. t . u r . r , 1 .. O . . I . . . . . .. . . . . .. . . . . . .- 2! 15. . §‘§§:fi , . . 3.35"... . .. y . . .. 1 . f . . . 1 u . 1 .1. .. . . . . 1 . . s . . . .1 .. . . .. . . : . . . , . . a}!.$.flu.iol§‘lr . .. . .. . ., . .. . . . . . 1 11.}!!! it’lrplév. I: . A A ,. n l . . . t . 7 1 .. . psgvli.gifimm£ 1 . a tin}, . . . . . . V . . h . . ,. . . . v .. . 1 . . ~ .. . . . ,. . 1 . ._ n r , I . .. . . . a . . . . o . v . . . . . . .,. . . .. . . . o. . . y . . . . 1 1. . A v u z . ‘ a . . .. . . . : . . A . .. . 1. _. . r . . A . . u . y , . . .._ . . . . . . . . . f o. . ., . ‘ .. . . . .. a . 1 . . . .. . v. 1 . . . . . . . .1 . . “1... .. .. .. . . .7. .. .. Iv . 1 . . ~ ..r . » .1 . .12... a... .3315...» MWMMMWWWW [LSMWARV a, Miriam, M"? burs l Uriiwiewsitly3 This is to certify that the dissertation entitled The Size-Reliability Trade-off and the Construction Cost of , Coal-Burning Generating Units. presented by Bradley K. Borum has been accepted towards fulfillment of the requirements for Ma]— degree in icnnnmics_ Major professor /’-\ ‘ I Date 0“" ‘7‘; “’80! MSU is an Affirmative Action/Equal Opportunity Institution 0-12771 (n a 4);: a: s / ’- ¢ ~5_-r--+ PLACE “ RETURN BOX to romwo this checkout from your record. TO AVOID FINES mum on or boron duo duo. DATE DUE DATE DUE DATE DUE In 2 9 ma T—U MSU lo An Afflrmdlvo Action/Equal Opportunity Intuition emu-nut _.__....... w l ”-1—...- THE SIZE-RELIABILITY TRADEOFF AND THE CONSTRUCTION COST OF COAL-BURNING GENERATING UNITS By Bradley Keith Borum A DISSERTATION Submitted to Michigan State University in partial fulfillment of the requirements for the degree of DOCTOR OF PHILOSOPHY Department of Economics 1989 g) ABSTRACT THE SIZE-RELIABILITY TRADEOFF AND THE CONSTRUCTION COST OF COAL-BURNING GENERATING UNITS by Bradley Keith Borum The construction cost of a baseload coal-fired generating unit should depend, in general, on the engineering attributes of the unit. Previous studies generally found that there are scale economies in average construction costs over the entire range of observed unit sizes. However, these studies failed to include reliability as an attribute or characteristic of the units. Larger generating units tend to be considerably less reliable than smaller units. Thus, an important unanswered question is whether large generating units have lower average construction costs per Kw of capacity because of economies of scale or because of poor quality. The implication is that omitting unit reliability will bias the estimates of the construction cost function. To analyze this question, we develop an ex ante long-run unit reliability and construction cost model. Both unit reliability and construction cost were expressed as functions of the dominant design characteristics of the generating unit. Furthermore, a simultaneous relationship between construction cost and reliability was assumed. The simultaneous-equation model was estimated with a data set that contained observations on 84 coal-fired units that entered commercial operation during the period 1964-1974. The regression estimates were used to evaluate how capital costs per KH and capital costs per KNH responded to Bradley K. Borum variations in unit size and reliability. Both measures of capital costs were found to be characterized by economies of scale at low levels of reliability and diseconomies at high levels of reliability. The cost minimizing level of reliability for each measure was also found to decrease as unit size increased. Capital cost per KWH generated are found to be lowest for units in the 300-400 MN range with equivalent availabilities of 85 to 90 percent. Copyright by BRADLEY KEITH BORUM 1989 ACKNOWLEDGMENTS Special thanks go to Dr. Harry M. Trebing for stirring my interest in the field of public utility economics and his continued encouragement to complete this project. The other members of my dissertation committee, Drs. Ken Boyer, Warren Samuels and Peter Schmidt, were unusually helpful and prompt with their suggestions. It is no exaggeration to say that their suggestions greatly improved the entire study. Special thanks also go to 8.". Stoller Corporation. This study would not have been possible without the unit availability data it so kindly provided to me. Kesa Hall, Beth Hynes and Joyce Smith typed various parts of this manuscript and their assistance is greatly appreciated. Finally, special recognition must go to Julie Relue. This project might never have been completed without her kindness, understanding and moral support. TABLE OF CONTENTS xi List of Tables ...................... viii List of Figures ...................... CHAPTER 1: INTRODUCTION ................. l The Cost of Poor Unit Reliability .......... 2 Relationship Between Unit Attributes and Construction Costs ........................ 5 The Changing Electric Utility Environment ...... 7 Methodology ..................... 8 CHAPTER 2: SURVEY AND CRITIQUE OF THE LITERATURE ..... 11 The Basic Production Process and Technological Change 11 Models Which Fail to Properly Control for Capital Heterogeneity .................... 14 Models Which Avoid the Vintage Problem ........ 25 Summary ....................... 43 CHAPTER 3: DEVELOPMENT OF A GENERATING UNIT CONSTRUCTION COST AND RELIABILITY MODEL .......... 46 Introduction ..................... 46 The Heterogeneous Nature of Capital ......... 47 The Two-Dimensional Nature of Output ...... 47 The Unit Design Process and Ex Post Production . 48 The Model ...................... 51 General ..................... 51 The Expected Ex Post Cost Function ....... 52 vi Ex Ante Costs and the Investment Decision . . . . 53 Specification of the Construction Cost and Reliability Model .................. 55 The Determinants of Unit Construction Cost . . . 55 The Determinants of Unit Reliability ...... 59 The Need for a Simultaneous-Equations Model . . . 63 Estimation of the Simultaneous-Equations Model . 66 Empirical Analysis .................. 67 The Data .................... 67 Regression Results ............... 69 Summary ....................... 97 CHAPTER 4: AVERAGE CAPITAL COSTS AND THE UNIT SIZE- RELIABILITY TRADEOFF ............. 100 Introduction ..................... 100 The Behavior of Average Capital Costs ........ 101 Efforts to Improve Utility Performance and the Size- Reliability Tradeoff ................. 120 Summary ....................... 124 CHAPTER 5: CONCLUSIONS .................. 126 Summary ....................... 126 Suggestions for Future Research ........... 130 APPENDIX A: THE DEFLATION PROCESS ............ 132 APPENDIX B: ESTIMATION OF A COBB-DOUGLAS SPECIFICATION OF THE COST FUNCTION .............. 133 APPENDIX C: DERIVATION AND STATISTICAL SIGNIFICANCE OF NONLINEAR DERIVATIVES ............ 141 END NOTES ........................ 143 BIBLIOGRAPHY ....................... 149 vii Table Table Table Table Table Table Table Table Table Table Table Table Table Table 1-1: 2-1: 2-2: 3-1: 3-2: 3-3: 3-4: 3-5: 3-6: 3-7: 3-8: 3-9: 3-10: 3-11: LIST OF TABLES Average Equivalent Availability Factors in the United States, 1971-1980 ........... 3 Capacity Additions by Technological Group and Year: 1950-1982 (% of New Capacity) ..... 13 Size Distribution of New Coal Capacity Year: 1950-1982 (Mwe) ............ 14 Ordinary Least Squares Estimate of the Construction Cost Function .......... 72 Ordinary Least Squares Estimate of the Construction Cost Function .......... 73 Ordinary Least Squares Estimate of the Construction Cost Function .......... 74 Ordinary Least Squares Estimate of the Construction Cost Function .......... 75 Ordinary Least Squares Estimate of the Reliability Function ............. 77 Two-Stage Least Squares Estimate of the Construction Cost Function .......... 78 Two-Stage Least Squares Estimate of the Construction Cost Function .......... 79 Two-Stage Least Squares Estimate of the Construction Cost Function .......... 80 Two-Stage Least Squares Estimate of the Construction Cost Function .......... 81 Two-Stage Least Squares Estimate of the Reliability Function ............. 82 Plant Cost Elasticities with Respect to Size for a Generic Unit ........... 84 viii Table Table Table Table Table Table Table Table Table Table Table Table Table Table Table Table Table Table Table Table Table 3-12: 3-13: 3-14: 3-15: 3-16: 3-17: 3-18: 3-19: 3-20: 3-21: 3-22: 4-1: 4-2: 4-3: 4-4: 4-5: 4-6: 4-7: 4-8: 4-9: 4-10: Plant Cost Elasticities with Respect to Size for a Subcritical Unit ......... 85 Plant Cost Elasticities with Respect to Size for a Supercritical Unit ........ 86 Plant Cost Elasticities with Respect to Size for a Generic Unit ........... 87 Plant Cost Elasticities with Respect to Size for a Subcritical Unit ......... 88 Plant Cost Elasticities with Respect to Size for a Supercritical Unit ........ 89 Plant Cost Elasticities with Respect to Reliability for a Generic Unit ........ 90 Plant Cost Elasticities with Respect to Reliability for a Generic Unit ........ 91 Plant Cost Elasticities with Respect to Reliability for a Subcritical Unit ...... 92 Plant Cost Elasticities with Respect to Reliability for a Supercritical Unit . . . 93 Plant Cost Elasticities with Respect to Reliability for a Subcritical Unit ...... 94 Plant Cost Elasticities with Respect to Reliability for a Supercritical Unit ..... 95 Capital Cost Per KWH for a Subcritical Unit . . 103 Capital Cost Per KW for a Subcritical Unit . 104 Capital Cost Per KWH for a Subcritical Unit . . 105 Capital Cost Per KW for a Subcritical Unit . . 106 Capital Cost Per KWH for a Supercritical Unit . 107 Capital Cost Per KW for a Supercritical Unit . 108 Capital Cost Per KWH for a Subcritical Unit . . 109 Capital Cost Per KW for a Subcritical Unit . 110 Capital Cost Per KWH for a Supercritical Unit . 111 Capital Cost Per KW for a Supercritical Unit . 112 ix Table Table Table Table Table Table Table Table Table 4-11: 4-12: 4-13: 4-14: 8-2: B-3: B-4: B-5: Capital Cost Per KWH for a Subcritical Unit . 113 Capital Cost Per KW for a Subcritical Unit . . 114 Capital Cost Per KWH for a Supercritical Unit 115 Capital Cost Per KW for a Supercritical Unit . 116 Ordinary Least Squares Estimate of the Construction Cost Function .......... 134 Ordinary Least Squares Estimate of the Construction Cost Function .......... 136 Two-Stage Least Squares Estimate of the Construction Cost Function .......... 137 Ordinary Least Squares Estimate of the Construction Cost Function .......... 139 Ordinary Least Squares Estimate of the Construction Cost Function .......... 140 LIST OF FIGURES Figure 3-1: Possible Forms for the Incremental Heat Rate ..................... 50 Figure 4-1: Capital Cost Per KW ............. 118 Figure 4-2: Capital Cost per KWH ............. 119 xi CHAPTER 1 INTRODUCTION In this dissertation we show that the existence of economies of scale with respect to the construction costs of coal-fired generating units depends on the interaction of the size and reliability of the unit. The costs of building coal-fired units is characterized by economies of scale at low levels of unit reliability, constant returns at higher levels of reliability, and diseconomies at very high levels of reliability. This result is in sharp contrast to the conclusions reached by all other researchers and is of interest for a number of other reasons. First, our results are derived by explicitly taking into account that reliability, as measured by equivalent availability,‘ is an attribute of coal-fired units and in general is inversely related to the size of the unit. Second, we recognize the simultaneous nature of the choice of the attributes of a generation unit and its construction cost. Third, the Federal Energy Regulatory Commission (FERC) has proposed changes in policy which could substantially deregulate the generation of electricity. The proposals deal with competitive bidding for new generation capacity, independent power producers, and the administrative determination of avoided costs. A major concern under all-source bidding is how to evaluate and weigh the price and nonprice characteristics of each proposal when ranking the bids. An important nonprice attribute to include when evaluating a bid for baseload generation capacity is the reliability or availability of the unit. Each of these reasons will be examined in greater detail below. 1 The Cost of Poor Unit Reliability A general result of previous studies is that there are scale economies in construction costs over the entire range of observed unit sizes.2 These studies ignore the ex ante design process in which reliability is a key parameter. As a result, these studies overlook the possibility that a relatively inexpensive baseload coal-fired unit to build may not be so inexpensive to operate if it is frequently out of service due to forced outages or necessary maintenance. The key issue here is the intensity with which a unit is used. Baseload units are meant to be operated at maximum capacity ' continuously. The capital intensive nature of baseload coal-fired generation means that the average total generation costs of a unit can be significantly reduced if the unit is used intensively. Electric utilities consistently increased the average size of new generating units until the mid-1970’s.3 This trend was based on a number of widely held propositions: construction costs per kilowatt of capacity fell as unit size increased;‘ operation and maintenance costs per kilowatt-hour (kwh) could be reduced by building larger units; and that new, larger units historically had lower heat rates. In general, however, there is a negative relationship between the size and reliability of a generating unit (see Table 1-1). There are a number of reasons for this inverse relationship. One is that the movement to larger units was accompanied by a movement to higher steam pressure conditions. Previous studies generally have found that increases in steam pressure conditions have been associated with higher forced outage rates.5 Second, similar types of outages are generally 3 Table 1-1. Average Equivalent Availability Factors in the United States, 1971-1980 Average Equivalent Iechnglogy - Unit Qaptgitx Attilabiltty Fgctor All fossil-fueled steam 79.61 100 - 199 MW 83.05 200 - 299 MW 80.32 300 - 399 MW 73.88 400 - 599 MW 72.02 600 - 799 MW 69.33 800 MW and above 68.49 Source: Joskow and Schmalensee, 1983 4 longer for larger units than for smaller units. This is due to the larger area and parts that have to be repaired. And third, more materials and equipment simply create more opportunities for breakdown.6 The reliability of a utility system is defined as the ability of the system to meet the demand for power at any given point in time. Individual generating unit reliability is one of the primary determinants of system reliability. The more frequent a generating unit breaks down, the lower the reliability of the system. Thus, the lower average reliability of larger units adds to a utility’s total system costs because additional capacity must be built if a given level of system reliability is to be maintained. Our primary concern is with total per-kwh generation costs at the level of the individual unit. The annual total generation costs of a unit consist of fuel expenses, capital-related costs, and labor expenses. In general these account for 50%, 40%, and 10%. respectively, of total generation costs. Annual capital-related costs are by definition fixed and are the product of the total construction costs of the unit and the annual fixed charge rate for the utility. The fixed charge rate basically consists of property taxes assessed on the unit and the cost of stocks and bonds issued by the utility to finance construction of the unit. A poor level of reliability means that the capital-related costs of a generating unit are spread over a lower level of output than if the unit is used more intensively. Thus, poor unit reliability results in higher average generation costs for the unit. 5 Poor reliability can also reduce the thermal efficiency of a generating unit.7 Good heat rate performance is related in general to a high level of utilization because heat loss is fairly constant at any load. So heat loss is relatively larger at low load than at a high load. Deratings also increase heat rates, because restarting a unit means that heat energy must be expended to reheat the boiler and other components. As a result, frequent deratings of a unit due to outages can be expected to increase the unit’s average fuel costs. The heat rates of large units are more likely to be adversely affected by frequent deratings because large units, in general, are more prone to outages. e t o h t n ribut u i n Co The decision to build a baseload coal-fired unit means that the utility is purchasing a piece of capital equipment with various engineering attributes. Therefore, when comparing different generating units (or any type of capital equipment for that matter), one should make adjustments for any differences in key attributes of the units. The basic concept is that the cost of a generating unit should depend on the attributes of the unit. A number of key design decisions that significantly affect the costs of building a baseload coal-fired unit have been identified in the engineering and economic literature.8 These are: the size of the unit, unit order and replication, coal type, steam pressure conditions (subcritical or supercritical), pollution control strategies, cooling method, and reliability. 6 Previous studies generally found that there are scale economies in construction costs over the entire range of observed unit sizes. However, these studies failed to include reliability as an attribute or characteristic of the units. Larger generating units tend to be considerably less reliable than smaller units. So one has to wonder whether large generating units have lower average construction costs per kw of capacity because of economies of scale or because of poor quality. The implication is that omitting unit reliability will bias the estimates of the construction cost function. A unit's attributes and construction costs are determined simultaneously. A utility might be expected to modify its choice of unit attributes if it knows something about the error term it faces in the construction cost function. This means that the choice of attributes will be correlated with the error term. This will result in ordinary least squares (OLS) estimates of the cost function being biased. (OLS is the most widely used estimation technique in previous studies.) If a complete model involves the simultaneous determination of attributes and cost, then simultaneous estimation techniques are necessary. Note that simultaneous equation error will occur only if the utility has some conception of the error term it faces. But it would seem to be unreasonable to assume that the utility is totally unaware of the direction and size of the error. After all, each major utility in the nation has considerable experience participating in the construction 7 of different types of generating units. Also, a utility that is considering building a generating unit can draw on the experience of other utilities that have recently built similar types of units. the Changing Elggtrjg Utjljty Entjnnnngnt Three controversial notices of proposed rule makings (NOPRs) were recently issued by the FERC. The NOPRs deal with competitve bidding for new generation capacity, independent power producers (IPPs), and the administrative determination of avoided costs. The most controversial aspect of the NOPRs is that they would include IPPs as potential sources of new generation capacity under any competitive bidding programs. A major concern under any all-source bidding program is, how to evaluate and weigh the price and nonprice characteristics of each proposal when ranking the bids.9 An important attribute to include when evaluating a bid for baseload generation capacity is the reliability or availability of the unit. Baseload units are meant to be operated at maximum capacity whenever they are available. Each generating unit design is likely to have a different level of reliability. Also, each design can enhance reliability by adding redundancy to key components and/or by specifying the use of more reliable but more costly materials and equipment. Thus, it is extremely important to determine the consistency between the design of the unit, its construction cost, and its reliability. Numerous states also have implemented or proposed performance 0 standards for individual generating units.‘ The two most common criteria used to measure unit performance are equivalent availability 8 and heat rate. Utilities operating units that are found to be efficient are financially rewarded, while utilities with units that fail to meet specified minimum performance levels are penalized. One possible problem is that imposing minimum standards for a narrow range of performance criteria can create perverse incentives for the utility. For example, the utility might be willing to incur excessive costs in areas outside the incentive program so as to improve performance in the targeted areas. In this context, it is important to understand the extent to which there is a tradeoff between the reliability and the construction costs of a generating unit. The existence of such a tradeoff would call for regulatory policies focused on a utility’s design and construction decisions. If, on the other hand, unit performance is a random variable or a function of utility maintenance policies, then different regulatory policies would be necessary. nethodolggy When comparing pieces of capital equipment it is necessary to control for all relevent engineering characteristics. Most previous studies have treated the capital embodied in generating units as if it was homogeneous. Other studies have disaggregated the attributes of generating units along the dimensions of unit size and steam pressure conditions (or heat rate). These studies ignored the ex ante design and construction process in which reliability is a key parameter. As a result, these studies overlooked the possibility that a relatively inexpensive coal-fired unit to build may not be so inexpensive to operate if it is frequently forced out of service due to mechanical 9 failures. This is especially relevant given the capital intensive nature of baseload electric power generation which means that average total generation costs can be significantly reduced through intensive utilization of the unit. The central feature of the model developed here is that the cost of a generating unit depends on the engineering characteristics of the unit. Thus, emphasis will be placed on a multidimensional description of capital equipment that includes reliability as an attribute. We argue in Chapter 3 that the traditional neoclassical production model is inappropriate when capital has multiple attributes. Therefore, we have developed an engineering cost function that is flexible enough to allow all major engineering characteristics to be included. A critical review of the literature is presented in Chapter 2. This is followed by a presentation of the theoretical basis for the structure of our model in Chapter 3. There we argue that minimizing a unit's annual total per-kwh generation costs can be approximated by minimizing its annual capital cost per-kwh. This is based on the concept that intensive utilization of a unit not only spreads its annual capital-related costs over a higher level of output, but average per-kwh fuel costs are also reduced. We have developed an engineering construction cost function which includes reliability as one of the characteristics of a generating unit. This model enabled us to determine the cost minimizing combination of unit size and reliability while accounting for other important engineering attributes. Chapter 3 also includes a specification of the construction cost model and a discussion of error structure and estimation technique. It 10 concludes with econometric estimates of the construction cost function and an examination of the elasticity of per-kw construction cost with respect to unit reliability. In Chapter 4, we show (assuming that whenever a unit is available it is used) how annual capital costs per-kwh change for various combinations of unit size and reliability. Chapter 5 provides a summary of our results and ideas for further research. CHAPTER 2 SURVEY AND CRITIQUE OF THE LITERATURE The electric generating industry has been the subject of a large number of econometric studies of its production process. This is a result of the capital intensive nature of the generation process, the rapid technological advancement embodied in the generation equipment, and the abundance of detailed data at the plant and firm levels due to federal and state regulation of the electric utility industry. This review concentrates on that part of the literature which examines the capital cost of steam electric generating units. Emphasis is placed on the methodologies and data used in the studies that are reviewed. Particular attention is placed on the fact that few studies have properly addressed the heterogeneity of capital equipment and its role as a channel for technological advancement in the electric generation process. The Basic Prodnctjgn Procgtt and Igghnnlngigal Change Electricity is generated by a process that involves transforming energy from one physical state to another. The technology for transforming fossil fuel into electricity using steam turbines is well developed. Fossil fuel is burned in a furnace to generate heat. Pressurized high-temperature steam is created by transferring the heat to water circulating within an enclosed boiler. The pressurized steam is expanded through a turbine which turns a generator to produce electricity. The steam is then cooled in the condenser and returned to 11 12 the boiler to repeat the cycle. Thus, the energy transformation process can be divided into four stages--fuel combustion, steam generation, steam expansion, and power generation." Each stage of the production process is represented by a different piece of capital equipment. It is here that capital heterogeneity is introduced. The furnace is linked to combustion, the boiler to the creation of steam, the turbine to steam expansion, and the generator to the production of electricity. Each piece of capital equipment is purchased with numerous engineering characteristics which are substituted for one another at the design stage of the construction project. This causes heterogeneity at the individual component level, but heterogeneity is also created at the generating unit level by the physical linking of the components. As a result, a generating unit "represents a series of individual and joint optimizations that are reflected in the designs” of the individual components and the unit as a whole.12 Another source of capital heterogeneity is the innovation process itself. Traditionally the manufacturers of electrical equipment have played a key role in the development of technological innovations in electric power generation. This means that the vast majority of technological innovations have been capital-embodied."3 Electric utilities participated in the innovation process by being among the first to purchase the equipment and use it under actual operating conditions. As the innovation proves itself technically and l3 economically it is gradually implemented by other utilities. As a result, a number of technologies can and do coexist at any given time in the industry. It is also important to note that technological innovation and ‘ The primary average unit size are positively correlated over time.1 goal of technological innovation has been to improve the thermal efficiency of the production process. The desire for increased thermal efficiency led to continued efforts to increase steam pressure and temperature conditions. Table 2-1 shows the steam pressure conditions of all coal-fired units placed into commercial operation between 1950 and 1982. This table shows that the movement to higher pressure (more technologically advanced) units occurred only gradually. Table 2-2 shows the size distribution of the corresponding units. Table 2-2 shows that average unit size increased rapidly until the early 1970’s. Together the tables show that the movement to higher pressure (more technologically advanced) units was accompanied by a movement to larger sized units. Table 2-1. Capacity Additions by Technological Group and Year: 1950-1982 (% of New Capacity) Period Turbine Throttle Pressure Groups (psi) l§QQ_Qr_Le;§ 1899 2999 2999 3599 1950-1954 39 45 13 2 0 1955-1959 10 32 36 20 1 1960-1964 2 21 20 45 12 1965-1969 2 8 1 46 42 1970-1974 0+ 5 0+ 32 62 1975-1980 0 6 1 62 31 1981-1982 0 2 4 88 6 Source: Joskow and Rose, 1985 14 Table 2-2. Size Distribution of New Coal Capacity Year: 1950-1982 (Mwe) Number of New Period Mean Minimum Maximum Units Installed 1950-1954 124 100 175 99 1955-1959 168 100 335 175 1960-1964 242 100 704 104 1965-1969 407 103 950 100 1970-1974 591 115 1300 109 1975-1980 545 114 1300 127 1981-1982 517 110 891 41 Source: Joskow and Rose, 1985 The main point is that the use of vintages to define periods of technologically homogeneous capital in the electric generation industry is likely to be inadequate. Tables 2-1 and 2-2 indicate that there are a number of technologies in use at any point in time, and that unit size and advanced technology are closely related. Thus, failure to adequately control for technology and size is likely to bias any parameter estimates. As a result, the studies reviewed here are classified into two groups--those studies that explicitly take into account or somehow control for capital heterogeneity when estimating the construction cost function parameters and those studies that do not. 0:: .1 .1 F. . ' o--r '1 - . .-i al -te --:neit Komiya (1962) studied the ex ante production function for steam electric generation and sought to explain shifts in the production function due to technological change. His sample consisted of 235 new 15 plants built between 1938 and 1956. The plants included both single and multiple units. The sample was divided into eight vintage-fuel type groups. Each fuel type, coal and noncoal, was divided into four technological vintage periods: 1938-45, 1946-50, 1951-53, and 1954-56. The idea was that each plant that entered commercial operation in a particular period embodied the best technology available at the time. Any differences in the production function across vintages would be evidence of technological change. Komiya estimated a Cobb-Douglas production function within each cell, but he concluded that the technology did not allow input substitution when the function performed poorly. He then estimated a Leontief type, or fixed proportion, model within each cell. YF - AF + BFX, Yc - Ac + BCX, + BNX2 YL - AL + BLX1 + BNX2 Where, YF - natural log of fuel input, total BTU’s, per generating unit when operated at full capacity, Yc - natural log of average equipment cost per generating unit in constant dollars (Note that the cost of structures and land were excluded.), YL - natural log of the annual average number of employees per generating unit, X, - natural log of the average size of the generating unit in megawatts, X2 - natural log of the number of generating units in the plant. l6 Komiya found that economies of scale at both the unit and plant levels were important factors in declining input requirements over time. Scale elasticities at the plant level for fuel and capital were estimated to range between .80 and .85. The scale elasticity with respect to labor was estimated to range between .50 and .60. Technical change was found to have little impact on capital or fuel input requirements. The effect of technological change was to reduce labor input by 46 percent from vintage 1938-45 to vintage 1954-56 for coal plants of a given size. There was also a significant difference in capital equipment requirements of equal sized coal and noncoal plants. The major weakness in Komiya’s study is the use of vintage cells to 5 As noted earlier, a characterize periods of homogeneous technology.1 number of technologies coexist at any given time in the industry. Also, improvements in technology are associated with increases in average unit size. This could cause his capacity parameter estimates to be biased. Barzel (1964) estimated log-linear input demand functions for fuel, labor, and capital. His sample consisted of 220 plants that entered commercial operation between 1941 and 1959. Each plant’s annual data was observed from its first full year of operation until 1960 or until there was a major change in the plant. The capital input demand equation is: 4 18 1'09 Pk I iE‘I bill 09x. 41-h}; b'x' Where, PK - total undeflated value of plant including equipment, structure, and land, X, - plant size measured in kilowatts, 17 X.2 - labor price observed in first full year of operation, X, - fuel price observed in first full year of operation, X, - plant factor in first full year of operation, X5“, - vintage dumies. Barzel includes the ex post plant factor as a proxy for the desired rate of utilization of the plant. He appears to be the first to recognize that plants with higher levels of desired utilization must have components which can handle the added stress, thus requiring more capital investment.16 Barzel finds that the coefficient of the size variable is .815. He concludes that there are economies of scale in the capital cost of the plant since the coefficient is significantly smaller than unity. He also estimated that the elasticity of plant investment with respect to the plant factor was .117. As a result, he concludes that quality is an important determinant of the costs of capital equipment. A major shortcoming of Barzels’ study is the use of vintage dummy variables. The dummy variables were included to shift the intercept over time in response to technological change, but there are at least two problems with this methodology. First, the shifts are partly due to inflation since Barzel used the total undeflated value of the plant as the dependent variable.17 Second, the period of time covered by his sample was one of considerable technological change and, given the deliberate pace of innovation in the industry, there is likely to be a number of technologies in use at any given time. Again, technological 18 change and the size of plants or units is correlated so that poor treatment of technological change can seriously bias the econometric results. Another problem with Barzels’ study is that the ex post plant factor observed in the first full year of operation is likely to be a poor proxy for the level of desired utilization for two reasons. First, availability and unit size are inversely related, while unit size and desired utilization generally are positively correlated. Thus, the ex post plant factor may understate the level of desired utilization due to ° Second, generating units the declining availability of larger units.1 may go through a break-in period the first year or two of commercial operation. The break-in period may be characterized by high forced- outage rates and derating or cycling of units meant for baseload operation." Galatin (1968) estimated input requirement functions for fuel, labor, and capital. His sample included 158 plants which entered commercial operation from 1920 to 1953. Only plants with units of the same vintage and size were included in the sample. The sample was divided into 12 vintage-fuel subsamples so that the effects of scale and technological change could be examined across the vintage cells. The six vintages were 1920-24, 1925-29, 1930-39, 1940-44, 1945-50, and 1951-53. Galatin postulated the capital cost of a generating unit is a function of the size of the unit and the number of units in the plant. The functional form was specified as: CT/N or CE/N - A,N + A,"2 + A3N3 + A,x,< 19 Where, CT - total undeflated capital cost of a plant including land, structures, and equipment, CE - total undeflated equipment cost of a plant, N - number of units in the plant, XK - size of each unit in megawatts. The capital cost function was estimated with data covering the vintage fuel-type cells 1945-50 and 1951-53, so that costs for land, structures, and equipment ”may be assumed to relate to approximately the same period."20 Galatin found that total capital cost and equipment cost per generating unit increased with the size of the unit. He also found that total capital cost and equipment cost per generating unit for coal-fired plants in the 1945-50 vintage fell as the number of units in the plant increased from one to three units, and increased as the number of units at the plant increased beyond three. Average costs per generating unit for mixed fuel-type plants of 1945-50 vintage and noncoal plants of 1951-53 vintage also fell as the number of units in the plant increased from one to two units, and then rose as the number of units increased beyond two.21 There are a number of problems with Galatin’s study. One is that the analysis of capital input is only applicable to plants composed of units of the same size, vintage, and fuel type. Secondly, the sample includes plants with units ranging in size from 4 MW to 150 MW. However, Galatin fails to recognize that desired utilization generally increases with unit size, and that the desired level of utilization, independent of unit size, is an important determinant of plant capital 20 costs.‘22 Thirdly, Galatin used vintages in an effort to control for the effects of changing technology. The primary objective of Huettner’s study (1974) is to examine the effects of technological change and plant capacity on the average investment required per unit of capacity. Huettner’s sample consisted of 391 plants divided into 13 vintage time periods from 1923-1968. Within each of the vintage cells he estimated an average capacity cost equation which included fuel type dummies and the reciprocal of the size of the plant as the primary explanatory variables. Huettner used stepwise regression analysis due to a conflict between the number of explanatory variables and the number of observations within each vintage cell. Huettner did some preliminary testing of the model on a subsample in order to reduce the number of explanatory variables to be considered when using stepwise regression analysis for the entire sample. The subsample consisted of 185 subcritical, coal-fired plants of full indoor construction. The subsample ranged from 5 observations to 30 observations per vintage period and averaged 14 observations per period. Due to the small number of observations in some of the vintage cells, Huettner included only three explanatory variables in the average capacity cost equation estimated with the subsample. The three variables chosen were the number of units in the plant, the fuel consumption of the plant, and the reciprocal of plant capacity. Huettner included the fuel consumption variable, as measured by the plants average heat rate, to test whether load type has an effect on average capacity cost. He noted, 21 Generating plants may also be classified as base-load plants, cycling plants, and peak-load plants. Base-load plants are designed to operate at maximum fuel efficiency without being shut down for long periods of time. This may increase unit capacity costs (UCC) above that of cycling plants which are designed to operate at the highest fuel efficiency consistent with rapid warm-up and cool-down during frequent shutdowns. Cycling plants might tend to have lower UCC due to looser tolerances on equipment, as for example on the turbine bl ades.” Huettner found the fuel consumption variable was generally of the appropriate sign, but statistically significant in only 2 of 13 vintage periods. He noted there was a high degree of correlation between plant heat rate and plant capacity which meant that multicollinearity was likely to be a problem. As a result, Huettner excluded the fuel consumption variable from the stepwise regression analysis of the full sample. The number of units variable was included by Huettner because "some studies argue that quantity discounts are a significant factor affecting equipment costs in generation plants: hence, one would expect UCC to decline as the number of units increased.“" Huettner found that plants with multiple units had lower average capacity costs in 10 of the 13 vintage periods, but the coefficient was statistically significant in only 3 of these 10 periods. It should be noted that this variable was dropped from the remainder of the analysis due to its poor performance. As a result, Huettner’s study analyzes plant-level economies instead of unit-level economies. Huettner found that average capacity costs generally declined as the size of the plant increased. The capacity variable coefficient was positive in 9 of the 13 vintage periods and statistically significant in 7 of these periods. Based on the performance of the capacity variable, 22 it became the primary variable of interest in the stepwise regression analysis of the full data set. Plant characteristics used as explanatory variables in the capacity cost equation for the full sample included fuel-type dummies, a full-indoor construction dummy, a supercritical dummy, and the reciprocal of plant capacity. Huettner found that plant fuel-type is a significant determinant of the average capacity costs of generating plants. Coal-fired plants were more expensive to build than oil-fired plants, and oil-fired plants were more costly than gas-fired plants. Supercritical plants were represented in only the 1959-60, 1963-65, and 1966-68 vintage periods, but were significantly more expensive than subcritical plants in 2 of the 3 periods. Huettner also found that average capacity cost declined with increased plant capacity in every vintage period since 1940. There are a number of problems with Huettner’s study. First is the use of vintages to define periods of homogeneous technology. Second, Huettner recognized that baseload and non-baseload plants have significantly different design characteristics due to differences in desired utilization, and that baseload Operation and plant size are highly correlated. But the estimated plant size coefficients will be biased by his failure to control for differences in desired utilization, and the mixing of baseload and non-baseload plants in the sample. Third, Huettner recognized that the reliability of a generating unit is inversely related to its size and “that the lower reliability of large units reduces their economic attractiveness.“” But he fails to include reliability as an explanatory variable so the parameter estimates may be 23 biased. As a result, it is impossible to determine whether large units cost less to build due to economies of scale or poorer quality as reflected by lower reliability. Wills (1978) recognized the non-homogenous nature of capital equipment in the steam-electric generating industry and noted the construction cost of a plant will be a function of its attributes. Thus, Wills estimated an hedonic cost function for steam electric plants. His sample included 156 plants which entered commercial operation between 1947 and 1970. The observations were divided into eight vintage cells. The attributes initially considered by Wills were plant capacity, average unit capacity, unit fuel efficiency, and the average number of employees that worked in the plant. He also noted that plants could be divided into groups based on construction-type, fuel-type, and whether the plant contained a single unit or multiple units. However, Wills concluded from a preliminary analysis of the sample that the effects of the dummy variables could be restricted to an interaction with the capacity variable. He also excluded the fuel efficiency variables because they were collinear with the size variable. As a result, the hedonic capital cost equation was of the following form: PRICE . a0 + (a, + BI + Y, + 5,, + Nc)Cap + ¢2CAP2 Where, PRICE - total nominal cost of the plant, CAP - plant capacity, B.- one if the plant is of full-indoor construction, zero otherwise; 24 n - one if the plant has only one unit, zero otherwise; a, - one if the plant burns coal, zero otherwise; 1% - dummy variables that represent the vintage of the plant. The model was normalized by plant size in order to remove a problem with heteroskedasticity. The model became: Price/Cazp - «0(1/Cap) + (a, + B, + YI + 5,, + N) (Cap/Cap) + «2(Cap /Cap) Wills argued that all of the explanatory variables were exogenous except the capacity variables. He believed it likely that plant size was correlated with the error term. Thus, he used instruments for unit size multiplied by the number of units in the plant as instruments for plant size. The instruments for plant size included the "expected absolute growth in demand for electricity from the utility times the number of units, the price of fuel times the number of units, the price of fuel squared times the number of units, and expected demand growth times the price of fuel times the number of units.”3 The hedonic cost function was estimated using random components instrumental variable estimation and random components estimation. Wills found that economies of scale in plant cost per unit of capacity are essentially exhausted at plant capacities of about 100 megawatts. He also found that vintage effects were not important determinants of plant cost per unit of capacity. There are a number of problems with Wills’ study. Once again there is the problem of using vintages to define periods of homogenous technology. Also, there is the problem of mixing baseload and non-baseload plants in the sample. The sample includes plants that range in size from 5 MW to 950 MW. Unit size and desired utilization 25 intensity are correlated but each, independent of the other, is an important determinant of the cost of building a generating unit. Thus, failure to control for desired utilization and mixing baseload and non-baseload plants in the sample will bias the coefficient estimates. ModelLWhich Avoid titfi Yintagg Problem” Stewart (1979) is concerned with the relative importance of capacity utilization and size of plant in determining the average cost of generating electricity. He adopts a quasi-engineering approach by incorporating technical information on the characteristics of the capital equipment and production process. A quasi-engineering approach is used because the investment decision of the utility "will encompass determining both the segment of total demand the new plant will serve and the configuration of the new plant." The load increment for which the new plant is designed and built is "defined by an instantaneous rate" (the size of the new plant), K, and the number of yearly hours the plant will produce at that rate (or duration).”’ Stewart defined the expected cumulative output of the plant as: 0 - 8760bK Where, 8760 - number of hours in a year, b - expected plant factor, K - capacity of the plant measured in megawatts. Stewart assumed that the range of technology available to the utility could be fully defined by the size and thermal efficiency of the 26 generating unit. 50 the average capacity cost (cost per KW) function was written as: P, - Pk(¢,k) The average capacity cost of a plant was expected to increase at an increasing rate with the fuel efficiency, a, of the plant. Stewart also expected the average capacity cost of a plant to decrease over some range of plant size. As a result, the utility was faced with the problem of choosing the cost minimizing level of fuel efficiency for a unit designed to meet an expected load increment defined by b and K. The cost minimizing heat rate was given as: a' - g(K,b,PF,r) Where, ¢° - cost minimizing heat rate (BTU/kwh), PF - price per BTU of fuel, r - cost of capital. Ex ante total generation costs are derived by substituting a' into the following cost function. TC°(K,b,PF,r) - g(K,b,PF,r)8760bKPF + rPK(g(K,b,PF,r),K)K Where the first part of the total cost function represents ex ante fuel costs and the second part represents ex ante capital cost. The estimated plant cost function was combined with the plant’s size, load factor, and factor prices to compute the cost minimizing heat rate and the average total cost per Kwh for each plant. Stewart found that plant utilization intensity was the dominant factor in reducing 27 average generation costs, while plant size was found to have relatively little impact. Our primary attention will be on Stewart’s plant cost function. He estimated a translog Specification of the cost of plant function: ln PK - A + Y, ln(a - T.) + Y... (m. - m2 + YK ln(K) + Y,<,((ln(K))2 + Ydln(K)ln (a - I.) +2Y,X,+u I Where, PK - nominal land and equipment cost per KW of the generating unit (excluding structures), - average heat rate of the unit (BTU’s/Kwh), - asymptotic heat rate (6000 BTU/Kwh), K - capacity of the unit (Kw), X.- regional dummies and natural log of the number of units in a given plant. The plant cost function was estimated using a sample of 58 plants which entered commercial operation between 1970 and 1971. The sample included plants with single units or multiple identical units. The sample consisted of 19 steam electric plants and 39 gas turbine plants. Stewart estimated two forms of the cost-of-plant function. One included only a dummy variable to differentiate between the two types of generating plants. Thus, the coefficients of the size and heat rate variables were restricted to be equal for each type of plant. The second specification allowed the plant type dummy variable to interact with the size and heat rate variables and their interaction variable. 28 The plant type dummy was not allowed to interact with the squared size or squared heat rate variables. Stewart found plant equipment cost fell at a decreasing rate as heat rate increased (thermal efficiency decreased) for both types of plants. He also found plant size had very little impact on the cost of equipment for either type of unit. Plant costs of gas turbines at the mean heat rate declined with unit size only for units smaller than 70 MW. Average equipment cost for steam plants was found to increase at a ”relatively modest rate” over most of the reasonable range of unit sizes and fuel efficiencies. We believe there are a number of flaws in Stewart’s study. One involves the estimation of a single quadratic function to approximate both technologies. Steam-electric and gas-turbine technologies are quite different so there is little reason to believe that scale economies will be at all similar for the two technologiesf” A second problem involves the mixing of baseload and non-baseload plants in the sample. The steam electric plants range in size from 200 MW to 800 MW and the gas turbines range from 20 MW to 187 MW. Failure to control for different levels of desired utilization means the size coefficient will be biased. Another problem relates to Stewart’s failure to include reliability as an attribute of a generating unit in the cost of plant function. He is interested in the relative importance of capacity utilization and plant size in determining the cost of generating electricity. However, he fails to recognize that utilization depends on availability and that availability is an attribute of a unit. 29 Komanoff (1982) estimated a log linear average construction cost equation. The sample consisted of all U.S. coal-fired units, 100 megawatts or larger, which entered commercial operation from January 1972 through December 1977. The units ranged in size from 114 MW to 1300 MW and averaged 608 MW. Fifteen of the units had flue gas desulfurization devices or scrubbers. Real capital costs per kilowatt, excluding AFUDC, was regressed on a number of explanatory variables using ordinary least square (OLS). Unfortunately, Komanoff shows the econometric results for only the statistically significant variables. All other variables were excluded from the final regression equation and were simply listed as having been tried in alternative specifications of the regression equation. Insignificant variables included the presence of cooling towers, supercritical boilers, and unit size. Komanoff found the presence of scrubbers added 26 percent to the capital cost of a generating unit. He also found that units which share a plant site with an identical unit have lower capital costs than non-multiple units. Capital costs were found to increase approximately 4 percent for each later year that the unit entered commercial operation. Other significant explanatory variables were regional dummies, which probably reflected regional variations in construction- type, and the cost of labor. Units built in the Midwest or Northeast are more likely to be of full-indoor design than units built in the Southwest or Southeast. Interestingly, Komanoff found capital costs to be significantly correlated with ownership by two large utility holding companies: the 30 Southern Company and American Electric Power (AEP). Generating units built by AEP were found to be 18 percent more costly than other comparable units, while Southern Company’s units were 15 percent less costly to build than other Southeast units. Komanoff argued these differences were probably due to the two utilities’ unit design and operation philosophies. AEP has a reputation for building highly reliable and efficient units, while Southern Company tends to build units with below-average reliability and fuel efficiency. As a result, Komanoff concluded unit reliability is a significant determinant of a units’ capacity costs.30 One problem with Komonoff’s study has to do with mixing baseload and non-baseload units in the sample. That this may be a problem is indicated by the inclusion of units as small as 114MW in the sample. Baseload and non-baseload units have different levels of desired utilization and, thus, different engineering characteristics which are likely to effect the capital costs of each type of unit. Failure to account for desired utilization can seriously bias the parameter estimates since unit size and desired utilization are generally correlated. Another problem arises from Komanoff’s failure to properly account for unit reliability in the capital cost equation. It is necessary to control for different levels of desired utilization and to include a reliability variable. This prevents the size coefficient from being biased since size and reliability are inversely related. Komanoff also implicitly recognizes the simultaneous nature of the relationship between unit reliability and capital costs. He notes that higher 31 initial capital cost due to conservative design philosophy and, thus, higher unit reliability may result in lower total costs over time. The endogenous nature of unit reliability means simultaneous estimation techniques are necessary for unbiased parameter estimates. Perl (1982) is concerned with calculating the levelized cost of electricity from coal-fired plants. ”Levelized costs are a constant annual charge for electricity which yield the same present value as actual annual charges over the life of a plant."31 Current accounting practices and the capital intensive nature of coal-fired plants causes high front end costs. Levelized costs, he argues, better reflect life time electricity costs. Perl’s methodology involves econometrically estimating capital costs, non-fuel operating and maintenance costs, availability factors, and heat rates for coal-fired units. These were regressed on the engineering characteristics of the units using OLS. His sample included 245 coal-fired units which entered commercial operation between 1965 and 1980. These components of cost and performance were combined in the following model to produce the levelized cost of electricity: I RR.(1+ a)' 1 '3‘ * I: G.(1 + a)'/(1 + r)' (1 + r)"' i=1 Where, RR- revenue requirement in year i, G.- generation in year i, N - book life of the plant, M - number of years from current date to start of commercial operation, 32 c - nominal discount rate, r - inflation rate. Perl assumed that plant life was 30 years, 1985 to 2014. He also assumed when forecasting capital and O & M expenses per kilowatt-hour that a unit is used if it is available. We will focus our attention on Perl’s average capital cost and equivalent availability equations. The dependent variable in the equivalent availability equation is the logit transformation of the equivalent availability factor. This transformation restricts the estimated variable to the interval from zero to one. The sample used to estimate the equation consisted of annual observations of equivalent availability for ”a large sample of coal units operating from 1969 through 1977.“” Observations for the first full year of commercial operation of a unit were excluded to avoid any bias due to break-in problems. Explanatory variables included the year the unit entered commercial operation to represent vintage, the age of the unit, the reciprocal of unit size, and numerous dummy variables. The dummies indicated a supercritical boiler, a balanced draft boiler, a cyclone boiler, boiler manufacturer, turbogenerator manufacturer, and whether the unit was built by the particular architect-engineer (A-E) or utility represented. Perl found equivalent availability tended to decline with increased age and larger unit size. Subcritical units were also substantially more reliable than comparable supercritical units. Perl also noted that there appeared to be significant differences in the availability of units built by particular A-Es and utilities. 33 Perl estimated a log linear specification of the capital cost equation. The dependent variable is the natural log of real capital cost per kilowatt excluding AFUDC. The sample consisted of 245 coal-fired units built between 1965 and 1980. Explanatory variables included unit size, regional wages, the date the unit entered commercial operation, and dummy variables indicating supercritical boilers, scrubbers, and whether the unit was designed and built by a particular A-E or utility. Perl found average capital costs were significantly related to unit size, the presence of scrubbers, and regional wages of construction labor. Supercritical units were found to be considerably more costly than comparable subcritical units. He also found average capital costs varied depending on which A-E or utility built the unit. Perl argued that this indicated the more experience the A-E had designing and building generating units, the lower the capital cost of a unit. Perl concluded that economies of scale are very limited for subcritical coal-fired units. The higher average construction costs of smaller units are offset by their higher equivalent availability. Thus, the cost of electricity from subcritical units is basically constant when unit size is beyond 200 megawatts. In contrast, Perl finds that supercritical units are characterized by economies of scale. Average capital costs fall with increases in size while availability remains roughly constant. As a result, Perl concluded that subcritical units are cheaper to build and operate than supercritical units when unit size is less than 800 MW, and that the reverse is true when unit size increases beyond 800 MW. 34 We believe there are a number of problems with Perl’s study. One problem relates to the use of A-E dummy variables and Perl’s conclusion, when these dummies prove to be statistically significant, that A-E experience is a significant determinant of the capital cost of a unit. A variable measuring experience must be included in the construction cost equation to separate the effects of experience and any attributes of particular A-Es. Characteristics of particular A-Es, such as design philosophy, choice of vendors for major components, and the quality of the units, may be correlated with experience. So both experience and A-E specific characteristics must be included to avoid biased parameter estimates. Another problem relates to Perl’s failure to include availability in the capital cost equation even though he recognizes that unit size and equivalent availability are inversely related. This will cause the parameter estimates to be biased and makes it difficult to determine whether large units cost less to build due to economies of scale or poorer quality. Houldsworth (1985) examined the relative importance of capacity utilization and plant size in determining the average cost of generating electricity. He adopted the same quasi-engineering approach used by Stewart,‘33 except for how the level of utilization is included in the model. Recall that Stewart defined the expected cumulative output of a generating plant as: 0 - 8760bk Where, 8760 - number of hours in a year, 35 b - expected plant factor, k - capacity of the plant measured in megawatts. It is also important to recall that Stewart’s sample consisted of a mixture of baseload and non-baseload plants which entered commercial operation during the period 1970-71. He used the plant factor observed in 1972 for each plant as a proxy for the expected plant factor. Houldsworth recognized the desired level of utilization is a significant determinant of generating plant construction costs. He also recognized that the ex post plant factor will probably understate the level of desired utilization. Plant size is positively correlated with desired utilization intensity, while equivalent availability is negatively correlated with unit size. Houldsworth also recognized that mixing baseload and non-baseload plants in the same sample is inappropriate since they have different levels of desired utilization. Houldsworth avoided these mistakes by restricting his sample to 32 coal-fired baseload plants which began commercial operation in the period 1972-1978. He also defined the level of utilization by the expected availability, a (k), since each unit was assumed to serve baseload demand. This meant that the expected cumulative output relationship became: 0 - 8760a(k)K Houldsworth combined the estimated plant cost function with the plant size, equivalent availability, and factor prices to compute the cost minimizing heat rate and the average total cost per kwh for each plant. The simulations conducted by Houldsworth indicated average total cost per kwh reached a minimum between 150 and 250 MW, and increased 36 moderately for larger sized units. Thus, Houldsworth concluded that declining availability offset the benefits of any reductions in heat rate and/or average construction cost per kw associated with units larger than 250 megawatts. Our primary concern lies with Houldsworth’s use of availability data published regularly by the North American Electric Reliability Council (NERC). These reports provide availability data that are cumulative over a ten-year period and are averaged over many types of units. The NERC data mixes units in the same size range even though they have considerable differences that significantly affect their reliability. Units within the same NERC size categories vary with respect to fuel-type (gas, oil, or coal), desired level of utilization (baseload or non-baseload), and in steam conditions (high or low steam pressure and termperature). ”The reliability data given are, therefore, average figures that reflect ’average’ hypothetical units.“” Joskow and Rose (1985) are interested in determining what impact unit size, differences in technology, tightened environmental restrictions, and the experience of utilities and A-Es has on the costs of building coal-fired generating units. They specify the construction cost model: LAC - :9?” AT, + b,LSIZE + bzRWAGE + baFIRST + b,SCRUBBER + b5COOLTWR + DBUNCONV + b7EXPERAE + b,EXPERU + b,EXPERI + S + U. Where, LAC - natural log of real cost per KW of a unit, net of AFUDC; 37 'L - one if the unit entered commercial operation in year t, and zero otherwise; LSIZE - natural log of unit size in megawatts; RWAGE - regional average union wage for construction workers in 1976; FIRST - one if the unit is the first unit on the plant site, zero otherwise: SCRUBBER - one if unit was built with a scrubber, zero otherwise; COOLTWR - one if the unit was built with a cooling tower, zero otherwise; UNCONV - one if the unit is not of full-indoor construction, zero otherwise; EXPERAE - the cumulative number of "like” units designed by the A-E being observed that entered commercial operation between 1950 and year t; EXPERU - utility experience since 1950; EXPERI - total industry experience since 1950; S - a seperate intercept term for each A-E. The data set consisted of 411 coal-fired generating units which entered commercial operation between 1960 and 1980. The units were divided into four turbine throttle pressure groups: 1800, 2000, 2400, and 3500 PSI. Subcritical units have steam pressures less than 3206 PSI, while supercritical units have steam pressure in excess of 3206 PSI. The units ranged in size from 100 megawatts to 1300 megawatts. Joskow and Rose treat this data set as a panel with individual generating units as observations over time on a cross section of A-Es. They believe there are A-E specific design characteristics common to units designed by a particular firm so they use fixed effects estimation to control for these effects. Fixed effects means estimating a separate intercept for each A-E. 38 It should be noted that Joskow and Rose specify a Cobb-Douglas relationship between cost and unit size. This forces the cost function to have a constant elasticity of unit cost with respect to size. Additional flexibility is added by allowing the size coefficient to take on a different value for each pressure group. The intercept is also allowed to vary across pressure groups. Joskow and Rose found significant differences between the cost characteristics of subcritical and supercritical units. Supercritical units are more costly to build than subcritical units except for large unit sizes. Only when unit size increases beyond 600 megawatts do supercritical units become cheaper to build than subcritical units. As a result, they conclude there "is no simple static tradeoff between unit size and construction cost: full exploitation of economies of scale in construction costs can only be achieved by moving from one technology to another. It would be wrong to think of static economies of scale independently of choice of technology.” They also found scrubbers and cooling towers added 15% and 6%, respectively, to the construction cost of coal-fired units. Experience was found to be numerically and statistically significant for supercritical units only. Average construction cost for a supercritical unit fell approximately 15% when the architect-engineer’s experience with that type of unit increased from zero to the average level of experience in the sample. We believe there are a number of problems with the Joskow and Rose study. One is the likelihood that baseload and non-baseload units, and their different levels of desired utilization, were mixed in the sample. 39 Again, the level of desired utilization, independent of unit size, is an important determinant of the cost of building a generating unit. Failure to control for desired utilization and mixing baseload and non-baseload units in the sample will bias the parameter estimates since the level of desired utilization generally increases with unit size. Joskow and Rose also note large units generally have lower equivalent availabilities than small units and that "especially poor performance is exhibited by the larger supercritical units."36 However, they fail to treat reliability as an attribute of generating units and thus exclude it from the construction cost function. As a result, it is difficult to determine whether large units cost less because of economies of scale or because of poorer quality. Schmalensee and Joskow (1986) were concerned with how the construction cost of a coal-fired generating unit varied with the quality of the facility. The two indices of quality were the units’ heat rate and equivalent availability. They used a two-stage estimation process. The first stage was concerned with obtaining estimates of unit-specific quality attributes from data on actual unit performance and operating characteristics that affect performance over time. A fixed effects model was used to obtain estimates of each of the two quality attributes which are supposed to enter the second stage of the process, estimation of a construction cost function. The sample used by Schmalensee and Joskow consisted of observations on 71 subcritical coal-fired units which entered commercial operation between 1960 and 1969. The units ranged in size from 218 MW to 709 MW. The sample also 40 contained operating performance data, heat rate and equivalent availability, for these units, for the years 1969 through 1977. The first stage consisted of two performance equations of the following form: REL - 0:, + WY, + V, EFF - 05, + WY, + V2 Where REL - -ln(1 - equivalent availability), EFF - -ln[(gross heat rate - 6000)/6000]. The W’s are matrices of exogenous variables that should affect intra-unit variations in performance over time. The variables included in W are: CAPU - deviation in output factor [-100X generation/(capacity x hours in service)] from the sample mean for all units, a measure of relative capacity utilization, AGE - unit age (calendar year - year unit entered commercial operation) minus three, BTU (MOIST, ASH, SULPH) - deviation of BTU’s per pound (percentage of moisture, ash, sulpher) of the coal burned from the sample mean for the observed unit. Age entered each equation quadratically to allow for the possibility that performance improves when a unit first enters commercial operation, and then decreases as the unit ages beyond some point. The D’s are matrices of unit--specific dummy variables that take on a value of one for a unit when the observations are associated with that unit and zero otherwise. Thus, the coefficients a, and 52 are the estimates of unit specific quality attributes used as explanatory variables in the construction cost equation. 41 Schmalensee and Joskow found unit performance deteriorated as units aged after a short break-in period. Reliability peaked after a year or less of Operation (note that age is measured as actual age minus three) and then fell, while fuel efficiency declined from the start of operations. Also, the coal characteristics variables were never statistically significant. Thus, intra-unit variation in coal characteristics appeared to have little effect on unit performance. Schamalensee and Joskow rejected the null hypothesis that unit qualities are identical. The estimated unit-specific coefficients of REL (the estimated elements of 5,) correspond to equivalent availabilities ranging from .6 to .97 and a mean of .84. The estimated unit-specific coefficients of EFF (the estimated elements of :2) correspond to heat rates ranging from 7,700 to 10,800 BTU/KWH and a mean of 9,000. The second stage consisted of estimating a construction cost equation of the form: AVCOST - f(SIZE, WAGE, BTU, TIME, EFF, REL). Where, AVCOST - natural log of unit capital cost in 1965 dollars per KW of capacity, SIZE - natural log of nameplate capacity in megawatts, BTU - natural log of unit-specific mean of BTU’s per pound of coal burned, WAGE - natural log of regional construction wage in 1965, EFF - design thermal efficiency of the unit (the estimated unit-specific coefficients, :2, as defined in the first stage), REL - design reliability of the unit (the estimated unit-specific coefficients, 5,, as defined in the first stage). 42 Schmalensee and Joskow estimated two specifications of the construction cost equation. The first specification was linear in the variables, except time which was entered as a quadratic. The second specification allowed the effects of reliability and fuel efficiency to interact with the quality of the coal burned variable (BTU). Each specification was estimated three different ways. One ordinary least squares (OLS) estimate was obtained by using unit-specific averages of observed heat rates and equivalent availabilities as the quality variables rather than the values (coefficients) estimated in the first stage. The second set of OLS estimates was provided by using the values (coefficients) estimated in the first stage. The third set of estimates was provided by an adjusted least squares technique developed by Schmalensee and Joskow. Schmalensee and Joskow found the quality attributes, EFF and REL, were statistically insignificant, and frequently had implausible signs and magnitudes. All six equations implied that increasing fuel efficiency reduced construction costs per unit of capacity. The adjusted least square estimates indicated REL had a positive impact on costs, but that it was never close to statistical significance. In the linear and interactive specifications estimated using OLS, REL had a negative insignificant coefficient. Schmalensee and Joskow found the size coefficients were statistically significant in the OLS estimates, but statistically insignificant in the adjusted least squares estimates. The magnitude of the estimated size coefficients did not differ very much and implied 43 that doubling unit capacity would reduce average construction cost per unit of capacity by between 10 and 12 percent. Schmalensee and Joskow are the first to include quality variables for both fuel efficiency and equivalent availability, but there are still a number of problems with their study. One problem relates to their inability to include a size variable in the first stage regressions, since it would be perfectly collinear with the unit-specific dummy variables.”’ Other things equal, equivalent availability falls as unit size increases. Unit size is also negatively correlated with construction cost per unit of capacity. Thus, use in the construction cost equation of an equivalent availability variable that fails to control for unit size may cause the parameter estimates to be biased. They also recognize there may be architect-engineer (A-E) specific variations in ex post performance given the level of construction costs and design performance levels, but cannot capture these effects explicitly due to a conflict between sample size and the number of explanatory variablesf” Again, these effects will be reflected in the fixed-effects estimates of the unit-specific quality variables of the first stage. M A review of the literature reveals that unit size, technological vintage, and fuel type have been viewed as the primary determinants of the construction cost per KW of capacity of a generating unit. A general conclusion of these studies is that there are economies of scale with respect to construction costs. 44 But this review also shows few previous studies have properly accounted for the desired utilization intensity of a generating unit. A majority of the studies mix baseload and non-baseload units in the sample and also fail to include the mode of operation (baseload or non-baseload) as an explanatory variable, so the estimated size coefficients are likely to be biased. Given that unit size and desired utilization intensity are positively correlated, it’s likely the estimated size coefficients are picking up the affect of moving from non-baseload to baseload operation, and not just the impact of unit size. Also, the vast majority of these studies fail to include reliability as an attribute or characteristic of generating units. They ignore the ex ante design process in which reliability is a key parameter. But the key issue is the intensity with which a unit is used. A poor level of reliability, especially for baseload units, means the capital-related costs of a unit are spread over a lower level of output than if a unit is used more intensively. Thus, these studies fail to recognize that an inexpensive unit to build may not be so inexpensive to operate. The studies by Perl, Houldsworth, and Schmalensee and Joskow (1986) are the only studies that include in their analysis the effects of unit reliability. Unfortunantly, each of these studies was flawed. Both Perl and Houldsworth fail to include availability in the capital cost equation even though they recognize that unit size and equivalent availability are inversely related. This causes their parameter 45 estimates to be biased and makes it difficult to determine whether large units cost less to build due to economies of scale or poorer quality. Schmalensee and Joskow (1986) were the only researchers to include equivalent availability as an explanatory variable in the construction cost equation. However, they used an estimate of equivalent availability that did not control for unit size. This is a significant problem since unit size and equivalent availability are, in general, negatively correlated. Thus, use of their equivalent availability variable in the construction cost equation may bias the estimated coefficient since it may be picking up the negative size effect. This review indicates a construction cost model must recognize the ex ante design and construction process in which reliability is a key parameter. Not only must the construction cost function include reliability as one of the attributes of a generating unit, but the model should also recognize that unit reliability is a function of numerous factors. The development of such a model is the subject of the next chapter. CHAPTER 3 DEVELOPNENT OF A GENERATING UNIT CONSTRUCTION COST AND RELIABILITY NODEL mm In this chapter we develop a model of the steam electric generation process that recognizes the multidimensional nature of capital embodied in baseload coal-fired generating units. The first section, the Heterogenous Nature of Capital, emphasizes how a utility’s choice of unit characteristics at the ex ante or design stage determines the ex post production relationships. Thus, the fuel-output relationship is fixed once the unit is built and it is fairly insensitive to the rate of generation. In the second section, the Model, we develop a model that highlights the capital-intensive nature of baseload coal-fired generation and the importance of intensive utilization if a unit’s average total generation costs are to be minimized. In the third section, Specification of the Construction Cost and Reliability Model, we develop a simultaneous equation model of unit construction cost per KW of capacity where average construction cost and reliability are endogenous variables. In the fourth section, Empirical Analysis, the data employed in the study is discussed and the estimation results are presented. 46 47 W - o f The cyclical nature of the demand for electricity has important implications for the nature of capital in the electric generating industry. The output of a generating unit can be thought of as having at least two dimensions. Power, the first dimension, is the instantaneous rate of output and is measured in kilowatts (KW). The second dimension is energy, measured in kilowatt hours (KWH). Energy is the product of a power level and the period of time (measured in hours) over which the unit operates at that level. Thus, energy is the cumulative level of output over a period of time. The demand for electricity fluctuates in a cyclical pattern over a day, week, or season. Generally, however, electric power is non-storable, so the supply of electricity must equal the demand for electricity at all times. Thus, a utility must install sufficient capacity to satisfy the maximum demand expected over the cycle. Given that the demand for electricity varies more quickly than generation capacity, a portion of the utility’s generation facilities will not be operated at maximum capacity at all times. As a result, generating units with the same maximum capacity may have different levels of cumulative output and units with the same levels of cumulative output may have different maximum capacities. In this environment it is reasonable to expect a utility that is building a new generating unit to consider both dimensions of output when making choices at the gt_nntg or 48 blueprint stage. Thus, the utility must decide what portion Of the total demand for electricity the unit will serve. This decision will then affect the size and desired thermal efficiency Of the planned unit. MW A utility faces a wide range Of production possibilities at the blueprint stage. Each blueprint represents a generating unit with different engineering characteristics such as unit size, unit type (baseload and non-baseload), reliability requirements, fuel type and quality, steam pressure conditions (an ex ante measure Of thermal efficiencyafi, pollution control techniques, unit life, expected capital cost, expected Operation and maintenance costs, and numerous other characteristics. But once the generating unit is built, the fuel-output and labor-output relationships are fixed. Thus, the utility faces a set Of gt_nntg production possibilities from which various engineering attributes are selected which shape the 95.29;; production rel ationship.40 Labor is heavily dependent on the design Of the unit and thus exhibits very little response tO variations in output. The Operational labor requirements are affected by the number and size Of units in Operation at a site. The choice Of fuel also affects the number Of Operational personnel needed, since it determines the fuel handling requirements. In particular, coal requires more labor input than does either Oil or natural gas. The number Of maintenance personnel also depends on the number and size Of units and the schedule Of routine maintenance, rather than the level of output. Routine maintenance is 49 scheduled on an annual basis and is geared to unit size, unit type, and the presence Of pollution abatement technologies such as scrubbers.‘1 The relationship between the flow Of fuel and output also depends on the design characteristics Of the generating unit. Thermal efficiency increases (heat rate falls) with the temperature and pressure Of the steam, the thermal efficiency Of the boiler, the efficiency Of the turbine, and the size Of the boiler and the turbine. Once the unit is built, marginal fuel use, or the incremental heat rate, is related to the capacity utilization Of the unit. According to Bushe (1981, Chapter 4) there are a number Of alternatives for the form Of the incremental heat rate function for a single generating unit (see Figure 3-1). He notes that, it is likely that the form depends on the design Of the unit and large baseload units may have forms like (d) or (e) Of Figure 3-1, while peaker units may have forms like (c). Since we are concerned only with baseload units in this study, we will assume that the relevant forms are (d) or (e). This assumption means the incremental heat rate is fairly insensitive tO changes in load within the normal Operating range Of a baseload unit. As a result, the amount Of fuel required is proportional tO the rate at which the unit produces electricity.“Z Thus, the fuel-output and labor-output relationships are conditional upon the design characteristics of the generating unit. Once the unit is built there is very little Opportunity for substitution among the inputs, so the technology for generating electricity is putty-clay. 50 di .91. — do do (a) L] (b) q .91. dq (c) q .eL EL dq dq /' _/ (d) (1 (c) q Figure 3.1. Possible Forms for the Incremental Heat Rate df/dq = incremental heat rate q = load Source: Bushe (1981 ), Chapter 4 51 ener The traditional neoclassical production model assumes that input capital is homogeneous (i.e., one unit Of capital services is equal to any other unit Of capital services). This assumption implies that a unit Of capital can be represented by a scalar measure such as size or the dollar value Of the capital equipment. We believe, however, that the heterogeneous nature Of capital means the electric generation process cannot be accurately summarized by the traditional neoclassical production function. The fuel-output and labor-output relationships are tOO dependent on the characteristics Of the capital equipment to be ignored!“ Therefore, we developed a model that explicitly recognizes the heterogeneous nature Of capital in the electric generating industny. Our concern is with the investment decision Of the utility since the characteristics Of the capital equipment restrict the variable input-output relationships or, in other words, the associated short-run production possibility sets. The utility must decide what portion Of total demand the new unit will serve and the associated engineering attributes Of the unit. We assume that the utility wants to serve an exogenous baseload and will choose the engineering characteristics Of a coal-fired unit to minimize the expected total cost Of meeting the load. A key issue here is the intensity with which a unit is used. The capital intensive nature Of baseload coal-fired generation means that the average total generation costs Of a unit can be significantly reduced if the unit is 52 used intensively. Baseload units are meant tO be Operated at maximum capacity continuously so that the level Of utilization is dependent on the expected availability Of the unit. Thus, the expected output Of the unit is defined as: 0 - 8760*A(X)*K, Where, 0 - expected output, measured in kilowatt hours, A(X) - expected availability Of the unit, X - unit attributes that affect availability, K . size Of the unit measured in kilowatts. h c d P O un tiO As noted earlier, electric generating technology is putty-clay. The thermal efficiency Of a unit is variable at the design stage and dependent on the utility’s choice of steam pressure conditions. But once a unit has been built, the fuel-output relationship is fixed.“ Thus, the total cost Of generating electricity is a function Of the level Of output, the price Of fuel on a BTU basis, the thermal efficiency Of the unit, construction costs per KW of capacity, and the annual fixed charge rated” The fixed charge rate is the annual cost Of money capital including depreciation, property taxes, and other expenses proportional to capital costs. As a result, expected §X_DQ§L total generation costs are: SRTC(P,.,P,,,r,¢,K) - .8760 A(X,,)K0 'PF + rPK(Zo)KO’ 53 Where, a = the unit's heat rate (BTU's/KWH), PF = price per BTU Of fuel, m2) Z = unit attributes which affect construction costs, unit construction costs per KW Of capacity, r = the annual fixed charge rate. Ex Ante Costs and the Investment Decision Given that the technology is putty-clay, the utility is faced with the task Of choosing unit attributes that minimize the expected total costs Of serving a baseload demand for electricity at the blueprint stage. The primary unit attributes to be chosen are unit size, steam pressure conditions (an ex ante measure Of thermal efficiency), and the reliability Of the unit. The average construction cost of a coal-fired unit is also assumed to vary with the choice Of these engineering characteristics. Briefly, it is reasonable to expect a movement from subcritical to supercritical steam pressure conditions to increase average construction cost. Higher pressure conditions improve thermal efficiency,46 but necessitate the use Of costly materials capable of handling the extreme pressure. It is reasonable to expect that aPk/aK will take on positive, negative, or zero values depending on the size of the unit. We expect that aPk/aK will take on negative values at low unit sizes and possibly become positive at large unit sizes. We also expect that the average construction cost will increase with the reliability Of the unit, aPk/aA>O. Finally, we expect average construction cost tO increase at an increasing rate as availability approaches the limit of 100 percent, asz/3A2>O.47 54 As noted earlier, a unit's fuel costs per KWH are relatively insensitive to the rate of generation.48 But the capital intensive nature of baseload coal-fired generating units means that intensive utilization Of a unit spreads annual capital costs (which are fixed once a unit is built) over a greater level Of output than if a unit is used less intensively. Thus, the ex ante total costs per KWH generated by a coal-fired baseload unit are in large part determined by the availability, or reliability, of the unit: TC(Pf,r,o,K) + a876OKA(X)Pf+rPk(Z)K0. This implies that the total generating costs per KWH Of a subcritical or supercritical unit can be approximated by minimizing the unit's annual capital cost per KWH produced: Capital Cost = (Total Capital Cost x Annual Fixed Charge Rate) per KWH Q Since 0 = 8760 A(X)K, Capital Cost = Capital Cost per KW * AFCR per KWH 8760 * A(X) This indicates that the ratio Of average capital cost to unit availability determines capital cost per KWH generated. In general, both availability and capital cost decline with increased unit size for both subcritical and supercritical technologies. Thus, minimum total generation costs per KWH can be approximated for a given type Of unit (subcritical or supercritical) by selecting the level Of reliability and unit size such that the ratio Of average capital cost to availability is the least. 55 SPECIFICATION OF THE CONSTRUCTION COST AN RELIABILITY MODEL The Determinants Of Unit Construction Cost The construction cost Of a coal-fired generating unit depends on the cost Of inputs and a number Of unit-specific attributes. Attributes commonly thought tO influence the construction cost per KW of capacity include unit size, unit order, steam pressure conditions, reliability, and cooling method. Reliability, measured by equivalent availability, is not the result Of a single design or construction decision. Rather, reliability encompasses a large number of design and construction decisions ranging from the number and sizing Of various types Of equipment to the quality of the inputs used to manufacture or assemble the various components Of the unit. Above all, redundancy of critical components is necessary to maintain a high level of unit reliability. A unit can continue in operation when a critical component fails, or needs regular maintenance, only if the component has a backup.49 As a result, one would expect that increasing the level Of reliability, everything else constant, requires additional capital investment which means aPk/aA>0. We also expect that increasing reliability beyond some point will cause costs to increase at an increasing rate. Thus, we expect asz/aA2>0. According to engineering literature, construction costs increase less than proportionately with the size Of the unit. As unit size increases, the amount of material and labor per KW of capacity decreases. For example, a 600 MW unit uses only twice the piping and steel necessary to build a 200 MW unit.50 But it would also seem reasonable to expect average construction costs to increase as unit size increases beyond some point. Extremely large unit size might require 56 the use Of additional structural reinforcement, special materials or construction methods. Thus, we expect that aPk/ak will take on negative values at low unit sizes and possibly become positive at very large unit sizes. The primary technological frontier with respect to the thermal efficiency Of coal—fired units built since 1960 has been in steam pressure conditions.51 These units fall intO two major technological classes--subcritical units with steam pressures below 3206 PSI and supercritical units with pressures greater than 3206 PSI. Subcritical units fall into three pressure classes around 1800 PSI, 2000 PSI, and 2400 PSI. These units require nO technological changes as steam pressure in increased. But the higher pressures dO require thicker casings for components and materials that can handle the higher pressures. Supercritical units represent an entire different technology since there is nO real boiling process and steam is produced continuously as the temperature Of the water increases. The need for some equipment associated with a conventional boiling process is removed, but the large increase in pressure necessitates considerable expenditure on special materials capable of withstanding these pressures. Thus, we will use the design steam pressure condition as an ex ante measure of thermal efficiency, and we expect supercritical units to be more costly to build than subcritical units. The majority of individual generating units are part Of multiunit sites, and the order in which the units are built has considerable 57 impact on their individual construction costs. The first unit at a multiunit site is usually built with sufficient waste disposal facilities, transportation facilities, fuel-handling facilities, and other common facilities to support the Operation Of all other units scheduled to be built on the site at a later date. Thus, we expect the first unit at a site tO be more costly than follow-on units. A couple Of previous studies have examined the effects Of utility and architect-engineer (A-E) experience on the construction costs Of generating units. Joskow and Rose (1985) found that there are important learning or experience effects as the number Of units built by a given A-E increases. However, they also found that the experience effects were limited to the building Of supercritical units. In order to account for the presence Of any experience effects, we include a variable which measures each A-E’s cumulative experience since 1950 with a specific technology. We broadly define all subcritical units as falling into one technology group, and all supercritical units as following into another technology group. In addition to the variables mentioned above, we also include a number Of dummy variables. First, it is possible that there are regional cost differences which might arise for a number Of reasons. But the primary reason is that the market for construction labor is generally regional and wages can vary considerably across regions. These variations may be due to differences in the degree Of unionization and the tightness Of the regional labor market. 58 Second, we include a dummy variable to indicate whether the unit is Of full-indoor design. In colder climates, boilers and turbine-generators are usually fully enclosed in protective structures. But these facilities are Often only partially enclosed or fully outdoors in warmer parts Of the United States. Thus, one would expect units Of a full-indoor design tO be more costly to build. Third, we include a dummy variable for each A-E so as to reduce or eliminate any potential omitted variable bias. There are likely tO be unobserved A-E specific design characteristics common to units designed by a particular firm. These unmeasured attributes may be correlated with experience or unit reliability which means that failing the account for them could cause the parameter estimates tO be biased. Also, the inclusion Of A-E dummy variables allows us to assess any differences between specific A-E firms.” A translog specification of the construction cost function will be estimated. The primary reason for using this specification is that it is flexible enough to allow all size-reliability effects to occur. The basic construction cost relationship is: lnPK - 80 + B,ln(MW) + Bz(ln(MW))2 + B,(-ln(1-EA)) + B,(-ln(1-EA))2 + 85(-ln(1-EA))ln(MW) + B;*PRESSURE + B7(PRESSURE * ln(MW)) + B,(PRESSURE * (-ln(1-EA))) + B,ln(l + EXPERAE) + B,,,LN(YEAR) + 7.3.x, + e,. Where, PK - the real dollar cost per KW Of a generating unit net Of capitalized interest costs, MW - the capacity Of the unit in megawatts (MW), 59 EA = a three year average Of a unit's Observed equivalent availability (The Observations covered each unit's second through fourth year of commercial Operation.), PRESSURE = a dummy variable which indicates whether the unit is supercritical, YEAR = the year the unit entered commercial Operation minus 1900, EXPERAE = the cumulative experience since 1950 Of the A-E with the technology of the Observed unit (If a unit enters commercial Operation in the year t the total experience Of the A-E is measured as the total number of units Of the same technology designed by the A-E that entered commercial operation before year t.), x = dummy variable indicating regionality, the presence of cooling towers, the first unit at a multiunit site, and the other variables discussed above, et = the error term. The Determinants Of Unit Reliability The engineering and economic literatures indicate that a number Of design and operational characteristics have a systematic effect on unit availability. Among these are unit size, steam pressure conditions, unit age, vintage, mode of Operation, and the degree Of redundancy of key components. Some engineering and economic studies assume that availability is independent Of unit size,53 but several studies that examine the size- availability relationship conclude that size and reliability are inversely related.54 One explanation for the inverse relationship is that similar types of outages are generally longer for large units than for smaller units due to the larger area and parts that have to be repaired. Also, large unit size means more material and equipment which simply creates more opportunities for things to break down. Thus, we expect aRel/aK< .>L=am can" ooum oo—— coo" coo coo can com com cov con whh< .>.=ao ooo oos ooo ooo oov oon mhh<3< .>L:oo oon— oouu cog“ ooo— ooo ooo oos ooo ooo cot con mph<=< .>_cao coo“ coon ccao coco coo cco cog coo coo coo cco th<3< .>L=oo coo ccg coo coo coo ccm ohh<3< .>H=oo ccmH ocoH ocHH cocH com coo cog coo coo coo com ohh<3< .>H=ao ccmH cooH ccHH cccH ccm cco cog cco coo coo ccm ophoxoou: 6» auaamog gqu maHHHuHum._o «Goo pea—a t :5 6:28 a 6.. 3:223. .gHYm o—coh 91 Rom oomH 3% 6% Sn 3...: .. acmugwo oH an “coupopcmwm u RH“ Hoo anon... < .>F:oo oooH oooH ooHH oooH oom ooo ooo ooo ooo ooo ooo ohh<3< .>H=cm can can ooo ooo ooo oom mhh<3< .>H=oo oooH oooH ooHH oooH oom ooo ooo ooo ooo ooo ooo ohh<3< .>w=co ooo ooo ooo ooo ooo ooo ohh<3< .>H=oo oooH oooH ooHH oooH oOm ooo ooo ooo ooo ooo ooo ohh¢ .>.=cu 8o 9: so so So 8... as So So an 8... mhhosoauz .:§.8::83.o£=§.8u80::%u.Tozfip 104 .zx Loo mgmHHoo cw mom monsoom HH< ”maoz oYo mHoah .o gmaomco cH omucooms moHommg copmmmgowg co oommo « oo.ooom oo.oooo mm.oooo oo.omoH oo.oooH oH.oom oo.ooo oo.ooo oo.omo oo.ooo oo.HmH gom oo.ooo oo.ooo oo.oHo oo.ooo oo.oHo mo.ogo oo.ooo oo.ooo oH.ooH mo.ooH oo.moH gom oo.ooo om.ooo oo.ooo oo.ooo oo.omH om.moH oo.ooH oo.ooH oo.ooH oo.ooH oo.ooH goo oo.ooH oo.HoH oo.ooH Ho.HoH oo.ooH mm.ooH oo.HoH oo.moH Ho.moH om.HoH oo.ooH goo oo.ooH oo.ooH HH.ooH oo.ooH oo.ooH oo.ooH oo.HoH oH.ooH oo.ooH oo.ooH Hm.omH goo oo.moH Hm.HoH mm.omH oo.moH oo.ooH oo.HoH oo.ooH oo.ooH oo.moH oo.oHo oo.moo goo oo.ooH oo.ooH oo.ooH oo.moH Hm.ooH oo.moH mo.ooH oH.omH oo.mHo oo.ooo oo.oHo goo oo.mHH oo.ooH oo.omH mo.moH oH.ooH oo.HoH oo.omH oH.mHo om.ooo oH.oHo oH.omo goo .HHm>< .>H=ou ooo ooo ooo ooo ooo ooo ooo ooo ooo ooo ooo ohho .>_=oo ooo ooo ooo ooo ooo ooo ooo ooo ooo com com ohh<3< .ooomo o8 ooo ooo ooo ooo ooo ooo ooo ooo oom oom opposoooz . ooo: Hoo.ooooooo o ooo xx ooo omoo .oooooo .oYo ooooo .132 Loo magma co moo omoomoo HH< "maoz “Yo mHoap .o gmuoogo co oougooms ouHoomo cooommgmms co omomo « 107 ooo.oo ooo.oo omH.Hm omm.oo ooo.oH Hoo.o ooo.o oHo.o gmo.H ooo. moo. gom ooo.o ooo.o oHo.o ooo.o ooo.H ooo.H omm. ooo. “so. ooo. ooH. gom ooo.H Hoo.H ooo.H on. ooo. ooo. omo. ooo. mom. ooo. oHo. goo ooo. ooo. ooo. moo. omo. ooo. moo. mom. ooo. mmo. Hoo. goo ooo. moo. ooo. ooo. ooo. ooo. ooo. oom. ooo. Hoo. oom. goo ooo. moo. oom. mmo. ooo. mmo. ooo. oom. oom. ooo. ooo. goo omo. omo. Hoo. ooo. oHo. ooo. oom. ooo. ooo. mmo. oHo. goo ooo. ooo. ooo. omo. oHo. ooo. goo. omo. mHo. ooo. oom. goo ._.o>< .ooooo oooH oooH ooHH oooH oom ooo ooo ooo ooo ooo ooo ophtxtam: .. 2.5 33:89:... o .3.— =3. 3.. 38 .328 .oYo as: 108 .32 Lao moapHoo co woo omgommo HH< “moo: oYo «Hoop .o gwuomgo co oungoomg ouHoomg economommg cc omooo « oo.ooooo oH.oomoo oo.ooogH oo.oooHH oH.ogoo oo.oogo oo.oooo om.mooH oo.omo oH.oom oH.omH gom Hm.oooo oo.mmmH Ho.oooH oH.mooH oo.oom om.oHo oH.Hoo oo.ooo oo.ooo oo.HoH oo.om gom Ho.oHo oH.Hoo oo.ooo oo.ooo om.ooo oo.ooo mm.ooo om.oHo mo.ooH oo.ooH Ho.ooH goo oo.Hoo oo.HHo oo.ooo oo.ooo oo.Hoo oo.moo oo.ooH oo.moH oH.ooH oo.moH oH.HoH goo Ho.ooo oo.omH om.ooH mo.ooH mo.moH oo.ooH oo.ooH oo.ooH oo.ooH oo.ooH oo.ooH goo om.ooH oo.ooH Ho.ooH oo.omH oH.ooH oo.ooH oo.HoH oo.ooH mo.ooH om.ooH oo.oHo goo oo.HHH oo.oHH oH.oHH oo.oHH oo.ooH oo.ooH oo.omH Ho.ooH oH.ooH Ho.ooo oo.ooo goo oo.Hm oo.om om.om oo.ooH oo.moH oH.mHH oo.ooH mo.HoH mm.HoH oo.ooo oH.oom goo .HHo>< .>.:om oooH oooH ooHH oooH oom ooo ooo ooo ooo ooo ooo ohh< .>.=um can com com ooo ooo com com ooo ooo ooo ooo mhh<3< .ooooo ooo ooo ooo ooo ooo ooo ooo ooo ooo ooo ooo otozooox . ooo: .ouoooooooo o ooo 3g ooo omoo .oooooo .oYo o_ooo .::x goo oucmu co moo omgomoo HH< "woo: oYo mHooh .o gmuoogo co omugoomo ouHoomg coooomgmmg co ooooo « lll oom.oo moo.oo ooo.nH ooo.oH ooo.o omo.o ooo.o ooH.o moo.H ooo. omo. gom oom.o ooo.o mom.H omo.H ooo.H omm. goo. mmo. ooo. ooo. oHo. gom ooo.H ooo. ooo. moo. omo. oHo. mmo. oom. moo. mmo. ooo. goo ooo. oHo. Hoo. ooo. ooo. ooo. ooo. ooo. HHo. ooo. ooo. goo ooo. ooo. ooo. mom. moo. ooo. oHo. Hoo. ooo. oom. omo. goo moo. mmo. omo. omo. mmo. oom. oHo. ooo. ooo. goo. omo. goo ooo. ooo. Hoo. moo. Hmo. ooo. omo. ooo. ooo. ooo. oHo. goo ooo. ooo. Hoo. ooo. omo. ooo. ooo. ooo. moo. oHo. ooH.H goo .H_o>< .>H:uu oooH oooH ooHH oooH oom ooo ooh ooo ooo ooo oom mhh.ooo ooo ooo ooo ooo ooo ooo ooo ooo 8o ooo ooo oooozoooz . ooo: ooo.o.ooooo o ooo =32 ooo oooo .oooooo .oHYo ooooo 114 .zx ooo oooHHoo co moo oooomoo HH< "muoz mYo oHooo .o cmuoooo co omoooomo ouHoomo oo.oomommo co omooo « om.oooo oo.oomH Ho.mooH oo.HooH oo.oooH mo.ooo oo.Hmo oo.ooo oo.ooo oo.omo oo.ooo gom mo.oHo oo.moo oo.ooo oo.oHo oo.ooo oo.ooo oo.ooo oo.omH oH.ooH Ho.moH Ho.ooH gom om.HHo oo.ooo oo.omH oo.ooH om.ooH mo.moH oo.HoH oo.ooH oH.ooH oo.ooH oo.HoH goo oo.ooH oo.HoH oo.moH om.ooH oo.ooH oo.ooH om.ooH Ho.ooH oo.moH oo.ooH oo.ooH goo oH.ooH Ho.ooH om.ooH oo.ooH Ho.moH oo.ooH oo.ooH oo.ooH oo.ooH om.ooH oo.omH goo oo.oHH om.HoH oo.ooH oo.ooH oo.ooH oo.moH oH.ooH mo.ooH oo.omH oo.oHo oo.ooo goo oo.oHH oo.mHH oo.ooH oo.ooH oo.ooH oo.moH oo.ooH oo.omH oo.ooo oo.ooo oo.moo goo oo.oHH oH.HoH om.ooH oo.ooH oo.ooH HH.ooH om.omH oo.ooo oo.Hoo oo.oHo oo.moo goo .H_o>< .>o:uo ooo ooo ooo ooo ooo ooo ooo ooo ooo ooo ooo oph< .>_=oo ooo" ooo" cog" oooH oom ooo ooo ooo ooo ooo ooo oph<3< .>o:uo oooH oooH ooHH oooH oom ooo ooo ooo ooo ooo ooo ohh<3