RELIABILITY-BASED OPTIMIZATION OF DISTRIBUTION SYSTEM PROTECTION By Yuting Tian A THESIS Submitted to Michigan State University in partial fulfillment of the requirements for the degree of Electrical Engineering - Master of Science 2014 ABSTRACT RELIABILITY-BASED OPTIMIZATION OF DISTRIBUTION SYSTEM PROTECTION By Yuting Tian The power system is one of the most complex systems in existence. In any complex system, it is impossible to avoid abnormal operations. In order to reduce the impact of abnormal operations and to restore the system more quickly to normal states, many control and protection mechanisms are established. Protection systems consist of sensing and isolation devices that operate in the event of a fault to disconnect the part of the power system that is affected by the fault. However, malfunctions can also occur within the protection system. Therefore, one objective of this thesis is to develop approaches for analyzing and modeling the reliability of power systems when the malfunctions of protection systems are considered. A methodology of evaluating reliability of distribution systems are presented. This method uses matrices to represent the relationship of devices in distribution systems and loads. Reliability indices such as SAIFI and SAIDI of the distribution system of RBTS bus 2 are calculated using the proposed methodology. Since power utilities are aim to provide reliable electric power with low cost to customers, the investment of protective devices need to be taken into consideration. In this thesis, an optimization problem is presented. The objective in this optimization problem is the cost of disconnects and the constraint is the reliability indice, SAIDI. This reliability-based optimization problem is solved for RBTS distribution system by Genetic Algorithm (GA). Dedicated to: My parents, Lifeng Tian and Jing Huang iv ACKNOWLEGEMENTS I would like to thank my committee chair, Dr. Joydeep Mitra, for his guidance and support. Without his help, I may not able to finish my master’s thesis. I would also like to thank my committee members, Dr. Fang Z. Peng and Dr. Lixin Dong for their time, comments and support. Thanks also go to my friends and colleagues in ERISE lab, Dr. Niannian Cai, Ms. Nga Nguyen, Mr. Mohammed Benidris, Mr. Samer Sulaeman, Mr. Salem Elsaiahs and Mr. Valdama Johnsonthe. I would also thank all the faculty and staff of Michigan State University. Finally, I want to express thanks to my parents for their love, care, understanding and support. v TABLE OF CONTENTS LIST OF TABLES.....................................................................................................................vii LIST OF FIGURES..................................................................................................................viii CHAPTER 1 INTRODUCTION............................................................................................. 1 1.1 Introduction..............................................................................................................................1 1.2 Research Objectives.................................................................................................................2 1.3 Outline of Thesis......................................................................................................................4 CHAPTER 2 RELIABILITY EVALUATION OF DISTRIBUTION SYSTEM................6 2.1 Overview of Distribution System............................................................................................ 6 2.2 Previous Work......................................................................................................................... 7 2.3 Reliability Indices for Distribution System............................................................................. 8 CHAPTER 3 RELIABILITY EVALUATION OF DISTRIBUTION SYSTEM CONSIDERING PROTECTION FAILURES........................................................................10 3.1 Methodology for the Distribution System Reliability Evaluation......................................... 10 3.2 Case Study............................................................................................................................. 12 3.2.1 Case 1................................................................................................................................14 3.2.2 Case 2................................................................................................................................16 3.2.3 Case 3................................................................................................................................19 3.2.4 Case 4................................................................................................................................21 3.2.5 Case 5................................................................................................................................24 3.2.6 Case 6................................................................................................................................26 3.3 Reliability Evaluation for RBTS Busbar 2............................................................................ 28 CHAPTER 4 OPTIMIZE ALLOCATION OF DISCONNECTS BY GENETIC ALGORITHM............................................................................................................................37 4.1 Introduction............................................................................................................................37 4.2 Methodology.......................................................................................................................... 39 4.2.1 Coding...............................................................................................................................42 4.2.2 Fitness............................................................................................................................... 42 4.2.3 Reproduction.....................................................................................................................44 4.2.4 Crossover.......................................................................................................................... 44 4.2.5 Mutation............................................................................................................................45 4.3 Case Study............................................................................................................................. 45 4.3.1 Case 1................................................................................................................................45 4.3.2 Case 2................................................................................................................................49 CHAPTER 5 CONCLUSION................................................................................................51 5.1 Summary................................................................................................................................ 51 5.2 Future Work........................................................................................................................... 52 iii BIBLIOGRAPHY...................................................................................................................... 54 iv LIST OF TABLES Table 3.1 Data of Transformer..................................................................................................13 Table 3.2 Data of Lines.............................................................................................................13 Table 3.3 Number of Customers Connected to Each Load...................................................... 13 Table 3.4 Feeder Type and Length........................................................................................... 28 Table 3.5 Customer Data.......................................................................................................... 29 Table 3.6 Loading Data.............................................................................................................29 Table 3.7 Reliability and System Data..................................................................................... 30 Table 3.8 Summary of Six Cases..............................................................................................32 Table 3.9 Result for Case 1.......................................................................................................32 Table 3.10 Result for Case 2.....................................................................................................33 Table 3.11 Result for Case 3.....................................................................................................33 Table 3.12 Result for Case 4.....................................................................................................34 Table 3.13 Result for Case 5.....................................................................................................34 Table 3.14 Result for Case 6.....................................................................................................35 Table 3.15 Comparison of Six Cases Results........................................................................... 35 Table 4.1 Optimum Solution for Case 1................................................................................... 47 Table 4.2 System Data for RBTS............................................................................................. 49 Table 4.3 Optimum Solution for Case 2................................................................................... 50 v LIST OF FIGURES Figure 3.1 Diagram for Basic Case...........................................................................................14 Figure 3.2 Diagram for Case 2..................................................................................................17 Figure 3.3 Diagram for Case 3..................................................................................................20 Figure 3.4 Diagram for Case 4..................................................................................................22 Figure 3.5 Diagram for Case 5..................................................................................................24 Figure 3.6 Distribution System of RBTS Busbar 2.................................................................. 31 Figure 4.1 Cost as a Function of Reliability............................................................................. 38 Figure 4.2 Flowchart.................................................................................................................48 vi CHAPTER 1 INTRODUCTION 1.1 Introduction The primary objective of the power grid is to provide reliable and economic electrical energy to customers. However, the power system is one of the most complex systems in existence and it is impossible to avoid abnormal operations in any complex system. Abnormal operation is usually caused by system disturbances, which is defined as an undesired variable applied to a system that tends to affect adversely the value of a controlled variable [1].The most common disturbances in power systems are lightning, faults, large changes in load and failure of equipment due to weather, fatigue, etc. In order to reduce the impact of abnormal operation and to restore the system to normal status more quickly, many control and protection mechanisms are established. Protection of power system is an extremely important aspect as the quality and scheme of the protection decides system reliability, controllability and stability [2]. The performance of protection systems affects the whole power system in many ways, including electrical facilities and customers. Hence, there are always ongoing efforts toward improving the performance of protection systems and the links between protection systems and power systems. The electric power system is one of the largest and most complicated systems in the world, and consists of a generation part, a transmission part and a distribution part. The research reported in 1 this thesis deals with protection issues encountered in distribution systems. The distribution system is the portion of power systems which delivers electric energy from the transmission system to the customer. The distribution system extends downstream from the distribution substation to the customer meter. Often the initial overcurrent protection and voltage regulators are within the substation fence and are considered to be part of the distribution system [3]. 1.2 Research Objectives The reliability of an electric power system is defined as the probability that the power system will perform the function of delivering electric energy to customers on a continuous basis and with acceptable service quality [4]. This character shows how well a system is performing its intended function. There are several reliability indices that quantify different aspects of distribution service interruptions, and some of the most commonly used indices are System Average Interruption Frequency Index (SAIFI), System Average Interruption Duration Index (SAIDI), Customer Average Interruption Duration Index (CAIDI), Customer Total Average Interruption Duration Index (CTAIADI), and Customer Average Interruption Frequency Index (CAIFI). These indices will be introduced in chapter two in detail. These indices help to evaluate the customer satisfaction by representing the number of momentary and sustained interruptions, duration of interruptions and number of customers interrupted. The significance of conducting research of system reliability also plays roles in improving system performance. Besides, they provide a basis for new or expanded system planning and maintenance scheduling, as well as resource allocation. 2 It has been observed that protection system hidden failures commonly lead to multiple or cascading outages, which consequently can cause large-scale power system blackouts [5]. The protection system contains many protection devices, such as relays, breakers, fuses and disconnects. Each component could fail to operate, which may lead to the failure of protection systems and this would endanger the power grid in step. Thus, it is necessary to take the the likelihood of protection failure into consideration when evaluating the reliability of the distribution system. Assessment of system performance is a valuable procedure for three important reasons. First of all, it establishes the chronological changes in system performance and therefore helps to identify weak areas and the need for reinforcement. Secondly, it establishes existing indices which serve as a guide for acceptable values in future reliability assessments. Finally, it enables previous predictions to be compared with actual operating experiences [6]. Therefore, as operating conditions and technologies evolve in distribution systems, it is important to develop improved and more sophisticated models and methods for reliability evaluation of these systems. One of the objective of this thesis is to develop an improved model and method for distribution system reliability that takes into account the role of protective devices. The fundamental goal of an electric utility has always been to serve its customers with a reliable and low cost power supply [7]. It is apparent that more the protective devices are installed in the system, less the interruption duration is of the customer. However, the investment cost of utility will be more with the increase of the number of protective devices. Therefore, an optimization problem need to be solved to find the optimum number and placement for protective devices. 3 This is the second objective of this thesis. The objective function is the total cost of protective devices, and reliability indice should be taken into consideration as a constraint. Genetic Algorithm is applied in this thesis to solve the optimization problem, the detail is presented in chapter four. 1.3 Outline of Thesis The contents of this thesis are organized into five chapters. Following the chapter on introduction, chapter two gives a brief overview of the distribution system. Also, the main indices to be used in this research for assessing the reliability of the distribution system have been discussed. Chapter three proposes a methodology based on relation matrix to evaluate the reliability indices of distribution systems. Six cases are used to illustrate the method in detail. The variables in these cases are fuse, disconnect, alternative supply and fuse failure. The system reliability and individual load point reliability for six cases of the RBTS bus 2 distribution system are evaluated by the methodology proposed in this thesis. Chapter four presents a reliability-based optimization problem. This chapter proposes a methodology of using Genetic Algorithm to solve the reliability-related optimization problem. The optimum number and placement of disconnects are found for both the IEEE-RBTS bus 2 system and the whole RBTS system. 4 Chapter five is a summary of the whole thesis. It discusses the work that has been done and makes suggestions for future research. 5 CHAPTER 2 RELIABILITY EVALUATION OF DISTRIBUTION SYSTEM 2.1 Overview of Distribution System Generally, an electric power system includes a generating, a transmission, and a distribution system. The distribution system is the portion of power systems which delivers electric energy from the transmission system to the customer. The distribution system extends downstream from the distribution substation to the customer meter. Distribution lines are different from transmission and subtransmission lines in that (1) they operate at lower voltages than transmission lines, (2) they are usually radial, and (3) they usually have loads tapped all along the line, not just at the terminals [8]. In the past, distribution system received less attention than the other part of electric power system when considering reliability. The main reason for this are that generating stations are individually very capital intensive and that generation inadequacy can have widespread catastrophic consequences for both society and its environment [6]. However, in 1977, [9] presented that analysis of the customer failure statistics of most utilities shows that the distribution system makes the greatest contribution to the unavailability of supply of customer. What’s more, in book [10], the author states that the distribution systems account for up to 90% of all customer reliability problems. Therefore, it is essential to conduct research about reliability evaluation of distribution systems. 6 2.2 Previous Work After decades of effort in study of reliability of distribution systems, several methods have been applied to this area. Basically, these methods can be divided into two parts, analytical methods and simulation methods. Analytical methods are those that use system topology along with mathematical expressions to calculate reliability indices, which include Markov modeling, network reduction, fault tree analysis and cut-set analysis. Network reduction is useful for systems consisting of series and parallel subsystems. This is a method that uses series-parallel combinations to reduce network and then to determine load point indices and aggregate them to calculate the system wide indices. When using fault tree analysis, the components that cause interruptions to load, for each one should be determined first. Then the load point indices need to be combined to get the system indices. As for the cut set method, it can be applied to systems with simple as well as complex configurations and it is a very suitable technique for the reliability analysis of power distribution system [11]. The first step is to determine the first and second order minimal cut-sets that cause outages at each load point, then we can evaluate the reliability indices. When a system can be described by a set of discrete states, and the probability of moving to a new state is only dependent upon the current state, the system can be described by a Markov model [12]. Since protective devices and most components in power systems are repairable, Markov modeling shows its advantage in evaluating the reliability of protective systems. However, since distribution systems contain a large number of states, many simplifying assumptions must be made to limit the Markov model to a manageable size [12]. 7 Monte Carlo simulation is a way of simulating the conditions on the system by generating system states of failure and repair randomly to compute the reliability indices. One advantage of the simulation method is that this method is not restricted by the large size of the power grid. Two types of simulation methods are often used: sequential Monte Carlo simulation and non-sequential Monte Carlo simulation. The former one simulates the system operation by generating an artificial history of failure and repair events in time sequence. The later type evaluates the system’s response to a set of events and its order has no influence. When evaluate the reliability of distribution system, the performance of protection system should be taken into consideration. Hidden failures in the protection system are a main issue that affects the reliability of the distribution system and decreases the satisfaction of customers. A large amount of studies on reliability evaluation considering protection failures are conducted by researchers [12-16]. 2.3 Reliability Indices for Distribution System System availability, estimated unsupplied energy, number of incidents and number of hours of interruption are aspects that should be taken into consideration when evaluating the reliability of the power grid. Reference [3] presents a set of terms and definitions which can be used to foster uniformity in the development of distribution systems and several reliability indices are defined, which are listed below. The system average interruption frequency index (SAIFI) is defined as, SAIFI=  Total Number of Customers Interrupted Total Number of Customers Served 8 (2.8) This index indicates the average frequency of a sustained interruption that the customer experiences. Sustained interruptions are those interruptions that last more than five minutes. SAIDI refers to System Average Interruption Duration Index, which indicates the total duration of interruptions for the average customer, and it is defined as, SAIDI=  Customer Minutes of Interruption Total Number of Customers Served (2.9) CAIDI is Customer Average Interruption Duration Index, which indicates the average time required to restore service, which is determined by, CAIDI=  Customer Minutes of Interruption Total Number of Customers Interrupted (2.10) This index could also be calculated as below, CAIDI= SAIDI SAIFI (2.11) CAIFI is the Customer Average Interruption Frequency Index, which represents the average frequency of sustained interruptions for those customers experiencing sustained interruptions. The equation is given below, CAIFI=  Total Number of Customer Interruptions Total Number of Distinct Customers Interrupted (2.12) One thing that needs to be noticed is that the customer interrupted is counted once, regardless of the the number of interruptions for this customer. 9 CHAPTER 3 RELIABILITY EVALUATION OF DISTRIBUTION SYSTEM CONSIDERING PROTECTION FAILURES 3.1 Methodology for the Distribution System Reliability Evaluation Distribution lines are different from transmission and subtransmission lines. Distribution lines have characteristics such as lower voltage, radial and load tapped all along the line. If we assume there are l lines, m transformers and n loads in a distribution system. We can use a matrix RL to represent the relationship between loads and lines, the size of RL is n  l , and use RT to represent the relationship between loads and transformers, the size of RT is n  m . If load i will be affected by line j , then RL (ij )  1 . If the fault on line j will not interrupt load i , RL (ij )  0 . Similarly, if load i will be affected by transformer j , then RT (ij )  1 , otherwise, RT (ij )  0 . These could be represented as follows, 1, if load i will be affected by line j 1  i  n RL (i, j )   , 1 j  l 0, otherwise 10 (3.1) 1, if load i will be affected by transformer j 1  i  n RT (i, j )   , 1 j  m 0, otherwise (3.2) In this methodology, we use L to represent the failure rate of distribution lines. L is a 1  l vector and L (i ) is the failure rate of line i , 1  i  l . I L and U L are used to represent the number of interruptions and interruption duration of each load caused by distribution lines, respectively. The size of I L is n  1 and the size of U L is n  l . The element of I L and U L can be calculated as below, I L (i )  RL (i )LT (3.3) U L (i, j )  tRL (i, j )L (1, j ) (3.4) where t is the recovery time of load, which could be the fault clearing time or the isolation and switching time. The value of t depends on situations, the detail will be illustrated later by six cases in section 3.2. Similarly, we use T to represent the failure rate of transformers. I T and U T represent the number of interruptions and interruption duration of each load caused by transformers, respectively. The size of I T is n  1 and the size of U T is n  m . I T and U T are calculated as follows, I T (i )  RT (i )T T U T (i, j )  tRT (i, j )T (1, j ) (3.5) (3.6) Finally, the number of interruptions and interruption duration of each load can be calculated. We use matrix I and U to represent the total number of interruptions and total interruption duration of loads. The total number of interruptions is equal to the sum of the number of interruptions 11 caused by lines and the number of interruptions caused by transformers. Similarly, The total interruption duration equals to the sum of interruption duration caused by lines and interruption duration caused by transformers. I (i )  I L (i )  I T (i ) l m j 1 j 1 (3.7) U (i )   U L (i , j )   U T (i , j ) (3.8) Then SAIFI and SAIDI can be calculated as SAIFI=  N    N I (i ) N N i i i i SAIDI= (3.9) i NU N i i i   N U (i ) N i (3.10) i 3.2 Case Study Part of the distribution system of IEEE-RBTS bus 2 will be used as an example. The procedure of evaluating reliability of this part by the methodology proposed in section 3.1 will be described. Table 3.1 and 3.2 contain the reliability-related data of transformers and lines. Table 3.3 shows the number of customer connected to each load. Six cases will be analyzed to show how to calculate the reliability of distribution system according to the methodology proposed in this thesis. Case 1 is the basic case, in this case the only protective device is a circuit breaker. In case 2, fuses are installed to protect the lateral lines. In case 3, disconnects are installed. In case 4, both fuses and disconnects are installed. In case 5, fuses, disconnects and alternative supply are all under consideration. Fuse failure is considered in case 6 based on case 5. 12 Table 3.1 Data of Transformer Transformer Failure rate (/yr) Repair time (h) 1~7 0.015 200 Table 3.2 Data of Lines Feeder type Length (km) 1 0.60 2 3 Feeder section Failure rate (/yr) Repair time (h) 2, 6, 10 0.039 5 0.75 1, 4, 7, 9 0.04875 5 0.80 3, 5, 8, 11 0.052 5 numbers Table 3.3 Number of Customers Connected to Each Load Load 1 2 3 4 5 6 7 Number 210 210 210 1 1 10 10 13 3.2.1 Case 1 In this case, the reliability of a small branch will be evaluated, which does not contain fuse or disconnect, only a circuit breaker is applied as protection in this basic case. The single line diagram is shown in Figure 3.1. Figure 3.1 Diagram for Basic Case The failure rate matrix of distribution lines is shown as below, L  [0.0488 0.0390 0.0520 0.0488 0.0520 0.0390 0.0488 0.0520 0.0488 14 0.0390 0.0520] (3.11) Since there is no protective equipment at lateral lines, fault occurs on every line and each transformer will trip the breaker and thus, interrupt all the customers. Hence, RL and RT should be all-ones matrices. 1 1  1  RL  1 1  1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1  1  1 1  1 1 1 1  1  RT  1 1  1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1  1  1 1  1 1 (3.12) Then the number of interruptions and interruption duration can be calculated by the methodology proposed. The number of interruptions and interruption duration caused by lines are as follows, RL (i )  1 1 1 1 1 1 1 1 1 1 1 I L (i )  RL (i )LT  0.52 (3.13) (3.14) Interruption duration of load i caused by distribution line j is U L (i, j )  rL RL (i, j )L (1, j ) (3.15) where, rL  5h . In this case, the interruption duration for load i is n U j 1 L (i, j )  2.6 , for all i (3.16) Then the number of interruption and duration caused by transformers can be obtained. T  [0.015 0.015 0.015 0.015 0.015 0.015 0.015] RT (i )  1 1 1 1 1 1 1 15 (3.17) (3.18) I T (i )  RT (i )T T  0.105 (3.19) The interruption duration for load i caused by transformer j is, U T (i, j )  rT RT (i, j )T (1, j )  200  1  0.015  3, for all i, j (3.20) In this case, 7 U j 1 T (i, j )  21, for all i (3.21) Then the total number of interruption and interruption duration for each load can be calculated. I (i )  I L (i )  I T (i )  0.52+0.105  0.625 l m j 1 j 1 U (i )  U L (i, j )  U T (i, j )  2.6  21  23.6 (3.22) (3.23) Hence, all the load will experience 0.625 times interruption in a year and the duration is 23.6 hours. Therefore, SAIFI=  N    N I (i )  0.625 N N (3.24) NU N (3.25) i i i i SAIDI= i i i i   N U (i )  23.6 N i i The units for SAIFI and SAIDI are interruption/customer.yr and hr/customer.yr, respectively. 3.2.2 Case 2 In this case, the transformer is assumed to be protected by a fuse in each lateral. When a short circuit fault occurs, the corresponding fuse will blow and will disconnect that lateral. Hence, the 16 fault on that lateral will not affect loads on other laterals. The interruption duration for the corresponding load is the repair time of failure. Figure 3.2 Diagram for Case 2 In this case the RL and RT matrix will not be all-ones matrix anymore. RL (i, j )  1 ,if j=1,4, 7,10 and if load i is connected to line j. 1 1  1  RL  1 1  1 1 1 0 0 0 0 0 0 0 1 0 0 0 0 0 1 1 1 1 1 1 1 0 0 1 0 0 0 0 0 0 0 1 0 0 0 17 1 1 1 1 1 1 1 0 0 0 0 1 0 0 0 0 0 0 0 1 0 1 1 1 1 1 1 1 0 0  0  0 0  0 1  (3.26) Now take load 1 as an example, the number of interruptions is, I L (1)  RL (1)LT  0.2244 (3.27) Interruption duration of load i caused by distribution line j is, U L (i, j )  rL RL (i, j )L (1, j ) (3.28) The interruption duration for load i is, 11 U L (1)  U L (1, j )  1.22 (3.29) j 1 Now, we can evaluate the interruption caused by transformers. Load i will only be affected by transformer j which connected directly to load i. Therefore, 1 0  0  RT  0 0  0 0 0 0  0  0 0  0 0 0 0 1 0 0 0 0 0 0 1  0 1 0 0 0 0 0 1 0 0 0 0 0 1 0 0 0 0 0 1 0 0 0 0 0 ( 2.30) For load 1, RT (1)  1 0 0 0 0 0 0 (3.31) T  [0.015 0.015] (3.32) I T (1)  RT (1)T T  0.015 (3.33) U T (1,1)  rT RT (1,1)T (1)  3 (3.34) U T (1, j )  rT RT (1, j )T (1)  0, for 2  j  7 (3.35) Thus, 7 U j 1 T (i, j )  3 for all i 18 (3.36) Then we can calculate the total number of interruptions and interruption duration for each load. I (1)  I L (1)  I T (1)  0.2244  0.015  0.2394 11 7 j 1 j 1 U (1)  U L (1, j )  U T (1, j )  1.122  3  4.122 (3.37) (3.38) Finally SAIFI and SAIDI can be calculated as, SAIFI=  N    N I (i )  0.248 N N (3.39) NU N (3.40) i i i i SAIDI= i i i i   N U (i )  4.165 N i i The units for SAIFI and SAIDI are interruption/customer.yr and hr/customer.yr, respectively. 3.2.3 Case 3 In this case, disconnects are applied in the distribution system. When disconnect is added, faults on feeders will still cause circuit breaker operates. Thus, RL and RT are all-ones matrices, and the number of interruptions is the same as in case 1. However, loads between the circuit breaker and disconnects will be recovered before fault is cleared in this case. The interruption duration for those loads becomes the isolation and switching time, rather than the repair time. 19 Figure 3.3 Diagram for Case 3 Let the isolation and switching time s equals 1 hour in this case. Let Z i be the nearest line to load i which installed disconnect. For example Z1  Z 2  4 , which means the nearest disconnect are installed on line 4 for load 1 and load 2. Then the interruption duration could be calculated as follows,  r R (i, j )L (1, j ), U L (i , j )   L L  sRL (i, j )L (1, j ), j  Zi otherwise (3.41) For example, U L (1,1)  rL RL (1,1)L (1,1)  5  1  0.0488  0.244 (3.42) U L (1,5)  sRL (1,5)L (1,5)  1  1  0.0520  0.0520 (3.43) After finding all the U L (1, j ) , then sum them up, 20 11 U j 1 L (1, j )  0.871 (3.44) When calculating the duration caused by transformers, it is similar to the way of calculating duration caused by lines,  r R (i, j )T (1, j ), U T (i , j )   T T  sRT (i, j )T (1, j ), j  Yi otherwise (3.45) Where, Y (i ) is a set of transformers which are in the same zone of load i. For instance, Y1  Y2  {1, 2}, Y7  {7} , then U T (1,1)  U T (1, 2)  rT RT (1,1)T (1,1)  200  1  0.015  3 (3.46) U T (1, j )  sRT (1, j )T (1, j )  1 1 0.015  0.015, for 3  j  7 (3.47) After obtaining all the U T (1, j ) , we are able to calculate, 7 U j 1 T (1, j )  6.075 (3.48) Thus, U (1)  0.871  6.075  6.946 (3.49) After finding all the U (i ) , it is easy to obtain that SAIDI is equal to 9.740, and SAIFI is the same as in case 1, which is 0.625. The units for SAIFI and SAIDI are interruption/customer.yr and hr/customer.yr, respectively. 3.2.4 Case 4 In this case, both fuses and disconnects are applied to protect the power grid. The number of interruptions is the same as in case 2, since faults on line 1, 4, 7, 9 will still trip the circuit 21 breaker, though disconnects are installed. The way to calculate the interruption duration is the same as in case 3. But the results are different, since RL and RT matrix are varied. Figure 3.4 Diagram for Case 4 In this case, 1 1  1  RL  1 1  1 1 1 0 0 0 0 0 0 0 1 0 0 0 0 0 1 1 1 1 1 1 1 0 0 1 0 0 0 0 0 0 0 1 0 0 0 1 1 1 1 1 1 1 0 0 0 0 1 0 0  r R (i, j )L (1, j ), U L (i , j )   L L  sRL (i, j )L (1, j ), 22 0 0 0 0 0 1 0 1 1 1 1 1 1 1 0 0  0  0 0  0 1  j  Zi otherwise (3.50) (3.51) Take load 1 as an example, U L (1,1)  rL RL (1,1)L (1,1)  5  1  0.0488  0.244 U L (1,5)  sRL (1,5)L (1,5)  1  0  0.0520  0 (3.52) (3.53) Then, 11 U j 1 L (1, j )  0.5753 (3.54) For transformers, 1 0  0  RT  0 0  0 0 0 1 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 1 0  r R (i, j )T (1, j ), U T (i , j )   T T  sRT (i, j )T (1, j ), 0 0  0  0 0  0 1  (3.55) j  Yi otherwise (3.56) U T (1,1)  rT RT (1,1)T (1,1)  200  1  0.015  3 U T (1, j )  sRT (1, j )T (1, j )  1 0  0.015  0, for 3  j  7 7 U j 1 T (1, j )  3 (3.57) (3.58) (3.59) Thus, U (1)  0.5753  3  3.5753 (3.60) Finally, it is found that SAIDI is 3.697 hr/customer.yr. SAIFI is 0.248 interruption/customer.yr, which is the same as in case 2. 23 3.2.5 Case 5 As shown in Figure 3.5 line 12 is connected to an alternative supply. In this case, the number of interruption is the same as in case 2, so as SAIFI. But the interruption duration will be shortened. For example, if there is a fault occurs on line 4, the breaker will trip and all the loads will be affected. Then the disconnects on line 4 and line 7 will open which isolates the fault, and then the breaker will reclosed. After this step, load 1 and load 2 are recovered. Later on, the normally open disconnect on line 12 will close, load 5, 6, 7 will be recovered. Therefore, the interruption duration for these loads, will change to the isolation and switching time, instead of the repair time of fault in line 4 as in case 3. Figure 3.5 Diagram for Case 5 The procedure to value the interruption duration is described below. Let’s define a set Z to represent the protection zone sectioned by disconnects. 24 For example, Z1  {1, 2,3}, Z 3  {4,5,6} .  r R (i, j )L (1, j ), U L (i , j )   L L  sRL (i, j )L (1, j ), j  Zi otherwise (3.61) Take load 1 as an example, since Z1  {1, 2,3} , U L (1,1)  rL RL (1,1)L (1,1)  5  1  0.0488  0.244 (3.62) U L (1, 2)  rL RL (1, 2)L (1, 2)  5  0  0.0390  0 (3.63) U L (1,3)  rL RL (1,3)L (1,3)  5  1  0.052  0.26 (3.64) The rest U L (i, j )  sRL (i, j )L (i, j ) , For instance, U L (1, 4)  sRL (1, 4)L (1, 4)  1  1  0.0488  0.0488 (3.65) U L (1,5)  sRL (1,5)L (1,5)  1  0  0.052  0 (3.66) After calculating all the U L (1, j ) , we are able to find the interruption duration caused by lines of load 1, which is, 11 U j 1 L (1, j )  0.5753 (3.67) The interruptions duration caused by transformers are the same as in case 4, which is 3h. Then, U (1)  0.5753  3  3.5753 (3.68) Finally, it is found that SAIFI is 0.248 interruption/customer.yr and SAIDI is 3.613 hr/customer.yr. 25 3.2.6 Case 6 Protective devices are not 100% reliable, so we need to consider protection failures. In this case, we assume that fuse could operate when it needed with probability 0.9 [6]. Then the number of interruptions and duration will be different to case 5. RL and RT in this case is as shown in 3.69 and 3.70. 1 1  1  RL  1 1  1 1 0.1 0.1  0.1  0.1 0.1 0.1 1 0.1 0.1 1 1 0.1 1 0.1  0.1 0.1 1 0.1 0.1 1 0.1 1 1 0.1 0.1 0.1 1 0.1 0.1 1 0.1 0.1 1 1  1 0.1 1 0.1 0.1 1 0.1 0.1 0.1 1 1 0.1 0.1 1 0.1 0.1 0.1 0.1 1 1 0.1 1 0.1 0.1 0.1 0.1 1 0.1 1 1 0.1 0.1 1 0.1  0.1  RT  0.1 0.1  0.1 0.1 0.1 1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 1 0.1 1 1 1 1 0.1 0.1  0.1  0.1 0.1  0.1 1  Then the number of interruptions and duration caused by lines for load 1 are as below, 26 (3.69) (3.70) I L (1)  RL (1)LT  1 1 0.1 1 0.1 0.1 1 0.1 0.1 1 0.1 LT (3.71)  0.2538  r R (i, j )L (1, j ), U L (i , j )   L L  sRL (i, j )L (1, j ), j  Zi otherwise (3.72) For instance U L (1,1)  rL RL (1,1)L (1,1)  5  1  0.0488  0.244 (3.73) U L (1, 2)  rL RL (1, 2)L (1, 2)  5  0.1  0.0390  0.0195 (3.74) U L (1,3)  rL RL (1,3)L (1,3)  5  1  0.052  0.26 (3.75) U L (1, 4)  sRL (1, 4)L (1, 4)  1  1  0.0488  0.0488 (3.76) U L (1,5)  sRL (1,5)L (1,5)  1  0.1  0.052  0.0052 (3.77) Then, 11 U j 1 L (1, j )  0.5803 (3.78) The analysis for transformer’s affect is similar. Then the number of interruptions caused by transformers is, I T (i )  RT (i )T T  0.024 for all i (3.84) In this case,  r R (i, j )T (1, j ), U T (i , j )   T T  sRT (i, j )T (1, j ), j  Yi otherwise (3.85) For load 1, U T (1,1)  rT RT (1,1)T (1,1)  200  1  0.015  3 (3.86) U T (1, 2)  rT RT (1, 2)T (1, 2)  200  0.1  0.015  0.3 (3.87) 27 U T (1, j )  sRT (1, j )T (1, j )  1 0.1 0.015  0.0015, for 3  j  7 (3.88) Therefore, 7 U j 1 T (1, j )  3.3075 (3.89) Then we could calculate the total number of interruptions and duration for each load. For example, I (1)  I L (1)  I T (1)  0.2538  0.024  0.2778 11 7 j 1 j 1 U (1)  U L (1, j )  U T (1, j )  0.5803  3.3075  3.8878 (3.90) (3.91) Finally, SAIFI and SAIDI can be valued. In this case SAIFI is 0.284 interruption/customer.yr and SIDAI is 3.888 hr/customer.yr. 3.3 Reliability Evaluation for RBTS Busbar 2 In this section the reliability of RBTS busbar 2 [17] will be evaluated. This system contains 36 lines, 22 loads and 1908 customers. The single line diagram for RBTS Busbar 2 is shown in Figure 3.6. Customer data, feeder types and length, loading data, reliability and system data are listed in Table 3.4~3.7. Table 3.4 Feeder Type and Length Feeder type Length/km Feeder section numbers 1 0.60 2, 6, 10, 14, 17, 21, 25, 28, 30, 34 2 0.75 1, 4, 7, 9, 12, 16, 19, 22, 24, 27, 29, 32, 35 3 0.80 3, 5, 8, 11, 13, 15, 18, 20, 23, 26, 31, 33, 36 28 Table 3.5 Customer Data Number of load points Load points Load level per load point, MW Customer type Average Peak Number of customers 5 1-3, 10, 11 Residential 0.535 0.8668 210 4 12, 17-19 Residential 0.450 0.7291 200 1 8 Small user 1.00 1.6279 1 1 9 Small user 1.15 1.8721 1 6 4, 5, 13, 14, 20, 21 Govt/inst 0.566 0.9167 1 5 6, 7, 15, 16, 22 Commercial 0.454 0.7500 10 12.291 20.00 1908 Total Table 3.6 Loading Data Feeder load, MW Feeder number Load points Average Peak Number of customers F1 1-7 3.645 5.934 652 F2 8-9 2.15 3.500 2 F3 10-15 3.106 5.057 632 F4 16-22 3.390 5.509 622 12.291 20.00 1908 Total 29 Table 3.7 Reliability and System Data Component P T  '' T 33/11 0.015 0.05 1 11/0.415 0.015 B33 0.002 0.02 B11 0.006 L33 0.046 L11 0.065 Cable 0.040 r rP r '' rC s 15 120 0.083 1 200 10 1 0.5 4 96 8 0.083 1 0.06 1.0 4 72 8 0.083 1 0.06 0.5 8 8 8 0.083 2 5 30 Where, P : permanent(total) failure rate (f/yr) (for lines/cables (f/yr.km)) T : temporary failure rate (f/yr) (for lines/cables (f/yr.km))  '' : maintenance outage rate (out/yr) r : repair time (hr) rP : replace time by a spare (hr) r '' : maintenance outage time (hr) rC : reclosure time (hr) s: switching time (hr) 30 3 Figure 3.6 Distribution System of RBTS Busbar 2 31 Reliability of six cases will be calculated and their characteristics are shown in Table 3.8. The differences are the inclusion or not of disconnects in the main feeders, fuses in each lateral, an alternative supply and fuses failures. Table 3.8 Summary of Six Cases Case Fuse Disconnect Alternative Supply Repair of Transformer Failure of Fuse 1 2 √ 3 √ √ √ √ 4 √ √ 5 √ √ √ √ 6 √ √ √ √ √ Table 3.9 Result for Case 1 CASE 1 SAIFI SAIDI F1 0.625 23.6 F2 0.192 0.959 F3 0.558 20.34 F4 0.625 23.6 SYSTEM 0.602 22.496 32 Table 3.10 Result for Case 2 CASE 2 SAIFI SAIDI F1 0.248 4.165 F2 0.14 0.699 F3 0.25 4.174 F4 0.247 4.16 SYSTEM 0.248 4.163 Table 3.11 Result for Case 3 CASE 3 SAIFI SAIDI F1 0.625 9.740 F2 0.192 0.777 F3 0.558 8.465 F4 0.625 11.66 SYSTEM 0.602 9.934 33 Table 3.12 Result for Case 4 CASE 4 SAIFI SAIDI F1 0.248 3.697 F2 0.14 0.621 F3 0.25 3.76 F4 0.247 3.75 SYSTEM 0.248 3.732 Table 3.13 Result for Case 5 CASE 5 SAIFI SAIDI F1 0.248 3.618 F2 0.14 0.523 F3 0.25 3.624 F4 0.247 3.605 SYSTEM 0.248 3.613 34 Table 3.14 Result for Case 6 CASE 6 SAIFI SAIDI F1 0.286 3.926 F2 0.145 0.529 F3 0.282 3.83 F4 0.285 3.917 SYSTEM 0.284 3.888 Table 3.15 Comparison of Six Cases Results CASE SAIFI SAIDI 1 0.602 22.496 2 0.248 4.163 3 0.602 9.894 4 0.248 3.732 5 0.248 3.613 6 0.284 3.888 35 3.4 Summary In this chapter, a methodology is proposed to calculate the reliability indices of distribution system. This methodology is derived from R. Billiton’s book [6]. Reference [31] introduced a methodology, zone branch reduction, which also uses matrix to calculate the reliability indices. The comparison between cases demonstrates the effect of protective devices. It is obvious that Case 5 is the most reliable one with lowest SAIFI and SAIDI, since it contains fuses, disconnects and alternative supply and all the protective devices are assumed perfectly reliable. SAIDI in case 1 is bigger than others, since it has no protection except the circuit breaker. The difference of SAIFI between case 2 and case 4 is because of the effect of disconnects. Since, disconnects are able to let the loads which are outside the fault zone recover more quickly. The interruption duration for such loads are decreased from repair time as 5 hours to switching and isolation time as 1 hour. Therefore, SAIDI in case 4 is smaller than case 2. SAIFI of case 2, 3 ,4 and 6 are the same, since fuses are installed in laterals in these four cases. The effects of faults will be reduced by fuses. Hence, SAIFI in these four cases are smaller than case 1 and case 5. Alternative supply is also a very effective way to improve the system reliability. SAIDI is decreased from 3.732 as in case 4 to 3.613 as in case 5. 36 CHAPTER 4 OPTIMIZATION OF ALLOCATION OF DISCONNECTS USING GENETIC ALGORITHM 4.1 Introduction The fundamental goal of an electric utility has always been to serve its customers with a reliable and low cost power supply [7]. From the cases in chapter 5, we find that disconnects are helpful to reduce the interruption duration of customers, which is able to enhance the reliability of distribution systems. It is apparent that more the disconnects are installed in the distribution feeder, less the interruption duration is of the customer. However, the investment cost of utility will be more with the increase of the number of disconnects. In recent years, electric utility industry has confronted many challenges in the increasingly competitive market, which demands them to serve its customers with higher reliability and lower cost power supply [20]. The presence of inverse relation between economic constraint and reliability is obvious, as shown in Figure 4.1 [21], so this causes complexity in management decisions. Hence, a method is needed 37 to find an optimum solution with lower investment cost and higher reliability. In this vein, this chapter proposes an optimization method for planning adequate number and location of disconnect in a distribution system with reliability consideration. Figure 4.1 Cost as a Function of Reliability The relationship between allocation of protective devices and SAIDI is complex and the constraint is non-differentiable. Thus, traditional analytical approaches such as linear and nonlinear programming have difficulty in dealing with this optimization problem. Previous work, such as [19][25-26], stated that the problem of location of protective devices naturally has binary specification in distribution networks. Each protective device has two states: connected or disconnected and can be model as 0 and 1, respectively. This specification causes using binary programming method for optimal location of protective devices [20]. However, as the size of the 38 distribution system becomes larger, the possible position to install protective devices increases rapidly and this lead to slower speed when solving this problem by binary programming. Therefore, evolutionary methods are applied to solve this kind of problem [20][27-29]. In recent past, nontraditional search and optimization methods are becoming popular in electrical engineering, such as Genetic Algorithms (GA), Ant colony optimization (ACO) and Particle Swarm Optimization (PSO). The method proposed in this chapter uses GA to find the optimum solution. Genetic algorithms are computerized search and optimization algorithms based on the mechanic of natural genetics and natural selection [23]. This method was first used by J. H. Holland in mid-sixties [22]. The detail of this methodology is presented in the next section. 4.2 Methodology The goal of system optimization is to minimize an objective function without violating any constrains [18]. The objective of this problem is to minimize the cost of investment, which is equal to the sum of the price of each disconnect. Minimize F  X T C Where, F is the total cost of investment; C is a vector of the unit price of disconnect, Ci is the price of disconnect installed on possible 39 position i; X is a vector of decision of positions. xi is the decision for position i, if xi  1 , which means a disconnect is installed on position i. Otherwise, if xi  0 , this means position i is not connected to a disconnect. The constraint is reliability. In this model, we use SAIDI to evaluated the reliability. Since the change of position and number of disconnects will also let the SAIDI varied. Therefore, SAIDI should be updated each time. This step can be realized by the methodology proposed in chapter 3. Using the methodology proposed in chapter 3, the interruption duration in each feeder and the whole system can be obtained. Then the constraint is as shown below, S  Smax (4.1) Where S is the Sustained Average Interruption Duration Index (SAIDI), Smax is the maximum SAIDI allowed. As shown before [3], SAIDI=  Customer Minutes of Interruption Total Number of Customers Served (4.2) Therefore, the mathematical model for this optimization problem can be stated as follows, Minimize F  X T C Subject to (4.3) S  Smax 40 This reliability-based optimization problem is solved by Genetic Algorithm (GA) and the steps of a typical genetic algorithm is as follows [23], Step 1 Choose a coding to represent problem parameters, a selection operator a crossover operator, and a mutation operator. Choose population size n, crossover probability pc , and mutation probability pm . Initialize a random population of strings of size l. Choose a maximum allowable generation number tmax . Set t=0. Step 2 Evaluate each string in the population. Step 3 If t  tmax or other termination criteria is satisfied, Terminate. Step 4 Perform reproduction on the population. Step 5 perform crossover on random pairs of strings. Step 6 Perform mutation on every string. Step 7 Evaluate strings in the new population. Set t=t+1 and go to Step 3. The detail of each step is presented below. 4.2.1 Coding In order to solve the optimization problem by GAs, the variables are firstly coded in strings. GAs work with a population of binary string (0 and 1), and because of the characteristic of this 41 problem, binary coding is used in this methodology. With the binary coding method, the decision of possible positions would be coded as a binary string with length n, where n is the total number of possible positions. The binary-coded string shows the decision for each possible position to connect to a disconnect or not. In the string, “1” represents “connected” and “0” represents “not-connected”. The string X can be shown as below, X   x1 x2  xn  (4.4) Where, n Number of possible positions to install disconnect xi Decision for position i, xi  0 or 1 and 1  i  n . 4.2.2 Fitness When dealing with constrained optimization problems, a penalty-parameter-less constraint handling approach is popular used, which is proposed by K. Deb in 2000 [24]. The concept is simple. In a tournament selection operator comparing two population members, three possibilities and corresponding selection strategy were suggested [23]: (a) When one solution is feasible and the other is infeasible, the feasible solution is selected. (b) When both solutions are feasible, the one with better function value is selected. 42 (c) When both solutions are infeasible, the one with smaller constraint violation is selected. The definition of a Constraint Violation (CV) is determined in [24] . There are two steps to find CV. First, normalize all constraints using the constant term in the constraint function. For example, the constraint g j ( x )  b j  0 is normalized as g j ( x )  g j ( x ) / b j  1  0 [23]. Equality constraints can also be normalized to h k ( x ) . Second, the constraint violation can be determined as follows, J K j 1 k 1 CV ( x )   g j ( x )   h j ( x ) (4.5) A way to use the above penalty-parameter-less approach is to convert the problem into the following unconstrained fitness function [23].  fitness( x )    Where f max f ( x ), if x is feasible f max  CV ( x ), if x is infeasible (4.6) is the maximum objective function value among the feasible solutions or zero when there is no feasible solution in a population. In this optimum allocation of disconnects problem, the only constraint is the reliability requirement, therefore, CV can be expressed as follows, CV ( x )  S ( x ) / Smax  1, if x is infeasible 43 (4.7) 4.2.3 Reproduction Reproduction, also known as selection operator. Reproduction selects good strings in a population and forms a mating pool [23]. Roulette-wheel selection and tournament selection are often used to form mating pool. In this work, tournament selection is applied. First, pick s individuals from the population, then choose the best among them to the mating pool. A binary tournament selection with s=2 is used in this work. After forming the mating pool, stings in mating pool are going to the next step: crossover. 4.2.4 Crossover In a crossover operator, new strings are created by exchanging information among strings of the mating pool [23]. This step is mainly responsible for the search of new strings. In order to create new strings, two strings are selected randomly from the mating pool, and these two strings are called parent strings, the newly created strings are known as children strings. After randomly selecting the parent strings from the mating pool, a single-point crossover is applied. First, a crossing point is randomly chosen. Then exchange all the bits on the right side of the crossing point, as shown below, 0 00 0 0 0 0 1 1 1  1 1 1 1 1 1 10 0 0 44 (4.8) Not all the old strings are used in crossover, a crossover probability pc preserve some of the good strings. Only 100 pc is used in order to percent of old strings are used in crossover operation. 4.2.5 Mutation Mutation of gene happens with low probability in nature. In GAs, a mutation operation is applied to mimic this change. The mutation operator changes 1 to 0 and vice versa for each bit of every string with a small mutation probability pm . This step allows the algorithm to a local search around current solutions. 4.3 Case Study In this section, two cases will be presented. One case is still the RBTS bus 2 [17], another is the whole RBTS system. The information of the whole RBTS system can be found in [17] and [30]. 4.3.1 Case 1 There are ten possible locations to install disconnect in this distribution system, which are on line 4, 7, 10, 14, 18, 21, 24, 29, 32 and 34. So we have 10 variables for this system. we can use 45 variables x1 to x10 to represent these possible positions. Then x1 represents the decision for position 1, which is on line 4 and x10 represents the decision for position 10, which is on line 34. For example, if the result shows that x1 is 1, this means a disconnect is installed on line 4. Variables xi in the objective function are calculated using MATLAB to obtain the optimum solution. X can be coded as below, X   x1 x2  x10  (4.9) In this case, the mathematical model is as follows, Minimize F  X T C Subject to, (4.10) S  Smax In this case we assume the price for each disconnect is 3000$ [20], that is Ci  3000 for all i. Several optimum solutions for different maximum SAIDI are obtained by MATLAB. The result is listed in Table 4.1. The flowchart for the methodology is as shown in Figure 4.1. 46 Table 4.1 Optimum Solution for Case 1 SAIDI_max SAIDI Position of disconnects Number of disconnects Investment cost ($) 3.66 3.6579 4, 18, 21, 29, 32 5 15000 3.63 3.6169 4, 7, 18, 21, 29, 32 6 18000 3.615 3.6150 4,7,10,18, 21, 29, 32 7 21000 3.614 3.6140 4, 7, 10, 18, 21, 24, 29, 32 8 24000 3.613 3.6128 4, 7, 10, 14, 18, 21, 24, 29, 32 9 27000 47 Figure 4.2 Flowchart 48 4.3.2 Case 2 In this case, the whole RBTS system is used. In this system, there are 287 lines, 170 loads and 18,289 customers in this test system, some of the system data are listed in Table 4.2 [17][30]. 69 possible places are chosen to install disconnects. The optimal solution is obtained by Genetic Algorithm and the result is shown in Table 4.3. Table 4.2 System Data for RBTS Bus 2 Bus 3 Bus 4 Bus 5 Bus 6 Total Lines 36 77 67 43 64 287 Loads 22 44 38 26 40 170 Customers 1,908 5,806 4,779 2,858 2,938 18,289 Positions 10 19 16 13 11 69 49 Table 4.3 Optimum Solution for Case 2 SAIDI_max 4.0 3.9 3.8 SAIDI Position of disconnects 3.9959 Bus 3: 6, 23, 35, 45, 59 Bus 4: 5, 23, 36, 63 Bus 6: 7, 21 3.8897 Bus 2: 4 Bus 3: 3, 8, 23, 35, 38, 45, Bus 4: 5, 23, 36, 60, 63 Bus 5: 7, 18, 39 Bus 6: 7, 21 3.7928 Bus 2: 4, 18, 21, 32 Bus 3: 3, 8, 21, 23, 35, 38, 45, 57, 59 Bus 4: 5, 7, 23, 26, 33, 36, 39, 60, 63 Bus 5: 4, 18, 36 Bus 6: 7, 17, 23 Number of disconnects Investment cost ($) 11 33,000 18 54,000 28 84,000 47 141,000 59 Bus 2: 4, 7, 18, 21, 29, 32 3.7 3.6969 Bus 3: 3, 6, 8, 10, 21, 23, 26, 33, 35, 38, 40, 45, 50, 57, 59, 62 Bus 4: 3, 5, 7, 10, 21, 23, 26, 33, 36, 39, 58, 60, 63, 65 Bus 5: 4, 16, 20, 28, 36, 41 Bus 6: 5, 9, 17, 21, 23 50 CHAPTER 5 CONCLUSION 5.1 Summary Protection systems play significant roles in power systems, which help to improve the reliability of power grids. In this thesis, basic reliability indices, such as SAIFI and SAIDI are presented. What’s more, this thesis proposes a methodology which is based on the methodology presented in the book “Reliability Evaluation of Power Systems” by R. Billiton, but the methodology in this thesis is easier to implement compared to the original one proposed by R. Billiton. To calculate the number of interruptions and interruption duration for each loads, this method uses matrices to represent the relationship of components, which is very straightforward and self-explanatory. SAIFI and SAIDI of IEEE-RBTS bus 2 system are calculated in six different cases. By comparing the results of the six cases, it is obvious to see the impact of protection systems and protection failures. Further, based on the methodology of evaluating reliability indices, a reliability-based optimization problem is proposed and solved by Genetic Algorithm. This optimization problem 51 is aim to find the minimum cost of investment of disconnects with reliability constraint. Optimum solutions have been found for RBTS bus 2 and the whole RBTS system. When I first try to solve the optimization problem, the binary programming method is used as applied in [25-26]. However, this method is slower compare to Genetic Algorithm, especially when the system becomes larger. Therefore, GA is chosen to solve the optimization problem. It is suitable for this allocation optimization problem and fast to find the optimum solution. 5.2 Future Work A multi-objective reliability-based optimization model would be established. The pareto-optimum can be found by performing a multi-objective optimization model. In addition, disconnect is the only protective device taken into consideration in this work. Other protective devices, such as reclosers, relays and fuses would also be considered in an optimization problem in the future. 52 BIBLIOGRAPHY 53 BIBLIOGRAPHY [1] IEEE Std-100-1992, "IEEE Standard Dictionary of Electrical and Electronics Terms," John Wiley&Sons, Inc., New York, 1992. [2] A. Girgis, S. Brahma, "Effect of Distributed Generation on Protective Device Coordination in Distribution System," in Large Engineering Systems Conference on Digital Object Identifier, pp. 115 - 119, 2001. [3] IEEE Std 1366-2012 (Revision of IEEE Std 1366-2003), IEEE Guide for Electric Power Distribution Reliability Indices, 2012. [4] M. P. Bhavaraju, R. Billinton, R. E.Brown, J. Endrenyi, W. Li, A. P. Meliopoulos, and C. Singh, "IEEE Tutorial on Electric Delivery System Reliability Evaluation," IEEE Power Engineering Society General Meeting, 2005. [5] Yu Xiaobin, C. Singh, "A Practical Approach for Integrated Power System Vulnerability Analysis With Protection Failures," Power Systems, IEEE Transactions on, vol. 19, pp. 1811-1820. [6] R. Billinton, RN. Allan, "Reliability Evaluation of Power Systems," New York: Plenum, 1984. [7] F. Soudi, K. Tomsovic, "Optimized distribution protection using binary programming," Power Delivery, IEEE Transactions on, vol. 13, No. 1, pp. 218-224, 1998. [8] P. M Anderson, "Power System Protection," McGraw-Hill, IEEE Press, 1999. [9] G. F. L. Dixon, H. Hammersley, "Reliability and its Cost on Distribution Systems," International Conference on Reliability of Power Supply Systems, IEE Conference Publication, No. 148, 1977. [10] Richard E. Brown, "Electric Power Distribution Reliability," ABB Inc. Raleigh, North Carolina. 54 [11] IEEE Std 493-1990, IEEE Recommended Practice for the Design of Reliable Industrial and Commercial Power Systems (Gold Book), 1995. [12] A. G. Phadke and J. S. Thorp, "Expose Hidden Failures to Prevent Cascading Outages," IEEE Computer Application in Power, vol. 9, No. 3, pp. 20-23, 1996. [13] D. C. Elizondo, J. D. L. Ree, A. G. Phadke, and S. Horowitz, "Hidden Failures in Protection Systems and Their Impact on Wide-Area Disturbance," IEEE Power Engineering Society Winter Meeting, vol. 2, pp. 710-714, 2001. [14] R. Billinton and S. K. Agarwal, "Examination of severe contingencies in a small area of a large composite power system using adequacy equivalents," Generation, Transmission and Distribution, IEE Proceedings C, vol. 137, pp. 107-114, 1990. [15] Fang Yang, A. P. Sakis Meliopoulos, George J. Cokkinides, Q. Binh Dam, "Effects of Protection System Hidden Failures on Bulk Power System Reliability," Power Symposium, NAPS 2006. 38th North American, pp. 517 - 523, 2006. [16] D. C. Elizondo and J. D. L. Ree, "Analysis of Hidden Failures of Protection Schemes in Large Interconnected Power Systems," in IEEE Power Engineering Society General Meeting, vol.1, pp. 107 - 114, 2004. [17] R. N. Allan, R. Billinton, I. Sjarief, L. Goel, K. S. So, "A reliability test system for educational purposes-basic distribution system data and results," Power Systems, IEEE Transactions on, vol. 6, No. 2, pp. 813 - 820, 1991. [18] R. E. Brown, S. Gupta, R. D. Christie, S. S. Venkata, R. Fletcher, "Distribution system reliability assessment usinghierarchical Markov modeling," Power Delivery, IEEE Transactions on, vol. 11, No. 4, pp. 1929 - 1934, 1996. [19] F. Darabi, A. T. Shooshtari, E. Babaei, S. Darabi, "Reliability Cost Allocation of Protective devices Using Binary Programming," Business, Engineering and Industrial Applications (ISBEIA), 2011 IEEE Symposium on, pp. 469-474, 2011. 55 [20] Bin Liu, Shiyan Kun, Jiyan Zou, Xiongying Duan, Xiang Zheng, "Optimal Feeder Switches Location Scheme for High Reliability and Least Costs in Distribution System," Intelligent Control and Automation, 2006. WCICA 2006. The Sixth World Congress on, vol. 2, pp. 7419-7423, 2006. [21] R. Billinton, S. Kumar, N. Chowdhury, K. Chu, K. Debnath, L.Goel, E. Khan, P. Kos, G. Nourbakhsh, J. Oteng-Adjei, "A Reliability Test System for Educational Purposes-Basic Data," Power Engineering Review, IEEE, vol.9, No. 8, pp. 67-68, 1989. [22] J. H. Holland, "Adaptation in Natural and Artificial Systems," The University of Michigan Press, Ann Arbor, USA, 1975. [23] K. Deb, "Optimization for Engineering Design," Second Edition, PHI, 2012. [24] K. Deb,"An Efficient Constraint Handling Method for Genetic Algorithm,"Computer Methods in Applied Mechanics and Engineering, 186(2-4), pp. 311-338, 2000. [25] R. Bupasiri, N. Wattanapongsakorn, J. Hokierti, D. W. Coit, "Optimal Electric Power Distribution System Reliability Indices Using Binary Programming," Reliability and Maintainability Symposium, 2003. Annual, pp. 556-561, 2003. [26] F. Soudi, K. Tomsovic, "Optimized distribution protection using binary programming," Power Delivery, IEEE Transactions on, vol. 13, No. 1, pp. 218-224, 1998. [27] L. G. W. da Silva, R. A. F. Pereira, J. R. S. Mantovani, "Optimized allocation of sectionalizing switches and control and protection devices for reliability indices improvement in distribution systems," Transmission and Distribution Conference and Exposition: Latin America, 2004 IEEE/PES, pp. 51-56, 2004. [28] M. Jafari, H. Monsef, S. Z. Moghadam, "Optimum number, placement and capacity of DGs and reclosers using analysis hierarchical process and genetic algorithm," Environment and Electrical Engineering (EEEIC), 2011 10th International Conference on, pp. 1-4, 2011. [29] Zhang Li, Xu Yuqin, Wang ZengPing, "Research on optimization of recloser placement of DG-enhanced distribution networks," Electric Utility Deregulation and Restructuring and Power Technologies, 2008. DRPT 2008. Third International Conference on, pp. 2592 - 2597, 2008. 56 [30] R. Billiton, S. Jonnavithula, "A test system for teaching overall power system reliability assessment," Power Systems, IEEE Transactions on, vol.11, No.4,pp.1670-1676, 1996. [31] Sree Rama Kumar Yeddanapudi, James D McCalley, "Reliability Analysis in Distribution Systems module 2," 2005. 57