costs escalate at a faster rate than normal inflation. 54 ”Seaman/OE Homommfiv was mfimmoooum owwgm wouflmnonoo .NN ounwfim 1| J — _ d _ J o QHHm m mmHm v nHHHm m nHHHm N mHHm H nfimHm 30m no i mnwwmoumm God on a no on f “3:693 Gown—MEMO onmummwam ”— gm u L :33qu .3 «03 a ”Ema lwoZOmmfiu mommooonm «segue: ,“---'--"l.{'luIIII'-.J‘--I'I'-|'-.IJ1II-II'I'II-O. II'"'II'I-'I1 80H“. owns? , mnacoowo . Sofia _ fiofiowdw , Gwcoflflvco . H 33305 swan—coo awoflhogo A . 3333mm Goflmowflu 03090me mcmnoxowfiu %«Tfimnm . :33 0 30 0.30.3.6 EDDUNKV noconfiuco 0 30m can mwon “033:3 muffin 55 The three specific cases give an overall view at the sludge handling scheme with regard to the major factors that could affect a choice of treatment, energy and money. 56 RESULTS Using the medium value for B. O.D. and 5.5. , the amount of raw primary sludge was estimated to be 1000 lb per million gallons of wastewater treated. Assuming a 5. 0% solids concentration, the volume of primary sludge that must be treated was found to be 2330 gallons per day (gpd). The amount of waste activated sludge produced per million gallons of wastewater treated was calculated to be 1068 lb. Assuming a solids concentration of O. 75 %, the volume of sludge was found to be 16, 578 gpd. Thus, the total volume of sludge produced per million gallons of wastewater is about 18,908 gallons. Using a specific gravity of 1. 03 and a solids concentration of the mixed primary and activated sludge of 1.27%, the amount of sludge solids generated is about 2530 ft3 per day. (See Appendix A for Calculations). 24 Table 20 shows the amount of raw primary, waste activated and total mixed sludge that has to be handled for the three design flows. TABLE 20 SLUDGE QUANTITIES Plant Size Primary Waste Act. Total Sludge (MGD) (GPD) (GPD) (MGD) (tons /day) 1 2,330 16,578 0.019 1.034 10 . 23,300 165,780 0.189 10.340 100 233,000 1,657,800 1.891 103.400 The volume of sludge determines the size of the unit process and the size determines the capital cost, capital energy, labor requirements and power needs. These four variables were determined for each stage in the sludge treatment process. Capital energy is the energy required for materials fabrication. From manufacturing data it was found that the average value of energy used in the production of one ton of finished steel is about 36 million (106) B. T.U. 30 It was also determined that one 94 pound bag of cement 57 requires about 175, 000 B. T.U. 's to produce.31 Using a water cement ratio of 0. 54 by volume and a concrete composition of 74 % aggregate, 3. 7% air, 9. 3% cement and 13 % water, yields an estimated require- ment of 2. 5 sacks of cement for each cubic yard of concrete. A cubic yard of concrete, therefore, requires about 437, 500 B. T.U. 's for production (See Appendix A). The first step of treatment is thickening using gravity thickeners (GT) and dissolved -air flotation thickeners (DAF). Table 21 shows the power, labor, capital cost and capital energy for both types of thickening. The calculations are shown in Appendix B. TABLE 21 THICKENING Plant Power Labor Cost Energy 6 Size (kwhAday)_ (hrZyr) (1000$) (BTUx 10 ) (MGD) GT DAF GT DAF GT DAF GT DAF 1 10.2 140 220 340 74 23 66 340*N/A** 10 20.4 1216 780 1100 194 257 230 1196*49** 100 40.8 9384 3600 5000 841 2567 1600 5868* 269** ‘1‘ if steel tanks are used; ** if concrete tanks are used N/A signifies that concrete tanks are not applicable here Table 21 shows that even though gravity thickening uses less energy during operations than the dissolved -air flotation machine, the capital energy required to construct the GT is about five times that of the DAF. The next step in the sludge handling process is stabilization. Anaerobic digestion (AND) and aerobic digestion (AD) stabilize the sludge to make it less offensive and reduce its volume. Table 22 shows the power, labor, capital cost, and capital energy for the two types of digestion. The calculations are shown in Appendix C. 58 TABLE 22 STABILIZATION Plant Power Labor Cost Energy 6 Size (kWh/day) (hr/yr) (10003) (BTU x 10 ) (MGDL AND AD AND AD AND AD AND AD 1 124 233 225 96 222 89 742 57 10 456 2685 1125 480 555 398 5418 390 100 1910 31930 5700 2420 4990 3315 45111 3014 Anaerobic digestion uses less operating power than aerobic digestion but costs more and requires more capital energy. After digestion the sludge can be conditioned before dewatering. Conditioning usually consists of chemical conditioning (CC) or heat treatment (HT) if there is a market for fertilizer. Table 23 presents the power, labor, capital costs, and capital energy for chemical condi- tioning and heat treatment. Chemical conditioning is cheaper, uses less operating energy and labor, and requires less capital energy than heat treatment but heat treatment allows for easier dewatering and provides a very useful end product for fertilizer, whereas chemical conditioning does not. See Appendix D for calculations. TABLE 23 CONDITIONING Plant Power Labor Cost Energy 6 Size (kwhfiay) (hr/yr) (x 1000$) BTU x 10 (MGD) CC HT CC HT CC HT CC HT 1 3 305 1040 520 46 203 29 45 10 80 3050 2600 1300 129 422 324 765 100 917 30500 4368 2190 256 2581 2394 4339 After conditioning the next step is dewatering. Dewatering reduces the volume of the sludge by reducing the water content. The major types of dewatering are drying beds (DB), vacuum filtration (VF), 59 centrifugation (CT) and pressure filtration (PF). Table 24 shows the comparison of the four types of dewatering with respect to the power and labor used in the Operation of equipment. TABLE 24 DEWATERING POWER AND LABOR Plant Size Power (kwyday) Labor (hr /yr) (MGD) DB VF CT PF DB VF CT PF 1 90 52 90 62 1750 1640 1370 2080 10 477 531 435 620 17500 5650 4200 5200 100 1551 5208 4400 6204 175000 35500 30000 26208 The power used for dewatering increases greatly as the flow increases except for drying beds which is lower due to the equipment used for removing the dried sludge. The labor requirements for drying beds at the 100. 0 MGD plant seem to be quite large. This is due to the use of one man per loader manhour. These values are based on operational data given for the specific equipment. Another comparison of the four dewatering techniques is shown in Table 25. Capital cost and capital energy are presented with respect to the design flows. TABLE 25 DEWATERING COSTS AND ENERGY Plant Costs (x 1000 $_) EnerguBTU x 10: (MGD) DB VF CT PF DB VF CT PF 1 91 211 422 183 307 180 86 79 10 829 475 844 366 350 510 288 137 100 11302 2638 2536 1468 2526 2727 1134 502 Pressure filters recently have become comparable in price with other dewatering techniques due to vast improvements in filter operations and size in the last few years. See Appendix E for calculations. The high capital costs for the drying beds is due to the large number of machines needed to unload the dried Sludge. 60 Dewatered sludge can be sent directly to disposal or it can be reduced in volume and weight by incineration (INC) or wet oxidation (WO). These two methods are the most common types of reduction used in sludge handling. Incineration produces a dry ash which can be sent to lagoons or to a landfill. Wet oxidation produces a wet ash slurry which usually goes to lagoons but can be used as a soil conditioner or fertilizer. Table 26 Shows the power, labor, capital cost and capital energy needed for the use of the reduction step. See Appendix F for the calculations . TABLE 26 REDUCTION Plant Power Labor Cost Energy Size (kWh/day) (hr[yr) (x 1000 $) (BTU x 106)_ (MGD) INC WO INC wo INC WO INC wo 1 603 610 1900 520 530 469 601 45 10 1242 6101 5400 1300 928 1408 2558 765 100 4932 61006 39000 2190 2880 6568 14350 4339 The labor requirements are unusually high for incineration because the dry ash cannot be pumped. Once the sludge is in the smallest volume feasible the sludge is deemed ready for "final disposal". The sludge can be used as a fer- tilizer and soil conditioner in a digested form (FERT), or sent to a sanitary landfill (LNF) as a dried cake or ash, or sent to permanent lagoons (LAG) in a Slurry or as a dried cake. All of these methods require capital costs and labor. Permanent lagoons do not use operating power or capital energy as defined in this report. Table 27 shows the power, labor, capital costs and capital energy requirements of the three basic methods of final disposal. The power involved in using the fertilizer and landfill method is due to the use of heavy equip- ment. Each process needs many machines to spread the sludge or to bury it. See Appendix G for calculations. The high labor requirements or final disposal are due to the large volume of sludge that has to be spread. The trucks with larger tanks can not be used because they bog down in the fields so more 61 MWme -1- ooowfi New coo comm oonw oovfi ooomom nfimwfi ovhwmm OOH mm: -11 com: mm: Owl CNN comm mmm oommm vhmm wmwfim OH Nwm 1: ow~ has mm mm owom m: omwm mom thN H rmZA 03 HMHM .mZA UNA HMMh .mZIH HMHM Noon on DHB Q 83 5 2 2: snmuocm umOU Hmfimmo Boned A=< Energy=1<>l< g3)_ (lb) (tons) (BTU x 106) 20.7 2605 1.30 46.8 65.4 8500 4.25 153.0 206.9 56100 28.05 1010.0 >I=fr om reference 3 6 6 based on 36 x 10 BTU's/ton Wall volumes (concrete) Dia. Depth Vol me of Wall* Energy'r’i‘ 6 (ft) (ft) (ft L (yd3) (BTleO ) 20.7 15 500 18.5 8.2 65.4 15 1553 57.5 25.2 206.9 15 4887 181.0 79.2 >:-'< Weight>1= Energyxok (ftz) Tanks (lb -ea) (ton) (B TU' s) 181 lat 2001162 18850 9.43 339.5x106 724 3 at 250 ftz 22150 33.23 1196.3 x 106 4308 10 at 450 ft2 32600 163. 0 5868.0 x 106 *from reference 36 ** based on 36 2:106 BTU's/ton - if concrete tanks are used; Tank Tank Tank No . Length Width Ar a of (ft) (ft) (ft ) Tanks 10 40 400 2 10 45 450 10 Volume of Concrete Walls* Floors“< Total Energyi 6 (£13) (ft3) ($13) (BTU's x 10 ) N/A 2364 676 112.6 49.3 12870 3750 615.6 269.3 *based on 12 in. support walls and 9 in. non-support walls and a depth of 10. 5 feet; five foot wet wall added ** based on a 9 in. slab thickness; five foot wet well add ed. #based on 437, 500 BTU's/yd3 88 Operating Power and Labor Plant size Powerrk Laborrzvz: (MGD) (kwhgday) (hrs/yr) 1 140. 0 340 10 1216. 0 1100 100 9384. 0 5000 >:i= Capital (MGD) Vol Cost Cost (ft3) (19 72) (19 75) 1 19,320 160,000 222,000 10 193,200 400,000 555,000 100 1,932,000 3,600,000 4,990,000 *from Fig. 9 Costs will double if a thickening digester is installed. Capital Energy Requirements Covers (steel)34 Plant Size Gov? Area Wt of* Capital Ener y** (MGD) (ft ) Covers (tons) (BTU's x 10 j 1 962 ea 16.8 ea =16.8 605 10 - 2376 ea 41.6 ea = 124.8 4493 100 9503 ea 166.3 ea = 997.8 35921 =:=based on 35 lb/ft2 of cover ** based on 36 x 106 BTU/ Ton Heaters (Steel)34 1. to raise temperature of incoming sludge BTU/hr =<2068 lb/day) (100) (95° - 68°) . Q4 hrs/day) (5 %) = 46, 530 per 106 gallons 2. to offset heating losses (assuming a well insulated covers and well insulated side walls no gas recirculation) 2600 BTU/HR/IOOO ft3 x 0.9 : 2340 where 0. 9 is the Michigan geographic correction factor. Plant Dig Heat for Heat for Total Size Vol Temp Losses Heat (MGD) (ft3) (BTU/111:) (BTU r (BTU/_hr) 1 19,320 46,530 45,208 91,738 10 193,200 465,300 452,088 917,388 100 1,932,000 4,653,000 4,520,880 9,173,880 Heater=i= Heater>¥= Size (BTU/hr) Weight(lbs) 140, 000 5, 600 1,000, 000 20,400 3 at 3,500,000 104,000 *from reference 34 92 Tanks (Concrete): Tank No. Tank Wall* Floor Total Dia of Depth Vol ea. Vol ea. V03 (ft) Tanks (ft) (£13) (ft3) (yd ) 35 1 22 1227 990 82 55 3 29. 6 2580 2445 558 110 6 36.4 6318 9764. 3574 *based on 12 inch thickness ** based on 12 inch thickness and l to 6 floor slope. Total Capital Energy: ' Plant Heaters>k Covers>i< 6 Tanks** 6 Total 6 Size (BTU x106) (BTU x 10 ) (BTU x 10 ) (BTU x10 ) (MGD 1 100.8 605 35.9 741.7 10 367.2 4493 558 5418.2 100 5616 35921 3574 54111.0 *based on 36 x 106 BTU/Ton of steel ** based on 43 7, 500 BTU's/yd3 of concrete QperatinLPower and Labor: Plant Size Power Labor (MGDL (KWH/da1)* (hr 55:24.4 1 ' 123.6 225 10 - 4 56. 4 11 25 100 1910. 0 5700 *from Table 6, methane gas will provide extra heater fuel. Methane Production: 1 ft3 of methane (at 70°F and 1 atm) has a net heating value of 960 BTU. Digester gas, 65% methane, has a heating value of 600 BTu/fl:3 63 ' Quantity of methane gas can be calculated"3 from C = 5.62 (ef - 1.42 %E )where C = ft3 of CH4/day e = efficiency of waste utilization F = BODL added, lb/day (See Appendix A) F = 2068 lb/day $3: 526 lb/day dx = net growth rate e = 0. 75 (average)63 d-f_ 5.62 [(0. 75) (2068 lb/day) — 1.42 (526 1b/day)] 4519 ft3 / 106 gallons treated. o H 93 Plant C 4 Heat Heat Size (ft /dzly) Value? Needed (MGD) (BTU/day) (BTU/c1211) 1 4519 4.4x 10" 2.2x106 10 45189 4.4x 107 2.2):107 100 451892 4.4x 108 2.2x 108 *based on 960 BTU/ft3 of CH4 *3“ due to heat losses and heat requirements Since gas produced is more than gas needed there will be no extra fuel needed. AEROBIC DIGESTION: As sumption: Current practice is to provide 15 days of detention time for waste activated sludge. More time required if primary sludge is involved. Use 20 days. 30 Hydraulic detention time = 18 to 22 days at 200C. Solids loading = 0.1 to 0.2 lb vss/ft3/day 02 requirements = 1. 6 to 1.9 lb BODS/lb destroyed Energy requirements for mixing: mechanical = 0. 5 to l. 0 hp/1000 ft air mixing = 20 to 30 SCFM/lOOO ft3 Solids = 644 ft3/day (See Anaerobic digestion) Volume of Digesters = (644 ft3/day) (20 days) = 12880 ft3 Air req'd = (25 SCFM/lOOO ft3) (12880 ft3) = 322 SCFM at 6. 5 psi estimated BHP = 12. 0 3 Size: Plant Dig. No. Tank Dimensions Size Vol of Depth Length Width Vol (MGD) (ft3) Tanks (ft) (ft) (ft) fig) 1 12880 1 10.7 60 20' ' 12960 10 128800 4 12.5 130 20' 130000 100 1288000 20 15.0 172 25' 1290000 No. Est* Plant Air (SCFM) Blowers (BHp) Wt. (lbs) 1 322 1 13 400 10 3220 1 150 2580 100 32200 4 1784 25200 *based on 1. 0 foot loss in diffusers, 30% loss in piping and an efficiency of 70 ‘70. 26 94 Cost: Plant Size Cost‘F Cost (MGD) (1972 35) (1975 $) 1 67,000 89,000 10 300,000 ' 398,000 100 2, 500,000 3,315,000 Capital Energy Requirements: Tanks (Concrete): Plant Dig. Walls* Fl or*>1< Total Size v61 (ft3) (ft ) (yd3) (MGD) (ft3) 1 12960 1830 1200 113 10 130000» 10780 10400 785 100 1290000 71973 86000 5851 *based on support walls 12 inches thick, non support walls 9 in. thick and 1. 5 feet freeboard ** based on 12 in. thick slab. Capital Energy: Plant Blower Tank Capital Energy Size Wt. Vol Steel* 6 Concrete** Totalé (MGD) (tons) (yd3) (BTU x 104 (BTU x 106) (BTU x 10 ) 1 0.20 113 7.2 49.4 56.6 10 1. 29 785 46.4 343.4 389. 8 100 ' 12.60 5851 453.6 2560.0 3013.6 =:=based on 36 x 106 BTU/ton of steel ** based on 43 7, 500 BTU/yd3 of concrete Operating Power and Labor: Plant Size Power=1< Labopzok (MGD) (kwhjdayL (hrs r 1 232. 7 96 10 2685. 0 480 100 31928. 0 2420 *based on estimated BHp of blowers and an Operating efficiency of 70% ** from Figure 8 95 ANNUAL COSTS - STEP 2 Power: Power (kWh/day) Costs ($ /Yr)* Size (MGD) .3111; AD AND .3._D_ 1 124 233 1358 2552 10 456 2685 4993 29400 100 1910 31930 20915 349634 *based on $ 0. 03/kwh Labor: Labor (hrs/yr) Costs ($/yr)* Size (MGD) AND AD AND ALP. l 225 96 1598 682 10 I 1125 ‘ 480 ' - 7988 3408 100 i 5700 2420 40470 17182 *based on $ 7.10/hr Capital Cost: Costs ($) Costs ($/yr)* Size (MGD) AND AD AND AD 1 222000 89000 22600 9065 10 555000 398000 56527 40536 100 4990000 3315000 508232 337633 *based on 8% over 20 years Capital Ene r gy; Capital Energy (BTU) Cost* ($ /Yr) Size (MGD) £1113 AD AND AD 1 7.4312108 5.7x 107 663 51 10 5.4 x109 3.9 x108 4834 349 100 4. 5 x 1010 3.0 x 109 40287 2686 *based on 35 0. 03/kwh and 3413 BTU/kwh and amortized at 8% over 20 years. ANNUAL COST OF CASES - STEP 2 Case 1 (Power Labor, Capital Cost): Size (M691 AND ($/yr1 AD (8 1n) 1 25567 12299 10 69508 73344 100 569617 704449 96 Case 2 (Capital Costs and Power): Size (MGD) AND (31/er 1 23969 10 61520 100 529147 Case 3 (Capital Energy and Power): Size (MGD) AND (gs/H) 1 2021 10 9827 100 , 61202 AI)($/Tr) 11617 69936 687267 AI>($/Tr) 2603 29749 352320 97 APPENDIX D C ONDITIONING CALCULATIONS CHEMICAL CONDITIONING As sumptions: Size: Plant Size 1 10 100 FeCl dosage 3 1. 5 to 2. 5 % for fresh solids l. 5 to 4. 0 % for digested Use 2. 0 % for design. Equipment will be bigger if digested sludge is used. Dewatering is the main step that uses chemical condi- tioning. Solids = 5 % influent Tanks must be lined with rubber. Contact time = 30 minutes If polyelectrolytes are used - feeders will be smaller (2068 1b/day) (2.0%) = 41.361b/day/106 gallons Feeders: Plant Sludge Chemicals=i< Chemicals Size ‘ (1b /day) (1b /day) (1b /min) (MGD) 1 2068 41. 4 0. 03 10 20680 413.6 0.29 100 206800 4136.0 2.87 *based on 2% feed. Mixing Tanks: Vol of Vol of Total Tank* Hp** Slud e Chemicals Vol Vol Required (MGD) (gal day) (gal/day) (gal/day) (gal) per hr 18908 378 19286 401.8 0.5 189080 3782 192862 4017.9 6. 0 1890800 37816 1928616 40179.2 40.0 *based on 30 min detention time. ** from reference 35 -- 0.25 hp for 250 gal tank. 0. 50 hp for 500 gal tank. 98 Cost: Plant Feed Feed Mixing* Cost (19 72$ )** Size Rate Volume Tank Vol Feeder Mixing (MGD) (lb/minL (gal) (gal) Cost Tank 1 ‘ 0.03 378 401.8 4500 30000 10 0.29 3782 4017.9 10000 52000 100 2.87 37816 40179.2 23000 170000 *based on 30 min detention time ** from references 4 and 35. Cost include purchased cost of equipment, motors, handling and setting, concrete, steel, electrical, instrumentation, insulation, paint and indirect costs. Cost Chemical Cost>i< (1975$) (1975 $Zyr) 45800 755. 6 79400 7548. 2 256000 75482.0 *based on 5¢/1b dry basis (East Lansing Sewage T. P.) Capital Energy Requirements: Plant Mixing Tanks* No. Capital** Size Vol Wt. of energy 6 (MGD) (gal) (lbs) Tanks (BTU x 10 ) 1 402 1600 1 at 500 28.8 10 4018 18000 12 at 350 324.0 100 40180 129600 81 at 500 2332.8 *from reference 35; stainless steel and includes feeder weight ** based on 36 x 10(3 BTU/ton of steel Operating Power and Labor: Plant Size Power* Labor==<>l= (MGD) (kWh/day) (hr 5 [yr) 1 2.7 1040 10 80.0 2600 100 895.0 4368 *based on Hp required for mixing in thr: 1 thr = 0. 7457 kwhr) and a 80% efficiency >:<>:< based on 0. 5 operators per shift (MAX)4 99 HEAT TREATMENT Assumptions: Pressure = 180 to 210 psig Residence time = 0. 5 hours Temperature = 3500 to 3900F Heat treatment is a wet oxidation process at lower pressures and temperatures. Therefore Size, construction requirements and operating labor are the same. (See Appendix F). Size: (Envirotech-Eimco): Plant Reactor:< No. of Vol. of Size Vol. Reactors Reactors (MGD) (gal) . 1 394 2 250 gal each 10 3939 1 4300 gal 100 39392' 5 8000 galeach *based on 30 minute detention time Cost: . Plant Loading Cost* Cost Size (lb/hr) (19 70 $) (1975 $) (MGD) 1 86. 2 130000 203300 10 861. 7 270000 422300 100 8616. 7 3 at 550000 2581000 *from Figure 24 Capital Energy Requirements: (due to reactor and its respective heat exchanger) Plant Reactor Reactor* Heater Ex. * Total Energy** Size Vol. Wt. Wt. Wt. 6 (MGD) (gal) (lbs) (lbs) (tons) (BTU x 10 ) 1 500 2500 N/A 1.3 45 10 4300 16700 25800 21.3 765 100 40000 141400 99700 120.6 4339.8 *from manufacturing data >:=>1< based on 36 x 106 BTU/ton of steel 100 Operating Power and Labor: Plant Size Power>i< Labor>1<>i< (MGD (kWh/day) (hrs (fir) l 305 520 10 3050 1300 100 30500 2190 *from reference 30; power includes electricity and fuel. Assumed to be half the power needed for wet oxidation. ** based on 0. 25 men per hour of operation. ANNUAL COSTS - STEP 3 Power: Size Power (kWh/day) Cost ($ /yr)* (MGD) CC HT CC HT 1 2. 7 305 30 3340 10 80 3050 876 33398 100 895 30500 9800 333975 *based on $ 0. 03/kwh Labor: Size Labor (hr/yr) Cost ($/hr)* (MGD) CC HT CC HT 1 1040 520 7384 3692 10 2600 1300 18460 9230 100 4368 2190 31013 15549 *based on $ 7.10/hr Capital Cost: Size Cost ($) Cost ($ /yr)* (MGD) CC HT CC ** HT 1 45800 203300 5420 20706 10 79400 422300 8087 43011 100 256000 2581000 101556 262876 *based on 8% over 20 years. ** includes chemical cost. 101 Capital Energy: Capital Energy Size (BTU x 106) (MGD) __c__c__ HT _C_§__ 1 29 45 . 26 10 324 765 290 100 2333 ' 4339 2089 *based on $0. 03/kwh and 2. 93 x 10- Annual Cost‘l< amortized at 8% over 20 years. ANNUAL COST OF CASES -STEP 3 Case 1 (Capital Cost, Power, Labor) Size (MGD) cc ($/er 1 12834 10 27423 100 142369 Case 2 (Capital Cost and Power) Size (MGD) cc (yyr) 1 5450 10 8963 100 111356 Case 3 (Capital Energy and Power) Size (MGD) cc ($/Yr) 1 56 10 1166 100 11889 _H_T_ 40 685 3885 4 kwh/BTU and HT ($114) 27738 85639 612399 Hfl?($j9r) 24046 76409 596850 EKF($19T) 3380 34083 337860 102 APPENDIX E DEWA TERING DRYING BEDS Assumptions: For mixed primary and waste activated digested sludge assume a loading of 15 lb/ftZ/year (Open Beds- Northern Climate) 30% solids concentration assumed 2068 lb sludge, for each 106 gallons treated (2068 lb/day) (365 days/year) = 754,820 1b/year (754, 8203/year) _ 2 _ (151b/ft—‘7year) " 50,321 ft _ 1.16 acres Plant Size Solids Be Area Acres (MGD) (1b (yr) (ft L 1 754820 50321 p 1.16 10 7548200 503210 11. 55 100 75482000 5032100 115. 52 Area can be reduced by using chemical conditioning or by using covered beds. _ Costs: Plant Size Area 2 Costs* Costs (MGD) (1000 ft ) (1971$) (1975$) 1 50.3 60000 90500 10 503. 2 550000 7 828800 100 5032.1 7500000 11302000 *from Figure 18 Costs include costs of normal excavation, piping for sludge distribution, sand and gravel drainage beds and underdrain collection piping. 9 103 Capital Energy Reguirements: — Beds The drying area is partitioned into individual beds, about 20 ft. wide by 20 to 100 feet long, of a convenient size so that one or two beds will be filled by a normal withdrawl of sludge from the digesters. The interior portions are usually two or three creosoted planks one on top of the other, to a height of 15 to 18 inches stretch- ing between slots in precast concrete posts. The outer boundaries may be of similar construction on earthern embankment for open beds, but concrete walls are required if the beds are to be covered.26 Plant Are? Length‘a" Total ' Concrete Vol. ** Size (ft ) - (ft) Length (ft3) (yd3) (MGD) 1 50321 224. 3 897 897 33. 2 10 503210 709.4 2837.5 2838 105.0 100 5032100 2243.2 8972.9 89 73 332.0 *beds assumed to be square for easy calculations ** volume of concrete was determined using a single wall 0. 5 feet thick and 2. 0 feet deep. 26 - Removal Requipment Dried sludge will be removed using front-end loaders. Plant Sludge* Loaders Req'd** Wt. of Loaders Size Vol. No. and Vol. (lbs) (tons) (M GD) (ft3 /d ayL 1 64.4 1 at 1.0 yd3 16200 8.1 10 644 1 at 1.5 yd3 16900 8.45 100 6440 3 at 5.0 yd3 132000 66.00 Operation (hrs/day) l. 5 8. 0 8. 0 *assuming 50% solids >:=>:< based on a 30 minute cycle or 16 loads per 8 hr day operating at 80 % efficiency (from Caterpillar handbook) 104 - Energy Plant Conc ete Steel Capital Energy (BTU x 106) Size (yd ) (tons) (Concrete)* Steel)** (Total) (MGD) . 1 33.2 8.10 15 292 307 10 105.0 8.45 46 - 304 350 100 332.0 66. 00 145 2376 2521 *based on 43 7, 500 BTU/yd3 of concrete ** based on 36 x 106 BTU/ton of steel. QperatingPower and Labor: Plant Size Power Labor 2) ' (MGD) (Hp -Hr/day)* (kwh/day)** (hrs (yr) 1 120 89. 5 1750 10 640 477. 3 17500 100 2080 1551.1 175000 *based on engine horsepower of the loaders operating at 16 loads/day and at 80 % efficiency. (from Cater- pillar Handbook). ** based on 1 hp-hr = 0. 7457 kwhr #based on 8 hours per machine used. VACUUM FIL TRATION As sumptions: Surface areas range from 50 to 300 ftz Yield = 4. 0 1b/ft2/hr for mixed primary and waste activated sludge. 2068 1b/day/106 gallons treated = 86.2 lb/hr (2068 1ll/day) (7 days/weekL _ . 2 (4 lb/ft‘fhrfl x hours7week) — filter area, ft Size: Plant Operation Solids Filter Ar ea* Size (hrs /wk) (lb/hr) (itZ) (MGD) , 1 40 362 90.5 (N/A)>:< 10 100 1447.6 361.9 (72.4)* 100 168 8617.7 2154.2 (430.8)* *if heat treatment is used for conditioning the filter yield may be about 20 lb/ftz/hr thus decrease the required filter area by 80 %. N/A - not good for flow g 3. O MGD 105 Costs: Plant Filter Area Cost? Cost Size 018) (1971$) (1975$) ‘ (MGD) 1 90.5 140000 211000 --- 10 362 315000 475000 (191000) 100 2154 1750000 2638000 (515000) *from Figure 14 Costs include the normal cost of the vacuum filters, auxiliary equipment, piping and structures. Capital EnergLEquir ements: Plant Filter Filteri'< Weight of Equipment * Size Area Drums Filter Accessories’ki‘EI‘otal (14(3)) (itZ) 190..and.Size (lbs) (lbs) (tong) 1 90.5 1 at 6' 7400 2500 4.95 10 362 1 at 12' 24300 4100 14.20 100 2154 5 at 14' 131000 20500 75. 75 *from reference 36 * =1< accessories include vacuum pump and filtrate pump. Capitalt 6 Energy (BTU x lQ_) 1.80 (---) (510 (180) 2727 (510) ‘ I #based on 36 x 106 BTU/ton of steel Operating Power and Labor: Plant Size Power* Labor=§<=l< (MGD) (kwlrjdayL (hrs(yr) 1 52 1640 10 531 (52) ‘ 5650 100 5208 (531) 35500 *from reference 20 ** from Figure 15 (will be more if sludge is hauled to landfill). 106 CENTRIFUGATION Assumptions: Feed solids = 2% Effluent solids = 15 to 40 % Length/Diameter ratio = 2.8 to 3. 2 Solids recovery = 80 to 95% Design was based on centrifuge performance presented by manufacturing data. Size: Plant Sludge Operation Feed Rate Size (gal/day) (hrs/week) (GPM) (MGD) 1 18908 40 55. 2 10 189080 ' 100 220.6 100 p890800 168 1313.‘ Cost: Plant Feed Rate Cost* Cost Size (GPM) (1972$) (1975$) (MGD) 1 55 280000 422000 10 221 560000 844000 100 1313 2000000 2536800 *from Figure 16 Costs include centrifuge equipment, sludge pumps and piping, sludge cake conveyors, equipment hoists, electrical facilities and enclosing structure. Capital Energy Requirements: Plant Feed No. Centrifuge Weight* Capita1=1< Size Rate of Each Total Energy6 (MGD) (GPM) Cent at GPM (lbs) (tonsL (Btu x 10 ) 1 55 lat 66 4800 2.4 86.4 10 221 lat 220 16000 8. 0 288 100 1313 9 at 150 7000 31. 5 1134 >i=from manufacturing shipping weights37 *2: based on 36 x 106 BTU/ton of steel 107 Operating Power and Labor: Plant Size Power’k (MGD) (kWh/day) 1 90 10 43 5 100 4400 *from Table 13 ** from Figure 17 PRESSURE FIL TER A s surnyations: 105 lb/it3 3. 0 ft3/chamber Cake Thickness = 1.5 inches Cake Length = 2. 0 hours Cake Solids = 50% results Cake Density 2 Cake Volume Labor** (hrs/yr) 1370 4200 30000 Loading 2 1.034 tons/day/lO6 gallons Ash Admixture Ratio = 1. 5 to 1. 0 Size: Plant Sludge Ash Total Moisturei‘ Size Load Load Solids Wt. (MGD) (lb/day) (lbzday) (lb/day) (lb/day) 1 2068 3102 5170 5170 10 20680 31020 51700 51700 100 206800 310200 517000 517000 *based on 50 % moisture Total Cake Cake** Wt. Vol. ab/aar) (831 10340 98. 5 103400 984. 8 1034000 9847.7 =kaased:<>'.< based on 36 x 106 btu/ton of steel Operating Power and Labor: Plant Size Power* Labo r>1= >:< (MGD) (kWh/day) (hr s /y£) 1 62. 0 2080 10 620. 4 5200 100 6204.0 26208 *based on 60 kwh/ton of sludge28 ** based on one man per hours of operation per filter28 ANNUAL COSTS - STEP 4 109 Size Power (kWh/day) (MGD) DB VF CT PF 1 89. 5 52 (-) 90 62 10 477.3 531(52) 435 620 100 1551 5208 (531) 4400 6204 Size Annual Cost* (MGD) DB VF CT PF 1 980 569 (-') 986 679 10 5226 5815 (569) 4763 6789 100 16984 57208 (5815) 48180 67934 *based on $ 0. 04/kwh Size Labor (hrs/year) (MGD) DB VF CT PF 1 1750 1640 13 70 2080 10 17500 5650 4200 5200 100 175000 35500 30000 26208 Size Annual Costs’l< (x 1000) (MGD) DB VF CT PF 1 12.4 11.6 9.7 14.8 '10 124.3 40.1 29.8 36.9 100 1242.5 252.1 213 186.1 *based on $ 7.10/hour Size Capital Cost (x 1000 $) (MGD) DB VF CT PF 1 90.5 211(-) 422 183 10 829 475 (191) 844 366 100 11302 2638 (515) 25361 1468 Size Annual Cost * (x 1000) (MGD) DB VF CT PF 1 9.22 21.5 43 18.6 10 84.4 48.4(19.5) 86 37.3 100 1151 268.7 (52.5) 258.3 149.5 ' *based on 8% over 20 years 110 Size Capital Energy (btu x 106) (MGD) DB VF CT PF 1 ” 307 180 (-) 86 79 10 350 510 (180) 288 137 100 2526 2727 (510) 1134 502 Size Annual Cost * ($ /year) (MGD) DB VF CT PF 1 274.9 161(-) 77 71 10 313 456.6(161) 258 122.7 100 2256 2441 (457) 1015 449 *based on $ 0. 03/kwh, 2.93 x 10'4 kwh/btu and amortized at 8% over 20 years. ANNUAL COSTS OF CASES - STEP 4 * Case 1 (Capital Cost, Power, Labor) Size Annual Cost ($/year) (MGD) DB VF CT PF 1 22600 33669 (-) 53686 34079 10 213926 94315 (60169) 120563 80989 100 2410484 577828 (310415) 519480 403534 *for calculations see Appendix C The cost figures in parenthesis are for vacuum filtration if used with heat treatment. Case 2 (Capital Cost, Power) Size Annual Cost ($ /year) (MGD) DB VF CT PF 1 10200 22069(-) '43986 19279 10 89626 54215(20069) 90763 44089 100 1167984 325728(58315) 306480 217434 Case 3 (Capital Energy, Power) Size Annual Cost ($ /year) (MGD) DB VF CT PF 1 1255 730 (-) 1063 750 10 5539 6272 (730) 5021 6912 100 19240 59269 (6272) 49195 68383 111 APPENDIX F REDUC TION INCINERATION Assumptions: Solids loading = 2 lb/ftZ/hr for mixed primary and activated Temperature 2 1400 to 1700 OF Heat Requirements 2 1800 to 2000 btu/lb of water Capacity 2 200 to 8000 1b/hr. Size: Plant Op. Solids Area* No. * Size (hrs /week) Load Req'd of (MGD) (lb/hr) (ftz) Hearths 1 40 362 181 9 10 100 1447. 6 724 8 100 168 8616. 7 43085 2 at 12 *based on 2 1b/hr/ft2 Costs: Plant Area Solids Co st* Cost Size (ftZ) (tons/day) (197235) (19 75$ ) (MGD l 181 1.03 400000 530000 10 724 10.34 700000 928000 100 4309 103.40 2500000 3315000 *from Figure 20 Capital Energy Requirements: Plant Area Weight of Incin. * Capital Energy=3==i= Size (ftz) (lbs) (tons) (btu's x 10 ) (MGD) 1 181 33485 16.7 601.2 10 724 131044 ' 65.5 2358.8 100 4309 797165 398.6 13450.0 *based on manufacturing data; about 185 lb per ft2 of hearth area (ENVIRO TECH) ‘112 Qpe ratinJgPowe r and Labo r: Plant Size Power>l= Labor* :1: (MGD) (kWh/day) (hrs/yr) 1 603 (268) 1900 . 10 1242 (667) 5400 100 4932 (1644) 39000 *from Figure 22 and) a power cost of $ 0. 015/kwh ** from Figure 21 values in parenthesis are for pressure filtration used with inc. Assuming 60% combustibles in medium quality sludge26 then the weight of ash is 48 % of the Sludge weight generated; assuming 100% combustion of all combustibles ash volume = .40 (2068 lb/day) : 8271b/day per million gallons treated. WET ~OXIDATION A s sumptions: Pressure 2 1000 to p750 psi Temperature = 2500 to 7000 F Residence Time = 20 to 60 minutes, 30 minutes average Plant Size Sludge Reactor* No. (MGD) Vol. Vol. of (gal/dayL (gal) Reactors 1 18908 394 2 at 250 gal 10 . 189080 3939 1 at 4300 gal 100 1890800 39392 5 at 8000 gal * based on 30 minute detention time Cost: Plant Size Optn. Loading Cost* Cost (MGD) (hrs/wk) (lb/111;) (197035) (1975$) l 40 362 300000 469000 10 100 1447. 6 900000 1408000 100 168 8616. 7 3 at 1400000 6568000 *from Figure 23 113 Capital Energy Reggirements: (due to reactor and heat exchanger) Plant Size Reactor Reactor* Heat Ex. * Total Energy** (MGDL (gals) wt (lbs) wt (lbs) wt (tons) (btu x 106) 1 500 2500 - N/A 1.3 45 10 4300 16700 25800 21. 3 765 100 40000 141400 99700 120. 6 4339. 8 *from manufacturing data (ENVIROTECH-EIMCO) ** based on 36 x 106 btu/ton of steel Operatingfower and Labor: Plant Size Power>1< Labo ring: (MGD) (kWh/daY) (hrs/yr) 1 610 520 10 6101 1300 100 61006 2190 *from Reference 30 ** based on 0. 25 manhours/shift of operation4 Wet oxidation combustion is about 80 to 90% complete.26 The amount of combustibles in medium sewage is about 60 %. Therefore, the weight of ash generated from each pound of sludge burned is (40 %)(2068 lb/day) This amounts to 973.2 1b/day 85% per million gallons treated. ANNUAL COSTS — STEP 5 Power: Power (kWh/day) Costs ($ /Year)* Size (MGD) INC WO INC WO 1 603 (268) 610 6603 (2935) 6680 10 1242 (667) 6101 13600 (7304) 66806 100 4932 (1644) 61006 54005 (18002) 668016 *based on $ 0. 03/kwh Labor: Labor (hrs/yr) Costs ($ /yr)* Size (MGD) INC WO INC WO 1 1900 520 13490 3692 10 5400 1300 38340 9230 100 39000 2190 276900 15549 *based on 3,5 7.10/hour 114 Capital Cost: Cost ($) ‘ Cost ($ /year) Size (MC-D) INC WO INC WO 1 530000 469000 53980 47768 10 928000 1408000 94517 143405 100 2880000 6568000 293328 668951 *based on 8% over 20 years. Capital Energy: Energy (btu x 106) Cost ($ /Year) Size (MGD) INC WO INC WO 1 601 45 538 40 10 2358 765 2111 685 100 14350 4339 12847 2885 *based on $0.03/kwh and 2. 93 x 10‘4 kwh/btu and amortized at 8% over 20 years. ANNUAL COSTS OF CASES - STEP 5 Case 1 (Power, Labor, Capital Costs) Size (MGD) ' Annual Cost ($ /yr) INC WO 1 74073 (70405) 58140 10 146457 (140161) 219441 100 624233 (588230) 1352516 Case 2 (Capital Costs and Power) Size (MGD) Annual Cost ($/Yr) INC WO 1 60583 (56915) 54448 10 108117(101821) 210211 100 347333 (311330) 1336967 Case 3 (Capital Energy and Power) Size (MGD) Annual Costs ($/Yr) INC WO 1 7141 (3473) 6720 10 15711 (9415) 67491 100 66852 (30849) 671901 115 APPENDIX G FINAL DISPOSAL FERTILIZER AND SOIL CONDITIONER: Assumgcions: Application 2 10 to 20 tons dry solids/acre/year Can be applied in cake or slurry. Must be digested or heat treated. Plant Size Solids Area=3= Vol. to be** (MGD) (tons/yr) (Acres) Spread(ga1@ay) 1 377.4 25. 2 4960 10 3774.1 251.6 49600 100 37741.0 2516.1 496000 *based on 15 tons/acre/year ** based on 5% solids concentration Costs: Costs will include costs of trucks to apply the sludge to the land. Cost of land is assumed to be free. Plant Size Vol. No. * of Tripsi< Capital** (MGD) (gal/day) Trucks per day Cost (8 1975) 1 4960 1 2. 5 22000 10 49 600 10 2. 5 220000 100 496000 100 2. 5 2200000 *based on 2100 gal capacity/truck and 2. 5 trips/day during one 8 hour working day at 80% efficiency. . ** based on $ 18, 000/truck and $4000/tank (from manu- facturer's data (Rhynard Truck Sales, Lansing, Mich.) 116 Capital Energy Requirements: (Due to weight of trucks) Plant Size No. of Wt. of* Capital Energy=i==f= (MGD) Trucks Trucks (tons) (btu's x 106) 1 1 5 . 180 10 10 50 1800 100 100 500 18000 *based on truck weight of 10, 000 lbs (from Rhynard Truck Sales, Lansing, Michigan). >:<* based on 36 x 106 btu/ton of steel. Operating Power and Labor: Plant Size Power Labori (MGD) (Hp -Hr)=:< (kwh/day)** (hrs /75L 1 2933 2187 2920 10 29333 21874 29200 100 293333 218740 292000 *based on 220 Hp per truck operating 8 hrs a day at an average efficiency of 60%. ** based on 1 Hp -Hr = 0. 7457 kwhr. #based on 8 hours per day. This size of truck was chosen because bigger trucks tend to bog down. (Rhynard Truck Sales) LAGOONING As 8 umptions: Depth = 5 feet At least two lagoons must be provided Solids loading = (MAX) 2.2 to 2.4 lb/yr/ft3 use 2.2 lb/year/cu. ft. Lagoons will be permanent lagoons (assumed) Size: Plant Vol. of Lagoon’k Lagoon** Size Sludge Vol. Area Area (MGD) (lb/yr) (131:3) (ftz) (Acres) 1 754820 343100 68620 1.58(0.63)t 10 7548200 3431000 686200 15. 75 (6.3) 100 75482000 34310000 6862000 157. 53 (63. 0) *based on solids loading of 2. 2 lb/year/ft3 ** based on 5. 0 foot depth #if a reduction method is used. Costs: Plant Lagoon 3 Cost* Cost ) (MGD) Vol. (1000 ft ) (1971$) (1975$) l ' 343.1 25000 36700 (14000)** 10 3431.0 95000 139400 (50000) 100 34310.0 450000 660300 (220200) *from Figure 11. Costs include normal excavation, dike construction and piping. ** if reduction step is used. Capital Energy Requirements: The building of the permanent lagoons require no cement or steel and also requires no equipment to remove any sludge. Even though there is no steel, concrete or brickused in the construction of the landfills there is still a considerable amount of energy used to construct the landfill. This energy was ignored to satisfy the definition of capital energy used here. Operating Power and Labor: Power is almost non-existant except for lighting and pumps. The lagoon itself doesn't use any power. Plant Size Power Labor=i= (MGD) Req'mts. Req'd. (kWh/day) (hrs/yr) 1 N/A 115 (95) 10 N/A 235 (160) 100 N/A 1400 (550) :10: *from Figure 12 ** if a reduction step is used. SA NI TARY LAND FILL Assumptions: Dried sludge or ash can be applied 2. 0 foot layers daily 6. 0 inches daily cover Working face 2 20 to 300 Operation time is usually an 8 hour day. 118 Landfill Equipment Plant Size Sludge Wt. * Shift Sludge Equipment>3<>3< (MGD) (tons/day) (hrs/wk) (tong/8 hr) Needed 1 4.14 (0.42)# 40 5.8 (0.6) 1 crawler dozer 10 41.36 (4.14) 100 23.2 (2.3) 2 crawler dozer 100 413.60 (41.35) 168 137.9 (13.8) 3 rubber tire 1dr *based on dewater sludge at 25% solids ** from Reference 69 ( ) values are if a reduction step is used Plant Equipment Flywheel>i< Machine=¥< Size Descrip. Hp Wt. (lbs) (MGD) 1 1x crawler dozer 80 (-) 19, 000 (~) 10 2 x crawler dozer 95 (80) 32, 000 (19000) 100 3 x rubber tired loader 160 (95) 29,400 (32000) *from Reference 69. ( -) means it is two small to use Plant Sludge Capital* Cost Size Wt. Cost (19 75$) (MGD) (tondeay) (19 72$) 1 4.14 (.42) 35000 46500 (-) 10 41.36 (4.14) 150000 199000 (46500) 100 413.60 (41.4) 650000 862000 (199000) *includes cost of equipment from Figure 26, if incineration is used their costs will decrease Capital Energy Requirements: No capital energy is used to construct the landfill since it is often made of earthen walls or just a hole in the ground. Plant Size Equipment Weight Capital Energy* (MGD) (lbs) (tons) (btu x 106) 1 19000 9. 5 342 (-) 10 64000 32 1152 (342) 100 88200 44.1 1587.6 (576) *based on 36 x 106 btu/ton of steel ( ) values are if a reduction step is used. 119 Operating Power and Labor: Plant Size Power Labor** (MGD) (hpheray)>3= (kWh/day) (hrs /year) 1 762 568(-) 2080(-) 10 4524 3374 (568) 5200 (2080) 100 19200 14317 (1687) 8760 (5200) *based on engine horsepower and an average efficiency of 60 % ** based on 1 man per machine for 8 hours. ANNUAL COSTS - STEP 6 Power: Size Power (kWh/day) (hKHn FERT LAka LNF 1 2187 lfl/A. 568(568) 10 21874 hoax 3374(568) 100 218740 lv/A. 14317(1687) Annual Cost* FERT - LAG LNF 23950 ——— 6220(-) 239520 -—- 36945(6220) 2395203 --- 156771(18473) *based on $0. 03/kwh >703 due to permanent lagoons Labor: Size Labor (hrs/year) (MGD) FERT LAG LNF 1 2920 115 (95) 2080 (2080) 10 29200 235 (160) 5200 (2080) 100 292000 1400 (550) 8760 (5200) Annual Cost* FERT LAG LNF 20732 817 (675) 14768 (-) 207320 1669 (1136) 36920 (14768) 2073200 9940 (3905) 62196 (36920) *based on 35 7.10/hour. ( ) if a reduction step is used. 120 Capital Cost: Size Cost (x 1000 $) (IMGD) FERT LAG LNF l 22 36. 7 46. 5 (—) 10 220 139.4 199.0 (46.5) 100 2200 660.3 362. 0 (199.0) Annual Cost* FERT LAG LNF 2241 3738 (1426) 4736 (-) 22407 14198 (5093) 20268 (4736) 224070 67252 (22427) 87795 (20268) *amortized at 8% over 20 years. ( C apital Ene r gy: ) values are if a reduction step is used. Size Energy (btu x 106) (MGD) FERT LAG LNF 1 180 --- 342 (342) 10 1800 --- 1152 (342) 100 18000 --- 1588 (576) Annual Cost * FERT LAG LNF 161 --- 306(-) 1612 --- 1031 (306) 16115 —-— 1422(516) *based on 2.93 x 10‘4 kwh/btu, $ 0. at 8% over 20 years. ANNUAL COST OF CASES - STEP 6 Case 1 (Capital Costs, Power, Labor) 03/kwh and amortized Size Annual Costs (MGD) FERT LAG LNF 1 46923 4555 (2101) 25724 (-) 10 469247 15867 (6229) 94133 (2572-1) 100 4692473 77192 (26332) 306592 (75661) 121 Case 2 (Capital Costs and Power) Size Annual Costs (MGD) FERT LAG LNF 1 26191 3738 (1426) 10956 (-) 10 261927 14198 (5093) ' 57213 (10956) 100 2619273 67252 (22427) 244566 (38741) Case 3 (Capital Energy, Power) Size Annual Costs (MGD) FERT LAG LNF 1 24111 --- 6526 10 241132 --— 37976 (6526) 100 2411318 --— 158193 (18989) Values in parenthesis are for use with a reduction step. 122 REFERENCES CITED 10. ll. 12. 13. 14. 15. 123 REFERENCES CITED Sludge Incineration and Fuel Conservation, N. E.R. C. , U.S. E.P.A., May 3, 1974. Barnard, J. and Eckenfelder, W.W., Jr., "Inter—relationships in Sludge Separations", in Water Qualitylmprovements by Physical and Chemical Processes III, Gloynda and Ecken- felder, P. 109, University of Texas Press, 1970. Burd, R.A. , A Study of Sludge Handling and Disposal, U.S. Department of the Interior Publication WP-20-4, May, 1968. Blecker, H.G. , and Nichols, T.M. , Capital and Operating Costs of Pollution Control Equipment Modules - Volume II - Data Manualz EPA-R5-73 -0236, 1972. Process Design Manual for Sludge Treatment and Disposal, E.P.A. Technology Transfer, EPA625/1-74-006, 1974. Electrical Power Consumption for Municipal Wastewater Treatment, U.S. E.P.A., EPA-R2-73 -281, July, 1973. Estimating Staffing for Municipal Wastewater Treatment Facilities, U.S. E.P.A., EPA68-01-0328, March, 1973. Process Des_ign Manual for Upgrading_Existing Wastewater Treatment Plants, E.P.A. Technology Transfer, October, 1974. Ritter, E. L. , "Design and Operating Experiences Using Diffused Aeration of Sludge Digestion", Journal of the Water Pollution Control Association, V. 42, October, 1970, p. 1782. Dorr-Oliver, Inc. , Cost of Wastewater Treatment Processes, U.S. Department of the Interior, TWRC - 6, December, 1968. Patterson, W.L. and Banker, R.F. , EstimatingCosts and Man- ppwer Requirements for Conventional Wastewater Treatment Facilities, EPA 17090 DAN 10/71, October, 1971. Nickerson, G.L. , et. a1. , "Chemical Addition to Trickling Filter Plants", Journal of the Water Pollution Control Federation, V. 46, January, 1974, p. 133. Doe, P.W., et. al., "Sludge Concentration by Freezing", Water and Sewage Works, V. 112, 1965, p. 401. "Review of Sludge Disposal Practices", Journal of the American Wastewater Association, V. 61, May, 1969, p. 225. Akers, D.J., and Moss, E.A. , Dewateringof Mine Drainage 51.11ng, U.S. E.P.A., EPA R2-73‘169, 19730 16. l7. 18. 19. 20. 21. 22.. 23. 24. 25. 26. 27. 28. 29. 30. 31. 32. 33. 124 Swets, D.H., Pratt, L., and Metcalf, C.C. , "Thermal Sludge Conditioning in Kalamazoo, Michigan", Journal of the Water Pollution Control Federation, V. 46, March, 1974, p. 575. Sherwood, R.J. , and Dahlstrom, D.A. , "Economic Costs of Dewatering Sewage Sludges by Continuous Vacuum Filtration", American Institute of Chemical Engineers Symposium Series, V. 129, no. 69, 1973, p. 192. White, William F. , "Fifteen Years of Experience Dewatering Municipal Wastes with Continuous Centrifuges", A.I. Ch. E. Symposium Series, V. 129, no. 69, 1973, p. 211. Dorr-Oliver, Manufacturing Data, 1968. Clark, John; Veissman, Warren; and Hammer, Mark, Water Supply and Pollution Control, 2d. ed. , International Textbook Co., 1971. pp. 566-594. State of the Art Review of Sludge Incinceration Practice, Depart- ment of the Interior, FWQA, 1707ODIV 04/70. Dotson, G.K.; Dean, R. B.; and Stern, G. , "Cost of Dewatering and Disposing of Sludge on the Land", A. I. Ch.E. Symposium Series, V. 129, no. 69, 1973. p. 217. "Sludge Dewatering", Manual of Practice No. 20, Water Pollution Control Federation, 1969. Vesilind, P. Aarne, Treatment and Disposal of Wastewater Sludges, Ann Arbor Science, 1974. Goodman, Brian L. , Design Handbook of Wastewater Systems: Domestic, Industrial, Commercial, Technomic Publishing Co. , 19 71. Metcalf and Eddy, Inc. , Wastewater Engineering, McGraw-Hill Book Co. , 1972. "Current Labor Statistics", Monthly Labor Preview, V. 98, March, 1975, p. 100. Forster, Hans W. "Sludge Dewatering by Pressure Filtration", A.I.Ch.E. Symposium Series, V. 129, no. 69, 1973, p. 204. Aguilar, Rodolpho, Systems Analysis and Design, Prentice -Hall, Inc., 1973. Personal communiques with Inland Steel Co. , Republic Steel Co. , and Bethlehem Steel Co. Personal communiques with Huron Cement Co. , Peerless Cement Co. , and Dundee Cement Co. Trovell, G. E.; Davis, H. E.; and Kelly, J. W. , Composition and Properties of Concrete, McGraw-Hill Book Co. , 1968. Hillier, Frederick S. and Lieberman, Gerald J. , Introduction to Operations Research, Holden-Day, Inc., 1974. 34. 35. 36. 37. 38. 39. 125 "PFT Water Quality Control Equipment", Envirex, Inc. , Manu- facturing data binder No. 340. Wallace and Tiernan, "Dry Flow Feeders and Meters", Division of Penwalt Corp. , Manufacturing catalog. "REX Water Quality Control Equipment", Envirex, Inc. , Manu- facturing data binder No. 315, Vol. 2. Dorr-Oliver Inc. ,"Bulletin No. 2650 C", Manufacturing catalog. Dorr-Oliver Inc. , "Bulletin No. 7400", Manufacturing catalog. Brunner, D.R. , and Keller, D.J. , Sanitary Landfill Design and Operation, U.S. E.P.A., 1972. 11'... "I11111111111111.1111“