.. “-3,.1 3-. _ i l “i “j "'5' . “EEK-.51“; If M? . a... - ‘ w . ~ ‘3 ;.- J. ‘. ”1.553.“ W1.“ « k H ‘ ' U v +‘ ‘2‘" . ‘ 9 ' - ‘ ".31'. "t, w t l ' '1'. n. - n'ugfl‘wl,‘ K.“ ‘I I 1 ll‘ > 233‘» ‘.“\\t“‘ | l ‘ fix -: ; ', l 1‘81"“ 1 _ .‘YM’UI . 4, ,. .vxfi .m M1, ..%L . _ , , 35‘. .-.:!3; ”#117554; A v- ”‘S‘Wb" L'.'.':‘.€rj9 1' ‘ ,..A . my (,LL 4 . ‘u 'e. Q .7 - ' . ‘va‘,1“5_5's‘,‘,: "Wan“ “,1 ‘ W ‘ I. ‘3‘ "'84.‘ . It... 'H- ‘ ,_, , This is to certify that the thesis entitled APPLICATION OF LEAN PRINCIPLES TO THE STRUCTURAL STEEL DELIVERY AND ERECTION PROCESS presented by VICTOR JALIL DACCARETT GARCIA has been accepted towards fulfillment of the requirements for the Master of! degree In Building Construction Science Marfiqement film? Major Professor’ 3 Signature 2/23Iéa Date MSU is an Affirmative Action/Equal Opportunity Institution - --»— -V-.-.-.-.-.-.-.-.-.-.-.-.-.-.-.-.-.—.-.- b ‘. MWA-. v .— LIBRARY Michigan State University PLACE IN RETURN BOX to remove this checkout from your record. TO AVOID FINES return on or before date due. MAY BE RECALLED with earlier due date if requested. DATE DUE DATE DUE DATE DUE MAY; 2 8 2005 NR 1 c 2207 Ital/«iii 290i 2/05 c:ICI_RC/DatoDue.lndd-p.15 _—_————— _ 7 —-. l APPLICATION OF LEAN PRINCIPLES TO THE STRUCTURAL STEEL DELIVERY AND ERECTION PROCESS By Victor Jalil Daccarett Garcia A THESIS Submitted to Michigan State University in partial fulfillment of the requirements for the degree of MASTER OF SCIENCE Construction Management Program 2004 ABSTRACT APPLICATION OF LEAN PRINCIPLES TO THE STRUCTURAL STEEL DELIVERY AND ERECTION PROCESS By Victor Jalil Daccarett Garcia The structural steel erection process is considered to be a relatively efficient and fast part of a construction project. Opportunities for improvement are sometimes overlooked and obscured by apparent success. Inefficiencies observed in the structural steel erection process include: unnecessary movement of personnel, unnecessary handling of steel pieces, and inefficient crew use. This investigation explores how to reduce or eliminate these inefficiencies by applying principles part of the lean production theory. One of the main principles of lean production is the reduction or elimination of non-value adding activities (waste) from the production process (Koskela 1993). The structural steel erection process of a building normally contains six distinctive activities: unloading, shakeout, erection, plumbing up, permanent connection and decking. According to lean production theory, unloading and shakeout activities are non-value adding. In this sense, the main goal of this research was to study the viability of eliminating non-value adding activities of unloading and shakeout from the structural steel erection process by creating an alternative erection process. It was found that it is possible to remove unloading and shakeout from the erection process of structural steel frames with characteristics similar to the case studied. Moreover, it was estimated that removing unloading and shakeout could result in a 26% reduction in duration and almost a 20% reduction in cost for the case study. TO GOD AND MY FAMILY iii ACKNOWLEDGEMENTS Above all I want to thank God for his presence and assistance in this master thesis and especially in my life. Thanks to my family (Issa Victor, Edda, Tatiana Yadira y Jorge Yamil) for their unconditional love, support, and encouragement. I also want to express my gratitude to Dr. Saturnino Rodriguez for his support and advice while at Michigan State University. Special thanks to Professor Tim Mrozowski; my guiding light in producing this master thesis. I extend my appreciation to Lou Gurthet and Fromy Rosenberg in the American Institute of Steel Construction for helping fund this research. I want to convey my gratitude to Mr. James D. Buzzie, Mr. Lawrence F. Kruth, and their team for sharing their knowledge. Thanks to my committee members, Dr. Robert von Bemuth and Dr. Amit Vanna for their comments and advice. Finally, thanks to all my friends that in one way or another played an important role in this chapter of my life. iv TABLE OF CONTENTS LIST OF TABLES- - - - _ - - ....... -- IX LIST OF FIGURES ..... - - _ - - - - - - - XI CHAPTER 1: INTRODUCTION..-..-.._--- - _- _ -- ..... - - - l 1.1 BACKGROUND ............................................................................................................ 1 1.2 PROBLEM STATEMENT ............................................................................................... 4 1.2.1 Work Flow .......................................................................................................... 7 1.2.2 Material Handling ............................................................................................. 9 1.2.3 Resource Management ....................................................................................... 9 1.2.4 Site Planning .................................................................................................... 10 1.3 GOALS AND OBJECTIVES .......................................................................................... 1 1 1.4 RESEARCH SCOPE ..................................................................................................... 12 1.5 METHODOLOGY ....................................................................................................... 17 CHAPTER 2: LITERATURE REVIEW.-- - ........... -- - 21 2.1 LITERATURE REVIEW OVERVIEW ............................................................................. 21 2.2 LEAN PRODUCTION .................................................................................................. 21 2.2.1 Origin of Lean Production ............................................................................... 22 2.2.2 Defining Lean Production ................................................................................ 25 2.2.3 Lean Production Principles and Methodologies ............................................. 29 2.2.4 Lean Construction ............................................................................................ 30 2.2.5 Problems in Construction ................................................................................ 30 2.3 RESEARCH ON STRUCTURAL STEEL ERECTION .................................................. 33 2. 3.] Applying Lean Principles to the Structural Steel Erection Process ................ 33 2.3.2 Just In Time in the Structural Steel Supply Chain ........................................... 36 2.3.3 Delivery Approaches and Labor Productivity ................................................. 40 CHAPTER 3: METHODOLOGY- -- - - - - - _ _ 43 3.1 METHODOLOGY INTRODUCTION .............................................................................. 43 3.2 PHASE 1: LITERATURE REVIEW ................................................................................ 44 3.3 PHASE II: TRADITIONAL PROCESS MODEL DEVELOPMENT ...................................... 44 3.4 PHASE III: ALTERNATIVE PROCESS MODEL DEVELOPMENT .................................... 46 3.4.1 Industry Survey ................................................................................................ 48 3.4.2 Alternative Model Creation ............................................................................. 48 3.4.3 Case Study ........................................................................................................ 49 3.4.4 Feedback Interviews ........................................................................................ 50 3.4.5 Proof of Concept Interviews ............................................................................ 51 3.5 PHASE IV: ECONOMIC FEASIBILITY ......................................................................... 52 CHAPTER 4: THE TRADITIONAL PROCESS - ..... - -55 4.1 INTRODUCTION To THE TRADITIONAL PROCESS ...................................................... 55 4.2 ON SITE OBSERVATIONS .......................................................................................... 55 4.3 INVESTIGATION INTERVIEWS .................................................................................... 56 4.4 THE TRADITIONAL PROCESS MODEL ........................................................................ 59 CHAPTER 5: THE ALTERNATIVE PROCESS - 64 5.1 INTRODUCTION TO THE ALTERNATIVE PROCESS ..................................................... 64 vi 5.2 INVESTIGATION INTERVIEWS AND THE ALTERNATIVE PROCESS ............................. 64 5.3 INDUSTRY SURVEY ................................................................................................... 66 5.4 THE ALTERNATIVE PROCESS MODEL ....................................................................... 69 5.5 FEEDBACK INTERVIEWS ........................................................................................... 74 5.6 PROOF OF CONCEPT INTERVIEWS ............................................................................ 76 5.7 BUFFERS .................................................................................................................. 78 CHAPTER 6: ECONOMIC FEASIBILITY- - .......... - -- - 80 6.1 INTRODUCTION ......................................................................................................... 80 6.2 CASE STUDY ............................................................................................................ 80 6.3 TIME AND COST ANALYSIS ...................................................................................... 81 CHAPTER 7: CONCLUSIONS - - - -- - - - 92 7.1 RESEARCH SUMMARY .............................................................................................. 92 7.2 RESEARCH CONCLUSION .......................................................................................... 94 7.3 RECOMMENDATIONS ................................................................................................ 96 7.4 RESEARCH LIMITATIONS .......................................................................................... 97 7.5 AREAS OF FUTURE RESEARCH ................................................................................. 98 REFERENCES. -------- -- -- - 101 APPENDICES - - ------ - -- 107 APPENDIX A: INVESTIGATION INTERVIEWS .................................................................. 108 APPENDIX B: FEEDBACK AND PROOF OF CONCEPT INTERVIEWS ................................ 123 APPENDIX C: INDUSTRY SURVEY ................................................................................. 128 APPENDIX D: ORGANIZED TRUCKLOADS ..................................................................... 153 vii APPENDIX E: ADDITIONAL INFORMATION ON LEAN .................................................... 182 viii LIST OF TABLES Table 1: Waste in construction: compilation of existing data ............................................. 6 Table 2: Mass vs. Lean Production characteristics ........................................................... 25 Table 3: Principles and changes to the model in Al-Sudairi’s study ................................ 35 Table 4: Comparison of material delivery methods .......................................................... 41 Table 5: Duration formulas ............................................................................................... 82 Table 6: Traditional erection process duration calculations ............................................. 82 Table 7:Alternative erection process duration calculations .............................................. 83 Table 8: Cost analysis formulas ........................................................................................ 84 Table 9: Crew cost calculations ........................................................................................ 87 Table 10 Traditional Process Cost Analysis .................................................................... 89 Table 11: Alternative Process Cost Analysis .................................................................... 90 Table 12: Investigation interviews responses A ............................................................. 112 Table 13: Investigation interviews responses B .............................................................. 116 Table 14: Investigation interviews responses C .............................................................. 121 Table 15: Feedback interviews results ............................................................................ 126 Table 16: Proof of concept interviews results ................................................................. 127 Table 17: Fabrication and erection companies responses ............................................... 136 Table 18: Organized steel with 12 inches as nominal height (Truck A) ........................ 154 Table 19: Organized steel with 12 inches as nominal height (Truck B) ......................... 154 Table 20: Organized steel with 12 inches as nominal height (Truck C) ......................... 155 Table 21: Organized steel with 21 inches as nominal height (Truck D) ........................ 157 ix Table 22: Table 23: Table 24: Table 25: Table 26: Table 27: Table 28: Table 29: Table 30: Table 31: Table 32: Table 33: Table 34: Table 35: Table 36: Table 37: Table 38: Table 39: Organized steel with 21 inches as nominal height (Truck E) ......................... 158 Organized steel with 21 inches as nominal height (Truck F) ......................... 159 Organized steel with 21 inches as nominal height (Truck G) ........................ 160 Organized steel with 21 inches as nominal height (Truck H) ........................ 161 Organized steel with 16 inches as nominal height (Truck 1) .......................... 163 Organized steel with 16 inches as nominal height (Truck J) .......................... 164 Organized steel with 16 inches as nominal height (Truck K) ........................ 165 Organized steel with 16 inches as nominal height (Truck L) ......................... 166 Organized steel with 16 inches as nominal height (Truck M) ........................ 167 Organized steel with 16 inches as nominal height (Truck N) ........................ 168 Organized steel with 18 inches as nominal height (Truck 0) ........................ 170 Organized steel with 19 inches as nominal height (Truck P) ......................... 172 Organized steel with 14 inches as nominal height (Truck Q) ........................ 173 Organized steel with 10 inches as nominal height (Truck R) ......................... 175 Organized steel with 24 inches as nominal height (Truck S) ......................... 179 Organized steel with 24 inches as nominal height (Truck T) ......................... 180 Mass vs. Lean Assembly Plant characteristics ............................................... 185 Mass vs. Lean Supply Chain characteristics ................................................... 188 LIST OF FIGURES Figure 1: Logical network of erection activities ................................................................. 2 Figure 2: Scope of the research project ............................................................................. 14 Figure 3: Responsibilities when the erector is different from the fabricator .................... 15 Figure 4: Responsibilities when the fabricator is also the erector .................................... 16 Figure 5: Phases of the research project ........................................................................... 17 Figure 6: Types of activities encountered in any product development ......... 27 Figure 7: Interdependence of activities in the structural steel erection process ............... 31 Figure 8: Traditional structural steel erection process including fabricator activities ...... 61 . Figure 9: Traditional structural steel erection process including fabricator activities ...... 72 Figure 10: Drawing of truckloads for steel with 12 inches as nominal height ............... 156 Figure 11: Drawing of truckloads for steel with 21 inches as nominal height ............... 162 Figure 12: Drawing of truckloads for steel with 16 inches as nominal height ............... 169 Figure 13: Drawing of truckload for steel with 18 inches as nominal height ................. 171 Figure 14: Drawing of truckload for steel with 14 inches as nominal height ................. 174 Figure 15: Drawing of truckload for steel with 10 inches as nominal height ................. 178 Figure 16: Drawing of truckload for steel with 24 inches as nominal height ................. 181 Figure 17: Lean Project Delivery System ....................................................................... 190 Figure 18: The Last Planner System ............................................................................... 195 xi CHAPTER 1: INTRODUCTION 1.1 BACKGROUND Construction of the structural steel frame of a building consists of four phases: design, detailing, fabrication and erection. In the first phase, the structural engineer designs the foundation and structural steel frame of the building and generates drawing details based on this design. The detailer then designs connections between structural steel members and develops shop drawings of each steel piece that is part of the structural frame. This process is called detailing. Shop drawings are submitted to the contractor and structural engineer to ensure that they comply with the engineer’s design. Upon approval of Shop drawings, the fabricator precisely fabricates the steel pieces that will be part of the structure. Once structural steel members are fabricated they are taken to the yard, loaded on trucks and transported to the job site for erection. During the erection phase, steel members are hoisted and fastened in their appropriate positions in the structure. The structural steel erection process of a building normally contains six distinctive activities: unloading, shakeout, erection, plumbing up, permanent connection and decking. Figure 1 on the following page is a model that shows how these activities are linked together. Shakeout is an industry term used to describe the activity of sorting out steel members on site. It occurs after steel is unloaded from the truck. Plumbing up is the vertical and horizontal alignment of the structural steel fiame. Permanent connection refers to the final bolt up of the structure after plumbing up. Labor productivity in the structural steel erection process can be impaired by several factors such as material management practices, disruptions to the work, changes and unfavorable weather conditions. A study by Thomas et al. (1999) investigated the impact of material delivery practices on labor productivity. The research consisted on studying three structural steel erection projects that used different methods of delivering structural steel members. In the first project only three deliveries of structural steel were Unloading Shakeout Erection I I l . Permanent Plumbing up Connection l l i Decking Figure 1: Logical network of erection activities (Eraso 1995) made. For the second project steel was delivered during the course of the work, interrupting erection operations. In the third project, steel was delivered and erected daily from the truck. The study found that in the first project almost 16% of the total work hours were lost due to poor material management practices and in the second project 14% of the total work hours were lost as a result of double handling structural steel. The investigation concluded that erecting structural Steel directly from the truck was the most efficient erection method. Thomas’ study suggests that considerable improvements could be made to the structural steel erection process by eliminating double handling of steel pieces as a result of unloading and Shakeout activities. Similar approaches to achieving efficiency are being suggested by construction researchers through application of lean principles first introduced in the automobile industry. This thesis explores the application of these lean principles to structural steel erection. Lean Production was first initiated in the Japanese automobile industry after World War II. It is called “lean” because it uses less of everything compared with mass production; half the human effort in the factory, half the manufacturing space, half the investment in tools, half the engineering hours to develop a new product in half the time and requires less than half the on site inventory (Womack, Jones and R005 1990). The lean production philosophy is based on several principles. One of the main principles of lean production is the reduction or elimination of non-value adding activities (waste) while maximizing value adding activities of a production process. A value adding activity is an activity that converts material and/or information into that which is required by the customer and a non-value adding activity (also called waste) is an activity that takes time, resources or space but does not add value (Koskela 1992). At this time there is an ongoing effort by researchers and practitioners to adapt the lean production philosophy to the construction industry. The goal of this research was to determine the viability of implementing this lean production principle to the structural steel erection process and estimate possible improvements that may result from its implementation. 1.2 PROBLEM STATEMENT Steel is an important structural frame material. It is safe for the environment because it is 100% recyclable and it can be used year round. In addition, steel is a material that can be produced and erected rapidly compared to other building materials such as concrete. Specifically, the erection of the structural steel frame of a building is considered to be a relatively efficient and fast part of a construction project. Opportunities for improvement may be overlooked and obscured by apparent success. While there has been extensive research on design and material aspects of structural steel, there is scarce research on production management of the steel erection process. As a result of advancements in the area of materials and design methods, today structures can be built using a smaller amount of structural steel. For example if the Sears Tower was built today it would require about 35% less steel than what was used in 1974 when it was constructed (AISC 2000) Although steel has several advantages over other materials used for a building’s structural frame, its production process on Site can still be improved. According to the lean production philosophy unloading and Shakeout activities are considered to be non- value adding activities because they are not transforming material or information into what is required by the customer. There are two types of customers for each activity: internal and final customers. In this case, the internal customers are the following activities that require the structural steel frame to perform their job. The final customers are the final users of the facility. What do customers require? They require a structural steel frame with characteristics described in plans and specifications. The plans and specifications of the building should be based on customer requirements. According to the lean production philosophy if unloading and shakeout are non-value adding activities they should be reduced or eliminated. On the other hand, erection, plumbing up, permanently connecting and decking are value adding activities because they are transforming material and information into a structural steel frame that complies with plans and specifications. Erection transforms pieces of steel by joining them together and forming the frame of the building. Plumbing up changes characteristics of the frame so that it is aligned vertically and horizontally. Permanent connection adds value to the structure by giving it the specified strength. Decking transforms the structure by adding a surface that will support other components of the structure. Table 1, developed by Koskela (1993), is a compilation of several studies performed by different authors in the United States and Sweden that indicate the presence of waste in construction. Waste is considered as anything that does not add value such as: defects in products, facilities difficult to build, poor materials management, and lack of safety. Specific studies (Oglesby 1989 and Levy 1990) of work flow processes estimated that the average share of working time used in value adding activities was 36% and 31.9% respectively. Specifically in the steel erection process, Al-Sudairi (2000) found that depending on project complexity, crew time spent on non-value adding activities varies from 35 to 45%. In other words, the structural steel erection process is far from being a “lean” process. This means that steel erection offers considerable potential for improvements by removing existing non-value adding activities. What would happen if the crew Spent most of its time on value adding activities? Table 1: Waste in construction: compilation of existing data (Koskela 1993) WASTE COST SOURCE COUNTRY Quality costs 12% of total project (Non-conformance) costs BuratI et a1. 1992 USA External quality costs 4% of total project Hammarlund & (During facility use) costs Josephson 1991 Sweden Lack of 6-10% of total Constructability USA constructability project costs 1986 Poor materials 10-12% of labor Bell & Stukhart USA management costs 1986 Working time used . Oglesby et al. for non-value adding oAfI’tzfifige‘e'y 2’3 1989 USA activities on site Levy 1990 o . . Lack 0 f safety 6 A) of total project Lev1tt & USA costs Samelson 1988 Ideally, according to lean theory, steel members should be erected directly from the truck without having to unload and shakeout steel. The sources of waste associated with unloading and shakeout activities in the structural steel erection process are classified as follows: 1. Unnecessary movement of personnel 2. Unnecessary handling of steel pieces 3. Inefficient crew use 4. Inefficient crane usage Even though the lean production system used in the manufacturing industry has proven to be valuable, its applicability in other industries such as construction is still being tested. Some inefficiency in the structural steel erection process can be eliminated or reduced by removing non-value adding activities such as unloading and shakeout. This study explores the possibility of removing non-value adding activities from the steel erection process and what process changes are necessary to do so. 1.2.1 WORK FLow According to Koskela ( 1993), problems in construction are caused by the neglect of flows (information, material and work flows). The construction process iS sometimes viewed as activities to be managed and improved individually disregarding that construction is a complete system in which activities are tightly linked together (Koskela 1993). In construction it is common that the work produced by one trade is necessary for the succeeding trade to perform its work, as a result the performance of one trade is directly influenced by the previous one (Tommelein et al. 1998). Particularly in the steel erection process, the internal customer of the fabricator is the steel erector. After producing the finished steel members, the fabricator delivers them to the site. The structural steel members produced and delivered by the fabricator are necessary for the erector to perform his job. As a result, fabricator performance will directly affect the erector. In some cases there is lack of coordination and communication between fabricator and erector. Some fabricators deliver steel members without great consideration of erection sequence (Al-Sudairi 2000). To increase the efficiency of the structural steel erection process both parties should work together. Ideally, the steel erection process should be a continuous flow process. “A continuous flow process (CFP) is a type of production line through which work is advanced from station to station on a first-in-first-out basis. The idea is to balance processing rates of different stations so that all crews and equipment can perform productive work nearly uninterruptedly while only a modest amount of work-in-process builds up in between stations” (Ballard et al. 1999). If the steel erection process was part of a CFP the erection crew would be performing “productive” work almost uninterruptedly and structural steel members would be delivered according to the exact sequence so that they are erected on a first-in-first-out basis while a small amount of steel members waits to be erected. One of the main objectives of a continuous flow process is to maximize the production of all the crews in the system (including equipment) without unnecessary stocking of materials between them. The flow in the erection process is commonly disrupted because the crew has to stop or delay the erection process in order to unload the trucks and shakeout steel members. Sometimes the time of the deliveries iS not planned in order to improve project performance. This lack of flow has a hindering effect on the crew’s productivity. In a Specific project it was found that the workdays in which material deliveries were made showed a reduction of almost 40% efficiency of the erection crew (Thomas 1999). One reason is that the erection crew spends time moving from where they are hooking up and connecting steel members to where the unloading and Shakeout will occur. Shifting from one activity to another requires additional planning and set up times. When the crew working needs to stop their present assignment having to plan and reorganize for new work it is estimated that their efficiency can drop up to 29% (Thomas et al. 1995). By removing non-value adding activities of unloading and Shakeout the work flow of the process improves having a direct impact in the crew’s productivity. 1.2.2 MATERIAL HANDLING Efficient material handling is necessary for the successful completion of a project. Research done in this topic presents evidence that it is being poorly practiced in the construction industry (Muehlhausen 1991). Construction managers should carefully plan and control the flow of materials because it represents a high percentage of project total costs. If not enough attention is given to material handling, the costs may increase dramatically. Conversely, good material handling practices could produce great savings for the project. The structural steel erection process involves a considerable amount of material handling. Triple handling of steel pieces occurs during unloading, shakeout and erection activities, which results in loss of productivity for the erection crew (Thomas et a1. 1999). This practice is considered to be waste according to the lean production philosophy that strives for one touch material handling. This is another reason why removing these two activities from the process is beneficial. 1.2.3 RESOURCE MANAGEMENT For shakeout activities to be excluded from the steel erection process, the crew in charge of loading steel on trailers would have to shakeout steel in the shop. Based on observations made of a local fabricator and erector, the typical erection crew used on site to unload and shakeout structural steel consists of: o 1 erection foreman o 4 structural steel workers II o l crane operator 0 1 oiler 0 l crane. A similar crew is used in the Shop to load pieces of steel onto trailers. The observed differences between the two crews were: 1. The wages paid to erection crewmembers is much more than the ones paid to loading crewmembers. 2. The crane capacity on Site is approximately double the crane in the Shop. 3. The crane on site generally needs an oiler while the crane in the shop does not. Due to these differences between crews, shakeout at the shop could have a lower cost than shakeout on site. 1.2.4 SITE PLANNING When erecting structural steel directly from the delivery truck, the truck could be located on site so that movement of the crane While hoisting steel members can be minimized, maximizing the crane’s productivity. In some projects little planning is done (before starting the erection process) of the location where unloading and shakeout will occur. Two important factors affecting where unloading and shakeout will take place are space availability and easier maneuverability of the crane. Sometimes the space next to where the structure will be erected is scarce and unloading and shakeout of structural steel there is impossible. If steel was erected directly from the truck, it could be located closer to where the steel members are going to be erected because the Space used by the truck is small compared to unloading and Shakeout space required. As a result, cycle times for hoisting steel members can be reduced improving the productivity of the erection crew. 10 Ii 1.3 GOALS AND OBJECTIVES The main goal of this research was to study the viability of eliminating the non-value adding activities of unloading and shakeout from the structural steel erection process and estimate possible improvements that result from their removal. Unloading and shakeout activities have been part of a common practice in the steel construction industry for years and some professionals consider that it may be counterproductive to exclude them. On the contrary, one of the main principles of the lean production theory is the concept of value, that is, focusing on removing non-value adding activities or waste. In order to resolve this conflict the objectives of this research were: 1. Investigate and analyze how the structural steel erection process is performed, from fabrication to erection on site. Create a process model of the structural steel erection process from storage of structural steel on the fabricator’s yard to their erection on Site. (Traditional Model) Create an alternative process model without unloading and shakeout activities. (Alternative Model) Determine the viability of implementing the alternative model. Estimate the improvements in time and cost of the structural steel erection process that result from removing unloading and shakeout activities. Provide recommendations to the steel construction industry based on the findings of this investigation. 11 Along with these goals and objectives, this study was based on three hypotheses: 1. Unloading and Shakeout have a hindering effect in the overall efficiency of the structural steel erection process. 2. It is possible to remove unloading and shakeout from the structural steel erection process. 3. By removing the non-value adding activities of unloading and Shakeout the duration and cost of the complete process will be reduced. These are evaluated based on the results of this investigation. 1.4 RESEARCH SCOPE This research focused on studying the structural steel erection process including storage of structural steel pieces on the fabricator's yard and transportation of steel pieces to the site. The way steel members are stored on the fabricator's yard is particularly important because it directly influences the productivity of the crew loading them on trucks. Plumbing up, permanently connecting and decking activities were not considered because they are value adding activities not critically affected by removal of unloading and Shakeout. Activities studied in depth in this research are illustrated in figure 2. While several principles, methodologies and tools are part of the lean production philosophy, this research was primarily based on the principle of minimizing or removing non-value adding activities from the steel erection process with the purpose of improving its efficiency. The objective was to determine to what extent these non-value adding activities can be removed from the production process by creating an alternate process and quantify its possible benefits. 12 It is common for the fabricator to subcontract a separate erector to erect the structural steel frame of a building. The activities performed by each party in this type of organization can be observed in figure 3. In other cases the fabricator also erects the structural steel members, this type of organization can be seen in figure 4. This investigation focused on the later because it covers activities that are done by both the fabricator and erector making it easier to communicate and coordinate when both parties are under the same organizational structure. Moreover, this type of organization removes legal barriers existing in the construction industry. The benefits of removing unloading and shakeout activities were estimated by means of a case study. The characteristics of the case study project are: 0 Office building use. 0 Moderate complexity of the structural steel frame. The structural steel pieces do not have complicated curvilinear shapes but it is not so Simple that most steel pieces are repetitive. o 4 stories high. 0 Available space on site for unloading and Shakeout activities. An office building 4 stories high was chosen because it is one of the most common types of buildings erected. The case study project was representative of a common structural steel frame. It has an approximate fabrication and erection cost of 9.5 dollars per square feet and weighs approximately 10 pounds per square feet. 13 FABRICATION fl U RTOR A GP. fl U U I .nAnING fl U TRANSPORTATION I INI DA DING m U HAKEOUT Research Project fl m U RECTION m U PLUMBING UP m U PERMANENT CONNECTION V Figure 2: Scope of the research project 14 FABRICATION m U STORAGE ricator m U LOADING Fab m U TRANSPORTATION U UNLOADING flfl U U HAKEOUT m RECT ION U PLUMBING UP Erector m m U PERMANENT (‘ NNFPTION m U Figure 3: Responsibilities when the erector is different from the fabricator 15 FABRICATION m U U STORAGE mm LOADING U TRANSPORTATION U UNLOADING 5mm E’j U S ERECTION U Same Fabricator and Erector fl PLUMBING UP m U PERMANENT C NNFCTION m U Figure 4: Responsibilities when the fabricator is also the erector 1.5 METHODOLOGY This research was developed in five phases (see figure 5): literature review, traditional process model development, alternative process model development, economic feasibility and conclusions. PHASE I: Literature Review Lean Production Research on Structural Steel Erection O FPHASE 11: Traditional Process Model Development U Company Selection On Site Observations Investigation Interviews ¥ Traditional Model Creation 1 O fiPHASE III: Alternative Process Model Development Industry Survey Alternative Model Creation Feedback Interviews Proof of Concept Interviews \ Buffers J 9 PHASE IV: Economic Feasibility Case Study Time and Cost Analysis 0 PHASE V: Conclusions Summary Findings and Recommendations Area of Future Research \ Figure 5: Phases of the research project 17 The approach taken in this investigation follows the guidelines suggested by different authors (see section 3.1). In brief, these phases are: Phase I: Literature Review Relevant literature in the areas of lean production and structural steel erection was compiled and analyzed. The literature review was important because it establishes the foundation of this investigation. In this phase research related to lean production and structural steel erection was explored and inefficiencies in the structural steel erection process uncovered. Phase II: Traditional Process Model Development The objective of this phase was to create a company specific process model of the structural steel erection process. To create this model a fabrication and erection company was selected, on site observation of fabrication and erection processes performed, key personnel within the company interviewed (investigation interviews) and finally the traditional process model created. This process model helped map the process so that it can be improved. The main activities included in the process model are: storage, transportation, unloading, shakeout and erection of structural steel. Phase 111: Alternative Process Model Development A new alternative process model was created to remove the non-value adding activities of unloading and Shakeout from the structural steel erection process. In the alternative process steel is erected directly from the delivery truck. The steps taken in this phase were: 18 Step 1: Development and administration of a survey sent to fabricators and erectors of the Great Lakes Area including Michigan, Illinois and Indiana to obtain information relevant to the development of the alternative process model. Step 2: Development of an alternative process model based on information from the literature review, investigation interviews and the survey. Step 3: Selection of a case study to explore the application of the alternative process. Step 4: Determination of whether the alternative process could be used in the case study by interviewing key personnel within the participating company. Step 5: Incorporation of appropriate changes to the alternative model. Step 6: Presentation of the model and interviews of project managers of two fabrication and erection companies in order to receive feedback on the proposed alternative process. Phase IV: Economic Feasibility The estimated duration and cost of the traditional erection process was compared to the estimated duration and cost of the developed alternative erection process by means of a case study. This analysis provided valuable information about the possible benefits that can be accomplished with the alternative process. Phase V: Conclusions The last phase summarizes the investigation, presents findings and provides recommendations. Several conclusions were formulated about: how lean l9 principles could be successfully applied to the structural steel erection process, the existence of non-value adding activities in the erection process, the advantages and disadvantages of using the alternative process, and the efficiency of erecting steel directly from the delivery truck including upstream fabricator activities. In addition, areas of fiIture research are discussed. 20 CHAPTER 2: LITERATURE REVIEW 2.1 LITERATURE REVIEW OVERVIEW This chapter presents relevant literature that is the basis of this research. This literature was classified in three subjects: lean production, lean construction and structural steel erection. The first part of the literature review is divided into five sections. The first section presents the origin of lean production and is based on the book The Machine That Changed The World by Womack et al. (1990). This book is one of the largest research investigations made in the automobile industry. It reveals a production philosophy with great impact in the manufacturing industry. The second section defines lean production. In the third section lean production principles and methodologies are presented. A brief introduction to lean construction is given in the fourth section. The last section talks about current problems in construction. There is a scarce amount of research related to production management of the structural steel erection process. Relevant research in this area is summarized in the last part of the literature review. Areas discussed include: applying lean principles to the structural steel erection process, just in time in the structural steel supply chain, and structural steel delivery methods and labor productivity. 2.2 LEAN PRODUCTION “Lean” is a term used by International Motor Vehicle Program researcher John Krafcik to describe the new production philosophy developed in the Toyota Motor Company 21 (Womack et al. 1990). This term was used to illustrate the differences between the new production philosophy and mass production. For a more in depth information on lean assembly plant, lean supply chain, lean customer relations, lean production, the lean project delivery system, the last planner system of production control, and work structuring see appendix E. The lean assembly plant, lean supply chain, and lean customer relations sections are based on the book The Machine That Changed the World by Thomas et al. (1990). 2.2.1 ORIGIN OF LEAN PRODUCTION After World War II, Eiji Toyoda a young Japanese engineer and Taiichi Ohno chief production engineer both working at the Toyota Motor Company in Japan, established the concept of lean production. In 1950 Eiji visited Ford’s Rouge plant in Detroit. Back home in Nagoya, afier a thorough study of the Rouge plant, Eiji Toyoda and Taiichi Ohno concluded that mass production could never work in Japan. Even though Toyota was determined to enter a full-scale production of cars and commercial trucks they had to face several problems. The Japanese market was very small and demanded different types of vehicles: luxury cars for government officials, large trucks to carry goods, small trucks for farmers and small cars for Japan’s crowded cities and high energy prices. During this time the Japanese work force was in search of more favorable employment conditions favored by new labor laws introduced by American occupation. Moreover, the devastated Japanese economy could not afford the latest Western production technologies. In addition, huge motor vehicle producers were anxious of establishing their operations in Japan and were ready to defend their established markets from Japanese exports. This 22 provoked the Japanese government to prohibit foreign investment in the Japanese automobile industry. It did not take long for Taiichi Ohno to conclude that Detroit’s tools and methods were not suited to become a full-range car producer with varieties of new models. From this point on was born what Toyota called the Toyota Production System now called lean production. One of the major problems faced by Ohno at this time was how to reduce the amount of machinery required to produce the metal parts stamped from sheet metal used to produce motor vehicle bodies. Craft producers such as Aston Martin, cut sheets of metal and beat it by hand on a die to get the final Shape. A die is a hard piece of metal with the shape the Sheet metal should adopt. To produce cars in a larger scale the procedure adopted by automakers such as GM was different. They first started by cutting flat pieces of sheet metal, slightly larger than the final part, out of a big roll of sheet metal. For this operation an automated machine was used to produce stacks of these pieces. Then they inserted these pieces in enormous stamping presses containing upper and lower dies that matched to produce different body parts such as fenders. These expensive press lines were designed to produce over a million of a given part a year. The dies in the press could be changed to produce different parts but this procedure could take a day. The problem was that the dies were very heavy and specialists had to align them with absolute precision otherwise they could produce wrinkled parts or even melt the sheet metal. For Ohno this procedure was impossible to implement because he would have required hundreds of stamping presses and he could only afford a few press lines. Instead 23 he developed simple die changing techniques (using rollers) which by late 1950’s took only three minutes and could be done by the same production workers that otherwise would be idle. The die changes were performed every two or three hours versus two to three months. Surprisingly, Ohno discovered that using this procedure each part could be produced at a lower cost. One reason was that it eliminated the cost of enormous inventories required by mass production systems. Probably the most important reason was that by making small amount of parts before assembly mistakes could be detected immediately. Another radical change was experienced by the Toyota Motor Company when, due to macroeconomic problems, the car business experienced a big crisis in Japan. Kiichiro Toyoda, president of the company, decided to survive the crisis by firing a quarter of the workforce. The workers went on a strike. They were in a strong position to Win the strike supported by several law changes that restricted the ability of company owners to fire workers. After negotiations with the union, it was decided that a quarter of the workforce was going to be terminated but Kiichiro Toyoda had to resign. In addition, the remaining employees were granted lifetime employment and their pay increased with seniority. Employees were now considered as fixed costs. In Table 2 the characteristics of lean production are summarized and contrasted to the characteristics of mass production. The first element mentioned in the table refers to characteristic of lean production of producing different products in less time. This is possible due to the flexible machinery used in lean production. Flexible machinery is machinery that can be moved or adapted easily to fabricate different products. At the same time having flexible machinery enables the fabrication of a wider variety of 24 products with less machines. In mass production the machinery is more rigid, this means that the parts are produced for a longer period of time. As a result, large inventories of parts are required. The last element, workforce stability, is used to describe how Toyota employees had lifetime employment. Table 2: Mass vs. Lean Production characteristics (Information from Womack et al. 1990) CHARACTERISTIC No. ELEMENT MASS PRODUCTION LEAN PRODUCTION 1 Product variety Low High 2 Machinery Inflexible Flexible 3 Numtier 0f High Low machines 4 Inventories High Low 5 Workforce stability Low High 2.2.2 DEFINING LEAN PRODUCTION Lean production can hardly be defined in one phrase. It consists of various principles, methodologies and tools. Lean production is primarily a customer-based production philosophy whose main objective is the reduction or elimination of non-value adding activities from the production process while maximizing value adding activities. In this 25 way, lean production focuses on adding value to a raw material as it advances through various processing steps until it becomes a finished product (Tommelein 1998). Koskela ( 1992) defines value adding and non-value adding activities as follow: 0 A value adding activity is an activity that converts material and/or information into that which is required by the customer. 0 A non-value adding activity (also called waste) is an activity that takes time, resources or space but does not add value. It must be understood that value is generated by satisfying customer requirements. Who is the customer? There are two types of customer for each activity: the following activities (also called internal customers) and the final customer (people using the facility) (Koskela 1992). What does the customer require? The following activities require the output of previous activities so that they can execute their work. For example, the structural steel erector requires steel members to perform the erection process. The final customer requires the completed building in compliance with the plans and specifications. While all activities expend cost and consume time, only conversion activities add value to the material or piece of information being transformed into a product. For this reason non-value adding activities (inspection, moving, waiting) through which value adding activities are bound together should be reduced or eliminated, while conversion activities should be made more efficient (Koskela 1993). Waste is anything that does not directly add value to the final product but consumes resources. That means that transportation of materials, set up of equipment, idle or waiting time of workers and equipment, and unnecessary stock of materials are all 26 considered waste. We know that some of these activities such as transportation of materials to the site, set up of equipment and certain inspections are unavoidable. Without them it would be practically impossible for a construction process to work. For these reason there are two categories of non-value adding activities. The ones that are unavoidable with current technologies and production assets are called non-value adding contributory activities and the ones that can be excluded from the process are called non- value adding idle activities (Al-Sudairi 2000). Any conversion activity that adds up to the final product is usually considered value adding. Examples of the different types of activities found in production processes can be found in figure 6. Some times, waste TYPE OF ACTIVITIES I NON-VALUE ADDING ACTIVITIES I VALUE ADDING CONTRIBUTORY DELAY ACTIVITIES ACTIVITIES ACTIVITIES (Type-1) (Type-2) Any conversion activity . Transportation . Waiting The efficiency of 0 Preparation work 0 Idle conversion activities is 0 Setting up 0 Piling up materials very crucial to improving equipment 0 Double handling any process ’ Batch & Queue 0 Transition among 0 Delivery of material sub-processes 0 Most of paper work 0 Inspection Figure 6: Types of activities encountered in any product development (Al-Sudairi 2000) 27 could be found within value adding activities. This is the most difficult type of waste to detect. This type of waste could be present in the form of an inefficient or ineffective process. Taiichi Ohno classified the sources of waste as follows (Womack and Jones 1996k 1. Defects of products 2. Over-production of goods not needed 3. Inventories of goods awaiting further processing or consumption 4. Unnecessary processing 5. Unnecessary movement of people 6. Unnecessary transport of goods 7. Waiting by employees for process equipment to finish its work or for an upstream activity to complete 8. Design of goods and services that fail to meet user’s needs In lean production various principles have been developed in order to enhance flow process design, control and improvement. These principles can be applied to almost any type of production system and they are (Koskela 1992): 0 Reduce the Share of non-value adding activities (also called waste). 0 Increase out put value through systematic consideration of customer requirements. 0 Reduce variability. 0 Reduce cycle times. 0 Simplify by minimizing the number of steps, parts and linkages. 0 Increase output flexibility. 0 Increase process transparency. 28 Focus control on complete process. Build continuous improvement into the process. Balance flow improvement with continuous improvement. Benchmark. 2.2.3 LEAN PRODUCTION PRINCIPLES AND METHODOLOGIES Among all these principles probably the most important is the reduction of non-value adding activities. Specifically in construction there is a very high share of non-value adding activities that obstruct the production process. There are also several existing methodologies that are used to attain lean production. Some of the most important ones are (Koskela 1992): Just In Time (JIT) Total Quality Management (TQM) Time Based Competition Concurrent Engineering Process Redesign (Reengineering) Value Based Management Visual Management Total Productive Maintenance (TPM) Employee Involvement All of these methodologies are partial approaches towards the improvement of a production system. Each methodology has its own set of techniques that have been developed. 29 2.2.4 LEAN CONSTRUCTION Adapting the lean production philosophy to construction is not a straightforward process. The construction industry is different from the manufacturing industry preventing the direct implementation of lean principles. Some of the differences include: one of a kind nature of projects, site production, and temporary multi-organization (Koskela 1993). In other words every project is different, built in a different site with different characteristics and by different project participants. The Lean Construction Institute (LCI) is an organization whose purpose is the adaptation of lean production to construction. Although there has been considerable amount of research done in the area of lean construction, less is known about it in the field of practice. 2.2.5 PROBLEMS IN CONSTRUCTION The efficient and effective administration of today projects has become a challenge for current construction management practices. There are an incredible number of parties involved in the construction process. Coordinating all these project participants seems to be almost impossible. With the years, projects have been growing more complex and it is hard for current construction management practices to keep up with the pace of this demanding industry. Although construction management information systems help alleviate some of the needs of the construction industry there is still a lot to be done. Construction management practices need to be advanced to solve basic problems. Several authors have criticized current construction project management practices. According to Koskela (1992), problems in construction are a result of the neglect of information, material and work flows. He explains how conventional 30 managerial methods like CPM (Critical Path Method) deteriorate flows by violating the principles of flow process design and improvement leading to an expansion of non-value adding activities. The CPM method views the construction process as a set of activities to be controlled and improved individually, forgetting that they are part of a bigger process FABRICATOR Fabrication and delivery of structUral steel CONCRETE CONTRACTOR Placement of anchor rods STEEL ERECTOR Erection of Structural Steel DECKING CONTRACTOR Metal decking and shear studs CONCRETE CONTRACTOR Reinforcement and pouring slabs Figure 7: Interdependence of activities in the structural steel erection process and most activities are related with each other. The work performed by a trade is required for the next trade to perform. Figure 7 presents a clear example of the interdependence 31 between activities in the erection of the structural steel frame of a building. The way work is handed from one trade to another has a direct impact in the succeeding trade performance. In some projects materials, information and work flows are neglected and current construction project management methods do not address this issue (Koskela 1992). This problem is aggravated by some contractual relationships existing in the construction industry in which the work is evaluated according to the cost and duration and have little consideration of how it may affect others. In some projects there are no mechanisms in place that prevent mistakes from occurring. Continuous improvement should be built in the system to learn from previous problems. For example, in some projects, when a deviation in cost and time is detected the project is brought back to schedule by focusing in the following activities. This means that downstream activities pay the price for mistakes done in upstream activities. The root causes that provoked the deviation in the first place are sometimes not addressed. Chances are it will happen again in the next project. According to a study by Tommelein et al. (1998), one of the shortcoming of using the Critical Path Method for field level planning is that it does not explicitly represent reliability between successive trades. This study illustrated the impact of work flow variability has on succeeding trade performance. Using a game, construction processes in which resources produced by one trade are prerequisite to staring work for the next trade were simulated. The game shows how waste and project duration can be reduced by improving the reliability of work flow between trades. Reliable work flow means that work is handed from one trade to another in a dependable way. 32 Schedules are sometimes not an accurate measurement of project performance. Research by Ballard (1997) suggests that schedules and budgets assume that poor performance will occur. On the project he studied, more than 30% of engineering deliverables were late on average by 56 days. Surprisingly the project was finished on time and on budget. Even though projects meet cost and time requirements they continue to have considerable amount of waste in them. 2.3 RESEARCH ON STRUCTURAL STEEL ERECTION Most of the research on structural steel has been performed from a design and materials standpoint. Limited research is available on production management of the structural steel erection process. Perhaps the reason is that steel erection is considered to be a relatively fast and efficient process. 2.3.1 APPLYING LEAN PRINCIPLES TO THE STRUCTURAL STEEL ERECTION PROCESS Womack and Jones (1996) summarized lean thinking into five key lean principles: precisely specify value by specific product, identify the (value stream for each product, make value flow without interruptions, let the customer pull value from the producer, and pursue perfection. According to Womack and Jones by understanding these lean principles and using them together managers can make a complete use of lean techniques. As stated by Womack and Jones (1996) lean thinking starts by defining value for a specific product from the customer’s point of view. That is, what the customer needs and wants from a specific product. Then the value stream for each product should be identified. The value stream is the set of actions required to produce a specific product, service or a combination of both. The actions that are part of the value stream can be classified in three different groups: steps that create value, steps that create no value but 33 are unavoidable with current technologies and production assets, and steps that create no value and can be avoided. In this thesis these steps or activities are referred to as value adding activities, non-value adding contributory activities and non-value adding idle activities. After eliminating wasteful steps the remaining value creating steps should flow continuously. The next principle consists of letting the customer pull the value from the producer. This means that customer needs should determine the production of goods rather than producing more goods than needed and pushing them to the customer. The last principle is to pursue perfection. This means that lean thinking does not stop by applying the previous four lean principles once. It is a continuous effort of reducing steps that create no value or muda. An investigation that studied the applicability of lean principles to the structural steel erection process is Evaluation of Construction Processes: Traditional Practices versus Lean Principles by Al-Sudairi (2000). Al-Sudairi explored what would be the results of applying lean principles to the structural steel erection process using computer simulation. First, he modeled the actual steel erection process. Then the five lean principles presented in Table 3 were considered in the model and the improvements in cycle time, productivity, utilization and throughput measured. Table 3 also summarizes the changes made to the model in relation to each principle. This process was applied to three different projects that varied in size and complexity. In this way be evaluated the impact these lean principles had in different projects. It was concluded that lean principles improved project performance by more than 30% when compared to traditional practices and that lean principles had a bigger impact in more complex larger projects. 34 Al-Sudairi also concluded that not all lean principles are applicable to the structural steel erection process. This conclusion was based on the results he obtained when “uncontrollable” factors such as traffic and delivery errors were applied to the computer model along with other lean principles such as the pull principle. Al-Sudairi implemented the pull principle by having small buffers of materials on site to supply immediate demands. Then he considered other factors such as variations in activity Table 3: Principles and changes to the model in Al-Sudairi’s study (Adapted from Al- Sudairi 2000) PRINCIPLE CHANGES TO THE MODEL Specify Value Materials were fabrIcated by bays Instead of levels Reduce contributory activities by Eliminate Muda combining unload activities to shakeout activities Rethink Your Operating Methods Buffer size is changed from big to medium Similar changes to principle 1, the Focus on actual objects from difference is that value is observed within beginning to completion erection process with small buffer size and strong coordination Materials are pulled from fabricator yard at the right time in the right quantity to the erection site All the aforementioned changes besides unload and shakeout activities were eliminated and rework rate was assumed to be zero Release resources for delivery just when needed Form a picture of perfection duration, traffic conditions and errors in material sequence. When these factors were considered in the model along with the pull principle the system became volatile. A pull 35 system, as explained by Womack and Jones (1996) is a system of dictating production and delivery instructions from downstream to upstream activities in which nothing is produced by the upstream supplier until the downstream customer Signals a need. The pull principle is one of the bases of the famous just-in-time system. The just-in—time system advocates producing and delivering the right items at the right time in the right amounts (Womack and Jones 1996). That means that if there are known uncontrollable factors they should be considered in the sizing of buffers so that the system runs smoothly. As lean principles and techniques are applied to the process these queues of materials tend to be reduced to a minimum. Even though Al-Sudairi’s investigation provided valuable insight about the presence of non-value adding activities in the structural steel erection process more research is needed to investigate new ways of removing non-value adding activities. In his investigation instead of removing non-value adding activities of unloading and shakeout from the structural steel erection process be combined them eliminating several steps to make the process more efficient. When there is an attempt to remove non-value adding activities from a process existing barriers found in the process should be ignored. In this way we do not limit ourselves to current production assets and technologies (Womack and Jones 1996). The barrier in this case was the difficulty of completely removing unloading and shakeout from the process. 2.3.2 JUST IN TIME IN THE STRUCTURAL STEEL SUPPLY CHAIN Just-in-time (JIT) is based on a pull system; this means that parts are produced in previous steps only to supply the immediate demand of the following steps. Ohno used a Simple mechanism to give the order to upstream steps to produce more parts. In his 36 system parts were supplied to the following steps using containers. When a container was used up, it was sent back to the previous step indicating them to produce more parts (Womack and Jones 1996). In this way containers worked as feedback mechanisms Signaling stations upstream that more product is needed. For this system to work efficiently there must be the appropriate number of containers to supply parts so that the process runs smoothly without having to stock parts or stop the process to wait for more parts. On the contrary, in push systems parts are produced by upstream suppliers based on forecasts that sometimes do not reflect reality. As a result the number of parts may be so much that needs to be stocked or there may be so few that the process needs to stop, in both ways waste is produced. More Just-In-Time: Location of Buflers in Structural Steel Supply and Construction Processes a paper by Tommelein and Weissenberger (1999) specifically addressed JIT in the structural steel supply chain. Their objective was to explore if JIT was being utilized in the structural steel industry by means of reviewing literature and interviewing steel fabricators, erectors and contractors. They explained how if JIT was used in the supply chain, materials should be brought to their location for final installation and be installed immediately upon arrival without incurring in any delay due to storage in a lay down or staging area. The paper presented common industry practices in the structural steel supply chain for building construction to later illustrate a JIT idealized version of the same supply chain. Following is in brief their explanation of the supply chain and its JIT version. Commonly on design-bid-build projects the owner hires an architectural engineering (AE) firm, which in turn hires a structural designer. At the beginning of the 37 process, the owner and designer go through a lengthy and iterative process of defining project requirements that will be part of the bid documents. Then the project is put out for bid and a general contractor (GC) selected. The GC subcontracts the steel work to the fabricator who subcontracts the field installation work to a structural steel erector. The responsibility of the fabricator is to acquire, fabricate and Ship the materials to the site in the sequence needed for erection. The fabricator may also subcontract detailing work. The GC will meet with the fabricator and erector during bid preparation to assess project site constraints to position the erector’s crane. This will determine the steel erection sequence and the layout of other temporary facilities. This sequencing drives the fabrication schedule that must coincide with the GC’s master schedule. Special consideration must be given to the time it will take the fabricator to procure the materials. The fabricator will make takeoffs and procure materials from the mill as soon as possible, even before detailing connections and creating shop drawings. This is done because steel mills usually work on 6 week rolling schedules. Meanwhile details and shop drawings will be created and submitted to the designer through the GC for approval. Materials received by the fabricator will be stored in a lay down area from where they will be retrieved for fabrication. In the fabrication shop a significant amount of handling back and forth of steel pieces is the result of the fabricator’s objective of maximizing machine and labor utilization. The fabricator gets paid in full for delivery of the structural steel to site even if the site is not yet ready to receive it. In this way the fabricator has the incentive to complete as much work as early as possible. The fabricator will thoroughly plan the sequencing and site delivery of steel pieces in the order they will be needed on site. It is very common in building construction to have scarce space on site that is why 38 careful planning iS required. Once steel arrives on Site the crane off-loads and moves pieces to a staging area from where steel is picked up and moved to its final position in the structure. According to Tommelein and Weissenberger (1999) in an ideal just-in-time system, there should be two pull mechanisms in the steel supply chain described as follows. The first pull mechanism controls the amount of steel produced by the mill. Part of the production fi'om the mill is dictated by custom orders. The other part of the production is dedicated to run-of-the-mill product in anticipation of custom orders. This product is stored in a place with limited capacity for storing product that will be replenished once it is needed. The second pull mechanism will handle the output from the fabrication process. Only a certain amount of steel will be fabricated to supply the erection process. In this case, a small inventory buffer may also be needed to balance fabrication and erection processes. No buffer should be maintained on site because there is no space. Although this approach of applying JIT'in the structural steel supply chain is a step in the right direction there is more to be considered. As mentioned earlier, structural steel an'iving on site should be erected on a first-in—first-out basis without having to store it. There needs to be certain amount of steel available for the erection crew to work continuously. In addition, the amount of steel waiting to be erected should consider other factors such as heavy traffic. A pull mechanism should be used to control the size of this queue of structural steel. This would eliminate unnecessary double handling of steel pieces during unloading and shakeout and the erection crew would be performing “productive” nearly uninterruptedly. In an ideal situation steel could be loaded on trailers 39 so that it could be erected directly from them. Trucks would not be idle because they would leave loaded trailers and would bring the empty ones back to the shop. In this case empty trailer trucks arriving to the fabricators’ shop could indicate the fabricator that more structural steel needs to be delivered to the site. This is similar to Ohno’s mechanism where used up empty containers of parts coming from downstream stations indicated upstream stations that more parts needed to be produced. Without some kind of pull mechanism controlling the amount of material on site, JIT would be difficult to implement in this part of the process. 2.3.3 DELIVERY APPROACHES AND LABOR PRODUCTIVITY Once structural steel is fabricated it is ready to be sent to the site where it will be erected. There are different approaches of delivering structural steel members to the Site. Thomas et al. (1999) studied the impact that approaches methods had on the erection crew productivity. Three projects that used different delivery approaches were studied. In the first project only three deliveries of structural steel were made, stockpiling randomly steel members on site. In the second project, steel deliveries were made during the course of the work interrupting erection operations. This means that the erection crew had to stop hoisting steel pieces in order to unload and shakeout steel pieces from the truck. Materials were double handled as part of unloading and shakeout activities. In the third project, steel was delivered and erected daily from the truck. Daily productivity data for each project was recorded (work hours per piece of steel, wh/pc). Other data that could potentially affect productivity was documented including temperature, weather conditions, and important events affecting the work. A multiple regression model was used to quantify the effect material deliveries (amongst other factors including snow, 40 wind, temperature and crane relocations) had on productivity. To compare delivery methods the work hours lost due to poor material management were estimated for each project. The first project lost 0.48 wh/pc (16% of total work hours) due to disorganized delivery and storage practices. The second project lost 0.27 prc (14% of total work hours) as a result of double handling steel members. The losses on the third project Were 0.07 Wh/pc. On the workdays in which material deliveries were made there was a loss of productivity of almost 40%. Table 4 is a summary of the work hours lost for each project. Table 4: Comparison of material delivery methods (Adapted from Thomas et al. 1999) LOST MATERIAL TOTAL $313; 135131;: WORK PROJECT DELIVERY WORK HOURS OF HOURS METHOD HOURS LOST PIECES PER PIECE 1 Dump and Hunt 1,256 200.6 414 0.48 Unload and 2 shakeout each 768 108.9 395 0.27 truck Erect steel directly from truck, 3 shakeout by 526 27.3 399 0.07 fabricator This investigation concluded that erecting structural steel directly from the delivery truck was the most efficient erection method. Thomas’ Study suggests that considerable improvements could be made to the structural steel erection process by eliminating double handling of steel pieces as a result of unloading and Shakeout activities. 41 Results from this investigation are very revealing because the common industry practice involves unloading and shakeout structural steel members before their erection. The results from this investigation are directly influenced by the characteristics of each project. Further investigation of projects with different characteristics is needed to support the conclusion about delivery methods. In addition, “point efficiency” can sometimes be misleading. Even though productivity of the erection crew is higher when structural steel is erected directly from the delivery truck, it does not mean that the process is more efficient. Changes in the erection method may have an impact in upstream activities resulting in an overall low efficiency. For example, additional time might be needed to sort steel by the fabricator in order to load the trucks in inverse order so that they can be erected directly from the truck. The inclusion of these upstream activities in developing conclusions about removing loading and shakeout is an important contribution of this investigation. 42 CHAPTER 3: METHODOLOGY 3.1 METHODOLOGY INTRODUCTION Although lean production can be very valuable in the manufacturing industry, researchers and practitioners are continuously exploring how it can be employed in the construction industry. Koskela (1992) suggests: I “The inherent recommendation of the new philosophy to construction practitioners is clear: the share of non-value adding activities in all processes has to be systematically and persistently decreased. Increasing efi’iciency of value adding activities has to be continued in parallel. The basic improvement guideline is thus: get started, define processes, measure them, locate and prioritize improvement potential, implement improvement and monitor progress! Process definition and measurement is crucial. Work processes must first be made transparent by charting them. Next, the inherent waste in processes must be made visible through suitable measures, and targets and monitoring should be focused on it. " This means that the first step is to map the process. Then appropriate measurements should be used to uncover existing waste in the process and determining opportunities for improvement. Afterwards possible improvements to the process should be estimated to establish if they Should be implemented. Finally, Koskela (1992) proposes to implement improvements and constantly monitor the progress. The methodology used in this research is similar to the approach proposed by Koskela (1992). This thesis is divided into six distinctive phases. In the first phase, 43 available research related to lean production and structural steel erection was compiled and analyzed and opportunities to improve the structural steel erection process were examined. After determining the theoretical course of action adopted in this research, a local fabricator and erector was visited and key personnel interviewed with the objective of mapping the structural steel erection process by producing a process model (Phase II). The purpose of the third phase was to create an alternative procedure with the exclusion of unloading and shakeout from the erection process. Then, in the fourth phase, the researcher determined if it is economically feasible to implement the alternative model. In Phase V the alternative process was presented to the construction industry with the objective of receiving feedback on it. The last phase summarizes this research, presents findings and provides recommendations. 3.2 PHASE I: LITERATURE REVIEW On the first phase of this investigation available literature on lean production and structural steel erection was compiled and studied. The first step was to gain an understanding of tools that could help in improving current construction practices. In this sense, the researcher examined literature on lean principles. The next step involved investigating the current status of research related to structural steel erection and determining opportunities to improve it. Methodologies used to improve steel construction were also studied. 3.3 PHASE II: TRADITIONAL PROCESS MODEL DEVELOPMENT A process model that describes the structural steel erection process was created in this phase. This process model is referred to as the “traditional process model”. The model helps visualize the activities that are part of the process and how they are related with 44 each other. Four steps were taken to create the traditional model and they are: company selection, on site observations, investigation interviews and traditional model creation. Step 1: Company Selection A fabrication and erection company was selected primarily based on specialty, geographic location and their interest in participating in the study. The selected company Specializes in fabrication and erection of structural steel. This facilitated the communicating and coordinating with personnel in fabrication and erection processes. The participating company was invited to participate in this investigation by allowing the researcher perform the following activities: study their structural steel erection process, conduct interviews with key personnel directly involved with the process, and provide information on the case study project. Step 2: On Site Observations In this step the researcher observed, understood and learned how the company performs fabrication, storage, loading, transportation, unloading, shakeout and erection activities. These observations were the starting point of the traditional process model. Step 3: Investigation Interviews Interviews were conducted with key personnel within the selected company to obtain information on technical details included in the creation of the traditional process model. In addition, interviews help gain valuable insight on how to create the alternative process model. These interviews were complementary to on site observations performed in the previous step. Personnel interviewed were: the 45 project manager, shipping and delivery foreman, and erection foreman. Interviewees were contacted via telephone to solicit their participation on the interviews and given their approval, to schedule each interview. In the interview, each interviewee was first asked to read a UCRIHS (University Committee on Research Involving Human Subjects) approved consent form. Then interviews were conducted. Responses provided were summarized. The consent forms, questions and responses of the interviews can be found in appendix A. Step 4: Traditional Model Creation This was the final step towards the creation of a process model depicting the traditional structural steel erection process. Information gathered during the on Site observations and interviews was used to create the process model. The process model contains a step-by-step progression of activities in the structural steel erection process including storage, loading, transportation, unloading, shakeout, and erection activities. The main reasons for the creation of the traditional model were to document the process and to describe how all the different steps of the process work together. This mapping of the process was the reference point to build the alternative structural steel erection process model. 3.4 PHASE III: ALTERNATIVE PROCESS MODEL DEVELOPMENT The objective of this phase was to create an alternative process without the non-value adding activities of unloading and shakeout. Several changes were made to the traditional process in order to exclude these activities. In this sense the goal of this phase was to create a process that allows the erection of structural steel members directly from the truck. With this goal in mind the objectives of the alternative process were: 46 1. Store steel pieces on the fabricator’s yard so that it facilitates loading according to erection order. 2. Load the trailers to the same capacity as in the traditional loading activity. 3. Load the structural steel members on the trucks so that they can be erected in the exact order on Site. 4. Arrange the structural steel members on trailers so that it allows for easy attachment of chokers for hoisting. This phase was developed in six steps: Industry Survey, Alternative Model Creation, Case Study, Feedback Interviews, and Proof of Concept Interviews. First a survey was sent to fabrication and erection companies to receive information on how to create the alternative process. Then an alternative model was created excluding unloading and shakeout activities. After that, a case study was selected and information about it compiled. Next the researcher verified if the alternative model could be applied to the case study. Feedback about the alternative model was obtained by interviewing key personnel within the participating company. Feedback interviews had two purposes: determine if the model could be applied to the case study and receive suggestions on how the model could be improved. Before each interview the alternative model was presented including the procedure for loading steel pieces on trucks. Finally, proof of concept interviews were conducted. In this step the project managers of two fabrication and erection companies were interviewed to determine if the alternative process was applicable to other companies in the steel construction industry. Following is a detail description of each step taken. 47 3.4 11611 a 3.4.2, 1“ S] (T' t: 3.4.1 INDUSTRY SURVEY The main purpose of the survey was to obtain information on how the alternative process model could be created. The survey was sent via mail to a total of 56 companies members of either the Great Lakes Fabricators and Erectors Association or the Associated Steel Erectors of Chicago. Companies were selected based on their specialty, fabrication and erection of structural steel. Companies specialized on other areas of steel construction such as fabrication of miscellaneous steel and fabrication and distribution of rigging equipment were not considered for the survey. The survey was directed either to the president, vice-president, project manager or Operations manager of each company depending on who the designated contact was on the website of each association. The envelope sent to each company included a UCRIHS (University Committee on Research Involving Human Subjects) approved consent form, the survey and a stamped envelope to return the survey. The consent form, survey and responses can be found in appendix C. 3.4.2 ALTERNATIVE MODEL CREATION A process model describing the alternative process was created based on the literature, on site observations, investigation interviews and industry survey. This process model is referred to as the “alternative process model”. Activities that described include storage, loading, transportation and erection. The traditional model was modified to create the new alternative model. 3.4.2.] Special Issues A significant difficulty in creating the alternative process was determining how the pieces of steel should be loaded onto trailers. The steps taken to determine how steel pieces should be arranged on each truck were: 48 . Shop drawings of the case study project (described below) were acquired. . The order of how the steel pieces were erected on site for the case study was obtained from the erection foreman. . A list of all the structural steel pieces of the case study was obtained. The list also included the following information about each piece: piece mark, sequence, quantity, shape, length, and weight. . Pieces of structural steel were then grouped according to the sequence in which they were erected. . Pieces of steel within each sequence were listed in the same order they were erected on Site. . The steel pieces to be loaded on each truck were determined by the weight of each piece, the capacity of the truck and the erection order. . The cross section of each steel piece was drawn to scale using CAD software. . The section of the trailer where pieces will be loaded was drawn to scale using CAD software. . Several loading patterns were tested using the drawings of the structural steel pieces and the trailer. The optimum loading pattern was selected. 3.4.3 CASE STUDY The selected case study is representative of a common structural steel frame of a building. In this way this investigation can be applicable to most buildings. The chosen structural steel frame had the following characteristics: Not excessively complex. The structural steel pieces that were part of the structure did not have complicated curvilinear shapes. 49 0 Between 3 and 6 stories high. 0 There was enough area available on site so that unloading and shakeout activities could be done without limitations. Once the case study was selected, information from it was obtained to explore the applicability and economic feasibility of implementing the alternative process. The participating fabrication and erection company provided the following information on the case study project: 0 Shop drawings, e-drawings, and structural plans of the project 0 Erection order of the structural steel pieces 0 Number of trucks used to transport the structural steel members 0 List of all the fabricated pieces of steel. The list contained the following information about each piece: piece mark, erection sequence, quantity, shape, length, and weight. 0 Erection crew description 0 Schedule of the structural steel erection phase 0 Specification of the crane used for erection This information was used to plan the transportation activity (how each truckload of structural steel will be loaded) and to estimate the cost and duration of the traditional and alternative processes. 3.4.4 FEEDBACK INTERVIEWS After development of the alternative process model interviews were conducted of key personnel within the participating company to determine if the alternative steel erection process was viable for the case study project. Interviews with the project manager, 50 shipping and delivery foreman and erection foreman of the participating company helped explore if the alternative process is realistic, possible and safe. Interviewees were contacted via telephone to solicit their participation on the interviews and given their approval, to schedule each interview. In the interview, each interviewee was first asked to read a UCRIHS (University Committee on Research Involving Human Subjects) approved consent form. Then the researcher presented to them the traditional and alternative model found in figures 10 and 11. Subsequently, the process of how each truckload planned in the alternative model was explained using the tables and figures found in appendix D. Then interviews were conducted. Responses provided were summarized. The consent forms, questions and responses of the interviews can be found in appendix B. The interviews helped determine if the alternative process complied with the objectives established in section 1.5.3 for the alternative process. Through feedback interviews weaknesses and strengths of the alternative process were revealed. 3.4.5 PROOF OF CONCEPT INTERVIEWS The objective of this step was to present the alternative model to other industry members to determine if hte model would be applicable generally within other steel firms in the construction industry. The project manager of two fabrication and erection companies were interviwed. The process followed in proof of concept interviews was the same as the process of the feedback interviews. Interviewees were contacted via telephone to solicit their participation on the interviews and given their approval, to schedule each interview. In the interview, each interviewee was first asked to read a UCRIHS (University Committee 51 on Research Involving Human Subjects) approved consent form. Then the researcher presented to them the traditional and alternative model found in figures 10 and 11. Subsequently, the process of how each truckload planned in the alternative model was explained using the tables and figures found in appendix D. Then interviews were conducted. Responses provided were summarized. The consent forms, questions and responses of the interviews can be found in appendix B. Information obtained from these interviews helped validate the applicability of the model and to identify concern areas they may have about using the alternative process. 3.5 PHASE IV: ECONOMIC FEASIBILITY The main objective of this phase was to determine the time and cost reduction which might result from removing non-value adding activities of unloading and shakeout from the structural steel erection process. To achieve this objective the alternative steel erection process was compared to the traditional process by means of a cost and time analysis. This analysis was made using the information obtained on the previous phase about the case study, cost data from RS Means Building Construction Cost Data and productivity data from the structural steel erection process of a project similar to the case study project. The steps taken to analyze each process are described below: 0 Step 1: Duration and Cost of the Traditional Process The activities that impact the cost and duration of the traditional process are: transportation, unloading, shakeout and erection. The cost of transporting the pieces of steel was estimated using the actual number of trucks used in the case study and cost data from RS Means Building Construction Cost Data for the cost of the truck. Unloading, shakeout and erection cost was estimated using the 52 productivity data of a time study made by Al-Sudairi (2000). In this time study, Al-Sudairi recorded the time in seconds required to unload, Shakeout and erect structural beams and columns for three projects with different characteristics. The productivity data used for the calculations is of a project with similar characteristics to those of the case study. Productivity units are pieces of steel (beams or columns) per second. The duration of activities was estimated by multiplying productivity by the number of pieces. The duration multiplied by the cost of the crew (including crane) gave the cost of each activity. Finally the cost and duration of the complete process was determined by adding the cost and duration of each activity. Step 2: Duration and Cost of the Alternative Model The activities affecting the cost and duration of the alternative process are: Erection order planning (foreman must plan the erection order in the main office), loading activity planning (time required to plan the loading arrangement of the structural steel pieces, done by the project manager), shakeout at the Shop, transportation, and erection. The duration of planning the erection order was calculated using the time required by the erection foreman to plan the order in which each piece of steel will be erected. This duration was obtained from the investigation interviews. Planning the loading activity was estimated using the actual time spent by the researcher in this activity. With its duration and the hourly wage paid to the project manager (obtained from RS Means Building Construction Cost Data) its cost was estimated. The duration and cost of shakeout at the shop was estimated using the same procedure used in step 1 for the same 53 activity. The cost of the transportation activity was estimated using the same number of trucks used in the actual case study and cost data from RS Means Building Construction Cost Data for truck cost. Finally the cost and duration of the complete process was determined by adding the cost and duration of each activity. Step 3: Comparing Processes This part of the analysis is probably the most important because it helped determine possible improvements to the process as a result of removing unloading and shakeout activities from the structural steel erection process. The output of this analysis helped answer several questions. The estimated improvements to the process were compared to the extra time and cost required in other preliminary activities as a result of the alternative process. Advantages, disadvantages, weaknesses and strengths of each process were discussed using feedback from interviews and output of the cost and time analysis. Results of these analyses helped determine possible benefits or losses of applying this lean principle (using this method) to the steel erection process of a project. 54 CHAPTER 4: THE TRADITIONAL PROCESS 4.1 INTRODUCTION TO THE TRADITIONAL PROCESS The traditional process model was created based on information from the literature review, on Site observations, and investigation interviews. It is a description of the structural steel erection process as performed by the participating company. The traditional process model illustrates the different steps that take place when erecting structural steel. Activities performed by the fabricator were included because they are affected as a result of removing unloading and shakeout activities from the erection process and erecting structural steel directly fiom the delivery truck. 4.2 ON SITE OBSERVATIONS The researcher visited the fabrication shop of the participating company with the objective of observing the fabrication process. The first area of the shop visited was the materials storage area. In this area, material arriving from the mill is organized and stored. Once Shop drawings are generated and approved by the designer, the fabricator can commence fabricating structural steel members. At this time raw steel is transported into the shop using a conveyor and structural steel members fabricated by cutting, drilling, shearing, punching, welding and assembling steel as Specified in shop drawings. In the shop, pieces of steel are divided into heavyweight or lightweight and fabricated in different areas. Pieces that. are alike are fabricated at the same time even though they might belong to several different sequences. This practice is considered by the fabricator to be more cost effective. When the schedule is tight and erection of steel is required as soon as possible, steel members are fabricated according to erection sequence. 55 After structural steel is fabricated, it is transported to a lay down area where it is stored. Structural steel is transported to the Site once the location and strength of leveling plates and anchor rods is verified and the on site crane is all set. Then trailers are loaded by packing steel as close together as possible with the purpose of transporting more steel with fewer trucks. Steel is transported according to erection sequence. The researcher also visited an on site project approximately three times a week during all the erection phase to get acquainted with the process. Steel was delivered by sequence after the crane was mobilized and assembled. Once structural steel arrived on site unloading and shakeout activities took place. Sequences were erected by hoisting first all the columns and then the primary and secondary beams on each bay of the sequence. This was similar to case study of Thomas et al. study (1999). 4.3 INVESTIGATION INTERVIEWS The project manager, shipping and delivery foreman and erection foreman of the participating company were interviewed. Interview questions were developed based on the fabrication and erection process of a common structural steel frame of a four-story office building. Questions and paraphrased answers of the investigation interviews can be found on Appendix A. The interviews were oriented towards obtaining information on four areas: company and personnel demographics, structural steel erection process details, observed problem areas and possible solutions in the process, and on erecting directly from the delivery truck. Demographic questions referred to company and employee experience, market niche, and projects executed per year. By means of these questions it was found that the personnel interviewed has extensive experience in their positions. The selected company 56 has over 50 years fabricating and erecting structural steel. Common projects executed by this company include office and commercial buildings between two to six stories high and an average total area of 100,000 square feet. Questions about the structural steel erection process were included to complement the information obtained from the on site observations. The questions focused on Specific details about the erection process. This company fabricates structural steel by sequence when the schedule is tight and requires erection to commence as soon as possible. A sequence is a section of the building to be erected. After each piece of steel has been fabricated they are marked with their piece mark, sequence number and project number. Labeling of steel members occurs before they are stored in a lay down area according to erection sequence. Delivery of steel is also made according to erection sequence. Trailers are loaded first by placing a uniform layer of steel and then by arranging pieces with similar sections on the other layers. Pieces of steel are packed as close together as possible so that they can be transported in lowest number of deliveries. Each load of steel is required to weigh a maximum of 56,000 pounds and has a maximum height from the ground to the top of steel on the truck of 13 feet and 6 inches. Erection Starts when at least 40% of the steel members have been fabricated, otherwise the erection crew may run out of steel to erect. The field general superintendent divides the building into sequences. On Site, the erection crew foreman plans the order in which each piece of steel is erected. Each piece is be labeled with this number. This is done on the day or preceding day for erecting that particular sequence. The erection crew foreman is also in charge of determining the location where unloading and shakeout will occur. This decision is based on several factors: availability of space on site, easier maneuverability 57 of the crane, easier unloading of the trucks and faster erection. When more steel pieces are required on Site, the erection foreman will order them from the Shop. Some questions about the process also centered on gathering information about crews, equipment used in the process and normal durations of activities. This data was used in the cost and time analysis performed in chapter 6. It was established that the crew used by the participating company to load fabricated pieces of steel on trailers consists of one crane operator, one 27'/2 ton mobile crane, two ironworkers on the trailer, one ironworker hooking steel and one shipping and delivery foreman. The shipping and delivery foreman invests approximately 25 percent of his time in planning the deliveries. Trailers are loaded in approximately two to three hours with an average of 41,500 pounds of steel. On site, the erection crew consists of one erection crew foreman, two ironworkers connecting steel, two ironworkers hooking steel on the ground, one crane operator and an oiler if required. It takes on average one hour for this crew to unload and shakeout a truckload of steel. Planning how each Specific piece of steel will be hoisted takes on average 25 minutes for the erection foreman. Another set of questions had the purpose of identifying opportunities for improving the process and possible ways to do it. The personnel interviewed have extensive experience in their area and their views are valuable. A problem identified by the project manager and the erection foreman was that the design of the structure is either incomplete or late changes are made to it that affect the efficiency of the fabrication and erection process. There were several inefficiencies identified by the shipping and delivery foreman. One of his concerns was that the pace of the fabrication process was very irregular. In other words, sometimes the output of fabricated steel varies too much. 58 Having to handle a number of fabricated pieces of steel that differ too much from the crew capacity is inefficient. Since steel is stored in a yard by sequence (before it is delivered to a Site), the shipping and delivery foreman also has difficulty handling the batches of fabricated pieces of steel because they belonged to different sequences. In addition, he explained that sometimes the sequences are either too big or too small (number of pieces per sequence). Both situations create problems when handling pieces of steel. If the sequence is very big, the pieces required on Site may be at the bottom of a pile. If the sequence is too small, some of the trailers are not loaded to their full capacity. Finally he said that he does not have enough information about the size of each sequence, making it difficult to allocate space for each sequence in the lay down area. Possible solutions to these inefficiencies revealed by the investigation interviews included: start fabrication and erection activities with a complete and accurate design, fabricate steel pieces continuously, fabricate according to erection sequence, plan each sequence uniformly, and make information about the process available. The last set of questions focused on the creation of the alternative process model. Areas of concern included: experience using this alternative delivery and erection method, possible ways of implementing the alternative process and potential problems and solutions of its implementation. Information gathered from this group of questions is very similar to the information gathered from the industry survey. For this reason, they will be discussed in chapter 5. 4.4 THE TRADITIONAL PROCESS MODEL The traditional process model (figure 8) depicts the activities that are part of fabrication and erection processes. In addition it illustrates the sequence in which these activities are 59 performed. The traditional process model was created with information obtained from on Site observations and investigation interviews presented in the two preceding sections. The traditional process model describes activities in fabrication and erection processes starting after the conclusion of the detailing process and concluding when pieces of steel are hoisted and fastened in their final position in the structure. When required by the schedule, fabrication of structural steel is performed according to erection sequence. The next activity in the traditional model refers to labeling of structural steel members with their piece mark, erection sequences and job number. Then Structural steel is stored on a lay down area according to erection sequence. The following activity consists of verifying that the location of anchor rods and leveling plates coincides with what is specified in the plans. After anchor rods and leveling plates are surveyed, steel pieces are loaded on trailers and delivered to the Site for erection. Steel is not delivered until the crane has been mobilized and assembled on Site. Once steel arrives on site, the erection crew foreman decides where unloading and shakeout of structural steel will take place. The erection foreman will also plan the exact order in which each piece of steel will be hoisted. After unloading and Shakeout activities 'are done each piece of steel is marked with the planned erection order. The succeeding activity comprises attaching chokers to the pieces of steel to be hoisted. Finally, pieces of steel are hoisted to form the structural frame of the building. 60 TRADITIONAL PROCESS MODEL DETAILIN G PROCESS O Fabricate structural steel according to erection sequence 0 Label pieces of steel with its piece mark, erection sequence, and project number 0 Store steel according to erection sequence 0 Figure 8: Traditional Structural steel erection process including fabricator activities 61 9? Verify anchor rods and I leveling plates location 0 L080 trucks by tightly Mobilize and assemble on site packing preces of steel crane 0 Deliver structural steel Over 30 years QUESTION 3 COMPANY Over 15 projects 5 -— 10 projects Over 15 projects Over 15 projects Over 15 projects Over 15 projects Over 15 projects Over 15 projects Over 15 projects H—ICHHUOW> Over 15 projects 136 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 4 COMPANY Buildings and industrial facilities Buildings Buildings Bridges Buildings Bridges Buildings and bridges Buildings Buildings a—mnmmenw> Bridges, Buildings and Industrial Facilities QUESTION 5 COMPANY 3 - 6 stories 3 - 6 stories 1 — 2 stories Not applicable 1 — 2 stories Over 6 stories Different stories l — 6 stories 3 — 6 stories E—ID'I'IFJUOW> 1 to over 6 stories QUESTION 6 COMPANY Most but not all steel is fabricated before erection starts Most but not all steel is fabricated before erection starts Most but not all steel is fabricated before erection starts All structural steel is fabricated before erection starts Most but not all steel is fabricated before erection starts Most but not all steel is fabricated before erection starts Most but not all steel is fabricated before erection starts Most but not all steel is fabricated before erection starts Most but not all steel is fabricated before erection starts HHEOMMUO§> Most but not all steel is fabricated before erection starts 137 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 7 COMPANY a. Changes by the architect/engineer b. Late release of shop drawings c. Inaccurate or incomplete design drawings d. Detailing mistakes e. Coordination of trades at the jobsite a. Design changes b. Lack of information c. Insufficient lay down area (1. Enforcement of more stringent safety a. Steel does not fit due to detailing errors a. Hole alignment a. Missing pieces b. Out of sequence deliveries c. Detailing/fabrication errors (1. Roof frame locations/dimensions not available at start of erection ~ Not answered a. Steel not properly detailed in the shop drawings Not answered a. Fabrication errors b. Detailing errors 0. Shipments out of sequence (1. Bad work site e. Concrete and anchor rods placement errors a. Out of sequence deliveries b. Crane access c. Anchor bolts errors (1. Site conditions e. Changes 138 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 8 COMPANY a. Standardize design drawings b. Complete designs to minimize changes c. Checking of detail drawings (1. Subcontractor input on scheduling a. Finish design prior to bidding b. More complete design drawings c. Improve site conditions (1. Follow OSHA not CMA safety plan a. Better attention to detail drawings U Not answered 1!! a. Quality control b. Roof frame information should b made available in detailing phase Not answered Correct detailing Not answered ~=Ouu a. More control a. Communicate importance of sequenced material b. Create site specific plan showing crane access 0. Inspect site request as built survey (1. Inspect site and go over crane, truck and lift access e. Make sure all parties agree to direction before starting QUESTION 9 COMPANY Yes No No Yes Yes No Yes No No H—EO’TJMUOW> Yes 139 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 10 COMPANY 10 percent of the projects Not applicable Not applicable 25 percent of the projects 2 percent of the projects Not applicable 1 percent Not applicable Not applicable HHEOGHUGw> 1 percent QUESTION 11 COMPANY Not applicable (yes) Yes Yes Not applicable (yes) Not applicable (yes) Yes Not applicable (yes) No Yes “HEOMHUGW> Yes QUESTION 12 COMPANY No No Yes Yes No No No No No a—mo-umcnws- No 140 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 13 COMPANY a. Erecting directly from the truck is oflen not safe or economically feasible b. Loading members to a truck in reverse order of erection does not coordinate well with the fabrication process a. There will be more sorting at the fabricating plant b. Trucks might not get close enough to exact point of erection c. Cost of driver to wait for the entire truck to be erected a. Paying per diem charges on flat bed not expensive versus labor a. When you erecting on an express way with lane closures there is no room to unload. You must erect directly from the truck b. Time is saved if there is no unloading, specially when only a few beams are on the truck a. Unsafe for large loads b. More time spent loading materials in the exact sequence 0. Truck drivers would be delayed a. Cost for truckers waiting for steel to be erected b. Cost of erection crew waiting for delivery truck to arrive d. Some trucks would have to be shipped with less than firll loads, having to use more trucks to deliver steel a. Usually heavier pieces are loaded on the bottom of the truckload and they are erected first a. The fabricator would need many trucks and have them lined up on street a. Access for hooking up the pieces of steel b. Site access to move trucks around c. Dropping trailers d. Safety a. Fabricators cannot load 20 — 30 pieces of iron because they are all of different heights and lengths 141 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 14 COMPANY a. Any coordination mistake in loading could cause the entire truckload to be un-erectable b. It is unsafe to try to erect from the truck a. See 13 b. Safety of working on the ground when compared to on the truck c. The truckload might be unstable when erecting Not answered a. Fabricator loads beams to close together b. Load not balanced properly on a truck a. Finding piece marks b. Keeping pieces in sequence c. Safety concerns about load shifis a. Trucks have to remain idle when erection is lost due to weather conditions b. Sometimes erection order has to be varied to daily site conditions c. See 13 Not answered a. Pinch hazards for book on men b. Fall hazards for men working on truck See 13 a. Takes away all options and if pieces of steel are not fabricated appropriately or missing you have to stop completely 142 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 15 COMPANY a. Erecting from the truck is unsafe and should be done only under special circumstances a. Load less steel on each truck b. Use of more equipment such as man baskets 0. Different loading techniques a. Erector determines truck loading b. Less steel per truck a. Erector should give proper loading sequence to the fabricator b. Fabricator should ask for loading requirements Not answered a. Fabricator would have to be located close to the site for delivery of steel. This could be achieved using a marshalling yard Not answered Not answered a. Coordination of loading b. Having tractors available “It—:0 Not answered QUESTION 16 COMPANY a. Space with dunnage between each layer b. Members need to be oriented in their erected position on the truck a. First piece erected must be last piece loaded b. Leave space between pieces of steel a. In order of erection b. Steel needs to be spaced so chokers can be used U a. If four beams are on a truck, 1"t and 2"d pieces need to be placed on the outside of the trailer and the 3rd and 4th piece in the middle Not answered a. Exact I'CVCI'SC CI‘CCIIOD OI'dCI' Not answered Not answered H IOHH a. In sequence according to how it will be erected b. With space between pieces Gun a. Pieces needed first have to be on top b. Leave space between pieces for rigging 143 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 17 A 11111 11111 B Not answered C IIIII IIIII D IIIII IIIII E E 11111 g IIIII 2 8 F 11111 11111 G Not answered H 11111 11111 , IIIII IIIII J Not answered QUESTION 18 A By sequence B As returned from approval with some selection of like pieces if time permits C Not applicable E D Not applicable 9: E Not applicable 5 F Not applicable U G Not applicable H Not applicable I Not applicable J Not applicable 144 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 19 COMPANY Less than 50 percent 50 — 60 percent Not applicable Not applicable Not applicable Not applicable Not applicable ~ommcnw> Not applicable QUESTION 20 COMPANY By sequence and by truck load By truckload and according to how each piece will be erected Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable HHIQH'JHUO w > Not applicable QUESTION 21 COMPANY 20,000 square feet 40,000 square feet Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable HHIQQHUO¢> Not applicable 145 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 22 COMPANY Electric overhead traveling crane (10 ton capacity) 40 ton hydraulic crane and fork lift Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable a—mnmmcnwr» Not applicable QUESTION 23 COMPANY 2 man crew, shop employees 5 man crew: l crane operator, 2 crewmembers on the ground and 2 crewmembers on the truck Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable H—EO'TJHUO w > Not applicable QUESTION 24 COMPANY Material handling, unloading and sometimes painting Storage, loading, driver or as needed for fabrication Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable HmflfififiUOW> Not applicable 146 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 25 COMPANY 60 minutes 90 minutes Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable 3"“ l: Cl'fi EH €115 Ufli> Not applicable QUESTION 26 COMPANY 16tons 20 tons Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable h~=nmwcnw> Not applicable _ QUESLION 27 > ‘— Ill—El: El IIIII HHHHH Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable HHEO'fiHUO Not applicable 147 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 28 COMPANY Project manager Erection crew foreman and shipping and delivery foreman Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable Not applicable HHIQMHGO¢> Not applicable QUESTION 29 COMPANY 60 minutes 60 minutes 30 minutes 3O — 120 minutes 60 minutes 30 minutes 60 - 120 minutes Depends on crane size Not answered a—mnwmunwrv 45 minutes QUESTION 30 COMPANY During the bid and planning phase Before the erection process starts When steel arrives on site Before erection process starts Before erection process starts Before erection process starts Before erection process starts and when steel arrives on site Before erection process starts Not answered a—mnmwcnw> Before erection process starts 148 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 31 COMPANY Coordinated between the GC and the erector Erection superintendent and GC during pre-award and base on how the prgject was bid Erection foreman Erection foreman and project manager Erection foreman Combination of the above Erection foreman and GC’s project manager or superintendent Erection superintendent and GC’s superintendent Not answered Gut—I: C) 'I'JHUO a > Erection foreman and erector’s project manager QUESTION 32 COMPANY Over 40 pieces Over 40 pieces 30 — 40 pieces Not answered Over 40 pieces 3O — 40 pieces Over 40 pieces Over 40 pieces Over 40 pieces h~fl0mmunw> 3O —- 40 pieces and over 40 pieces QUESTION 33 COMPANY 5 man crew: 1 Foreman, 2 connectors, 2 book on 5 man crew: 1 Foreman, 2 connectors, 2 book on 5 man crew: l Foreman, 2 connectors, 2 book on 5 man crew: l Foreman, 2 connectors, 2 book on 5 man crew: l Foreman, 2 connectors, 2 hook on 5 man crew: 1 Foreman, 2 connectors, 2 book on 5 man crew: 1 Foreman, 2 connectors, 2 hook on 5 man crew: l Foreman, 2 connectors, 2 book on 5 man crew: 1 Foreman, 2 connectors, 2 book on HHEOQMUO¢> 5 man crew: 1 Foreman, 2 connectors, 2 book on 149 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 34 Union wages Union wages Union wages Union wages Union wages Union wages Union wages Union wages Union wages “HIOMMUGW> Union wages QUESTION 35 COMPANY 100 ton / 160’ lattice boom crane 80 ton hydraulic crane or 100 ton crawler crane 20 to 30 ton hydraulic crane Hydraulic truck crane 40 ton hydraulic crane Varies Crawlers and hydraulic Erection superintendent 50 ton hydraulic crane with 100 feet boom HH:O’#HUO§> Mobile crane QUESTION 36 COMPANY Coordinated with GC / Erector Erection superintendent and GC/CM during pre-award Erection foreman Erector Erection foreman Erection foreman Erection foreman Erection superintendent Foreman HHIOEMUGQ> Erection foreman 150 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 37 Bid / planning phase Prior to start of shop drawings On site, daily One month prior to erection On site as erection progresses Exact order of individual pieces just before erection COMPANY On site In detailing As the work goes on H~=01H60w> Onsite afier complete delivery is confirmed QUESTION 38 No Yes No Yes No Yes COMPANY No No No HHEQMHUOW> No QUESTION 39 No No No Yes if possible No Yes COMPANY No No Yes H~=nmwcnw> No 151 Table 16: Fabrication and Erection Companies Responses (Continuation) QUESTION 40 COMPANY No Yes No NO Yes but the choker might require repositioning Yes No No Yes HHIQQHUOW> Yes QUESTION 41 COMPANY More than 3 inches More than 3 inches More than 3 inches More than 3 inches More than 3 inches More than 3 inches More than 3 inches More than 3 inches More than 3 inches H-louseicnw> 2 — 3 inches 152 APPENDIX D 153 Table 18: Organized steel with 12 inches as nominal height (Truck A) MARK ORDER SEQ QTY SHAPE DESCRIPTION LENGTH AVG-WT TOT-WT 1101 1 1 1 w 12X50 33-11-3/4 1843 1843 901 2,3 1 2 w 12X50 3311-04 1864 3728 1102 4 1 1 w 12X50 3311-374 1843 1843 602 5,6 1 2 w 12X53 33-11-1/4 1966 3931 601 7 1 1 w 12X53 3311-174 1966 1966 301 8 1 1 w 12X65 45-7-1/4 3161 3161 302 9,10,11,12 1 4 w 12X58 45-7-1/4 2842 11368 401 13 1 1 w 12X58 45-7-1/4 2842 2842 701 14 1 1 w 12X53 3341-04 1968 1968 702 15 1 1 w 12X53 33-11-1/4 1968 1968 801 16 1 1 w 12X53 3311-174 1966 1966 NUMBER OF PIECES 16 WEIGHT (LBS) 36584 Table 19: Organized steel with 12 inches as nominal height (Truck B) MARK ORDER SEQ QTY SHAPElDESCRIPTIONlLENGTH AVG-WT TOT-WT 1201 1 2 1 w 12X50 33-11-1/4 1843 1843 1002 2 2 1 w 12X50 33-11-1/4 1864 1864 1001 3 2 1 w 12xs0 33-11-1/4 1864 1864 1202 4 2 1 w 12xso 33-11-1/4 1843 1843 602 5,6,7 2 3 w 12xs3 33-11-1/4 1966 5897 501 8 2 1 w 12X65 457-174 3161 3161 402 9 2 1 w 12X65 45-7-1/4 3161 3161 502 10 2 1 w 12X58 45-7-1/4 2842 2842 302 11 2 1 w 12X58 45-7-1/4 2842 2842 402 12 2 1 w 12X65 457-174 3161 3161 402 13 2 1 w 12X65 45-7-1/4 3161 3161 801 14,15,16 2 3 w 12xs3 33-11-1/4 1966 5897 NUMBER OF PIECES 16 WEIGHT (LBS) 37536 154 Table 20: Organized steel with 12 inches as nominal height (Truck C) MARK ORDER SEQ QTY SHAPElDESCRIPTION LENGTH AVG-WT TOT- 1103 1 5 1 W 12X50 22-7-1/2 1131 1131 9C2 2,3 5 2 W 12X50 22-7-1/2 1 132 2263 1104 4 5 1 W 12X50 22-7-1/2 1131 1131 604 5,6 5 2 W 12X53 22-7-1 I2 1 199 2398 6C3 7 5 1 W 12x53 22-7-1/2 1 199 1 199 1801 8 5 1 W 12x40 31 -7-1 /2 1275 1275 1601 9 5 1 W 12X40 31 -7-1 /2 1275 1275 1401 10 5 1 W 12X40 31-7-1/2 1274 1274 1501 1 1 5 1 W 12x40 31 -7-1/2 1274 1274 1701 12 5 1 W 12X40 31 -7-1 I2 1275 1275 1901 13 5 1 W 12x40 31 -7-1/2 1275 1275 7C3 14 5 1 W 12x53 22-7-1/2 1 199 1 199 704 15 5 1 W 12x53 22-7-1/2 1 199 1 199 802 16 5 1 W 12xs3 22-7-1/2 1 199 1 199 604 1 ,2,3 6 3 W 12x53 22-7-1/2 1 199 3597 1204 4 6 1 W 12X50 22-7-1/2 1131 1131 1003 5 6 1 W 12X50 22-7-1/2 1131 1131 1301 6 6 1 W 12X40 21-11-1/2 878 878 2001 7 6 1 W 12x40 31 -7-1/2 1274 1274 1602 8 6 1 W 12X40 31 -7-1/2 1275 1275 1701 9 6 1 W 12x40 31 -7-1/2 1275 1275 2101 10 6 1 W 12X40 31-7-1/2 1274 1274 1302 11 6 1 W 12X4O 21-11-1/2 878 878 1004 12 6 1 W 12X50 22-7-1/2 1131 1131 1203 13 6 1 W 12X50 22-7-1/2 1131 1131 802 14.15.16 6 3 W 12x53 22-7-1/2 1 199 3597 NUMBER OF PIECES 32 WEIGHT (LBS) 37939 155 Ems: 35:5: 8 8205 N. 55 38¢ .8,“ memo—:25 .8 wEBSQ A: PSmE 890:5 l/ @285 $3 @585 Nxm L €699 _. .3on EBBEW mo 32 some 359% can 05on 8 3255 on 6:8 wing? Sarnoaaax “mHOZ J E SZ’OS —- BEE ml |||L 83m 095 55:00 LA 156 Table 21: Organized steel with 21 inches as nominal height (Truck D) MARK ORDER SEQ QTY SHAPE DESCRIPTION LENGTH AVG-WT TOT-WT 3881 1 1 1 W 21 X44 29-3- 1355 1355 3481 2 1 1 W 21X50 28-10-3/4 1510 1510 3882 3 1 1 W 21 X44 29-3- 1355 1 355 3482 15 1 1 W 21 X50 29-3- 1 509 1 509 3883 16 1 1 W 21 X44 28-10-3/4 1349 1349 3981 17 1 1 W 21X44 29—3 1351 1351 3482 37 1 1 W 21 X50 29-3- 1 509 1 509 3983 38 1 1 W 21 X44 28-1 0-3/4 1348 1 348 3982 39 1 1 W 21 X44 29-3 1351 1351 4081 1 2 1 W 21 X44 29-3- 1351 1351 3582 2 2 1 W 21x50 28-11 1521 1521 3982 3 2 1 W 21 X44 29-3 1351 1351 3383 4 2 1 W 21 X57 29-10-3/4 1782 1782 4582 9 2 1 W 21 X57 29-8-5/8 1 752 1 752 4081 30 2 1 W 21 X44 29-3- 1351 1351 3884 31 2 1 W 21 X44 28-1 1- 1336 1336 3982 32 2 1 W 21X44 29-3 1351 1351 4082 44 2 1 W 21 X44 29-3- 1355 1 355 4083 45 2 1 W 21 X44 28-10-3/4 1344 1344 4084 46 2 1 W 21 X44 29-3- 1 355 1 355 3782 58 2 1 W 21 X44 29-8-3/4 1 346 1 346 2681 63 2 1 W 21 X44 31 -3-5/1 6 1380 1380 4185 4 3 1 W 21X44 30-2-3/4 1668 1668 3882 5 3 1 W 21 X44 29-3 1 355 1355 3481 6 3 1 W 21X50 28-10-3/4 1511 1511 3881 7 3 1 W 21 X44 29-3 1355 1355 3784 8 3 1 W 21 X44 30-2-3/4 1668 1 668 NUMBER OF PIECES 27 WEIGHT (LBS) 38768 157 Table 22: Organized steel with 21 inches as nominal height (Truck E) MARK ORDER SEQ QTY SHAPE DESCRIPTION LENGTH AVG-WT TOT-WT 4181 32 3 1 W 21X44 29-10-3/4 1649 1649 3981 33 3 1 W 21 X44 29—3 1351 1351 4184 38 3 1 W 21X44 28-10-3/4 1349 1349 3581 51 3 1 W 21 X50 29-3 1 526 1526 3984 52 3 1 W 21 X44 29-1 0-3/4 1 653 1653 4181 56 3 1 W 21X44 29-10-3/4 1649 1649 3982 57 3 1 W 21 X44 29-3 1 351 1351 3983 62 3 1 W 21 X44 28-10-3/4 1349 1349 3581 71 3 1 W 21 X50 29-3 1 526 1526 4882 72 3 1 W 21 X83 29-1 0-5/8 2622 2622 41 85 79 3 1 W 21 X44 30-2-3/4 1 668 1668 3981 80 3 1 W 21 X44 29-3 1351 1351 3481 89 3 1 W 21X50 28-10-3/4 1511 1511 4284 98 3 1 W 21 X44 29-3 1351 1351 3784 99 3 1 W 21 X44 30—2-3/4 1 668 1668 3984 107 3 1 W 21 X44 29-10-3/4 1653 1653 3682 108 3 1 W 21 X50 29-3 1 537 1537 4282 1 09 3 1 W 21 X44 28-1 0-3/4 1 349 1 349 3981 110 3 1 W 21X44 29-3 1351 1351 4181 111 3 1 W 21X44 29-10-3/4 1649 1649 4181A 1 4 1 W 21 X44 28-10-3/4 1599 1599 3982A 2 4 1 W 21 X44 29-3- 1341 1341 3383A 3 4 1 W 21 X57 29-1 0-3/4 1 775 1775 3681 7 4 1 W 21X50 28-11- 1521 1521 4582A 9 4 1 W 21 X57 29-8-5/8 1 738 1738 4081A 20 4 1 W 21 X44 29—3- 1341 1341 4182 21 4 1 W 21 X44 29—10-3/4 1649 1649 NUMBER OF PIECES 27 WEIGHT (LBS) 42077 158 Table 23: Organized steel with 21 inches as nominal height (Truck F) MARK ORDER SEQ QTY SHAPEIDESCRIPTIONlLENGTH AVG-WT TOT-WT 41 81 A 25 4 1 W 21 X44 28-10-3/4 1599 1599 3982A 26 4 1 W 21 X44 29-3- 1341 1341 3884A 31 4 1 W 21 X44 28—1 1- 1326 1326 41 81 A 36 4 1 W 21 X44 28-1 0-3/4 1 599 1 599 4183 37 4 1 W 21 X44 29-10-3/4 1649 1649 4181A 41 4 1 W 21 X44 28-10-3/4 1599 1599 4084A 42 4 1 W 21 X44 29-3- 1 345 1345 4083A 47 4 1 W 21 X44 28-10-3/4 1334 1334 4083A 52 4 1 W 21 X44 28—1 0-3/4 1 334 1 334 4183 53 4 1 W 21 X44 29-10-3/4 1649 1649 4283 57 4 1 W 21 X44 30-2-3/4 1 672 1 672 4684 69 4 1 W 21X44 30-1-1/2 1351 1351 2584A 72,73 4 2 W 21 X44 19-1-3/4 432 864 4281 75 4 1 W 21 X44 30-2-3/4 1672 1672 41 B 1 A 83 4 1 W 21 X44 28-10-3/4 1 599 1599 3982A 84 4 1 W 21 X44 29-3— 1341 1341 3383A 85 4 1 W 21 X57 29—10-3/4 1775 1775 3783 89 4 1 W 21X50 28-11- 1521 1521 4582A 91 4 1 W 21 X57 29-8—5/8 1 738 1738 4081A 103 4 1 W 21X44 29-3- 1341 1341 4182 104 4 1 W 21X44 29-10-3/4 1649 1649 4181A 108 4 1 W 21 X44 28-10-3/4 1599 1599 3982A 1 09 4 1 W 21 X44 29-3- 1 341 1 341 3884A 1 14 4 1 W 21 X44 28-1 1- 1326 1326 4081A 119 4 1 W 21X44 29-3- 1341 1341 41 B3 120 4 1 W 21 X44 29-10-3/4 1649 1649 NUMBER OF PIECES 27 WEIGHT (LBS) 38554 159 Table 24: Organized steel with 21 inches as nominal height (Truck G) MARK ORDER SEQ QTY SHAPEIDESCRIPTIONILENGTH AVG-WT TOT-WT 4131A 124 4 1 w 21X44 28-10-3/4 1599 1599 3931A 125 4 1 w 21X44 29-3- 1340 1340 4033A 130 4 1 w 21X44 28-10-3/4 1334 1334 4234A 135 4 1 w 21x44 298- 1340 1340 4133 136 4 1 w 21X44 29-10-3/4 1649 1649 4233 140 4 1 w 21X44 30-2-3/4 1672 1672 4634 152 4 1 w 21x44 30-1-1/2 1351 1351 2534A 154,155 4 2 w 21X44 19-1-3/4 432 864 4231 157 4 1 w 21X44 30-2-3/4 1672 1672 4135A 4 5 1 w 21X44 30-2-3/4 1662 1662 4332 5 5 1 w 21x44 293- 1351 1351 4332 23 5 1 w 21X44 29-3- 1351 1351 3734A 24 5 1 w 21X44 30-2-3/4 1662 1662 4131A 32 5 1 w 21X44 28-10-3/4 1599 1599 4332 33 5 1 w 21X44 29-3- 1351 1351 4331 38 5 1 w 21X44 28-11- 1350 1350 3433 48 5 1 w 21X50 29-3- 1537 1537 3934A 49 5 1 w 21X44 29.10-3/4 1643 1643 4131A 53 5 1 w 21X44 28-10-3/4 1599 1599 4332 54 5 1 w 21X44 29-3- 1351 1351 5631 68 5 1 w 21X50 29-3- 1537 1537 4631 69 5 1 w 21X50 29-8-5/8 1686 1686 6432 87 5 1 w 21 X57 28-1 1- 1743 1743 6331 116 5 1 w 21X68 28-11- 2069 2069 6532 120,121 5 2 w 21X44 29-8-3/16 1313 2625 NUMBER OF PIECES 27 WEIGHT (LBS) 38937 160 Table 25: Organized steel with 21 inches as nominal height (Truck H) MARK ORDER SEQ QTY SHAPEIDESCRIPTIONI LENGTH AVG-WT TOT-WT 6382 141 5 1 W 21 X68 28-1 1- 2071 2071 4382 2 6 1 W 21 X44 29-3— 1351 1351 3383A 3 6 1 W 21 X57 29-10-3/4 1775 1775 5682 7 6 1 W 21X50 28-11- 1521 1521 4582A 9 6 1 W 21 X57 29-8-5/8 1 737 1 737 4382 17 6 1 W 21 X44 29-3- 1351 1351 41 82 18 6 1 W 21 X44 29-10-3/4 1649 1649 41 81 A 22 6 1 W 21 X44 28-10-3/4 1599 1599 4382 23 6 1 W 21 X44 29-3— 1351 1351 5782 28 6 1 W 21 X44 28—1 1- 1336 1336 4382 33 6 1 W 21 X44 29-3- 1351 1351 41 83 34 6 1 W 21 X44 29-10—3/4 1649 1649 4181A 38 6 1 W 21 X44 28-10-3/4 1599 1599 4382 39 6 1 W 21 X44 29-3- 1351 1351 5783 44 6 1 W 21X44 28-11- 1345 1345 4183 50 6 1 W 21 X44 29-10-3/4 1649 1649 4283 54 6 1 W 21 X44 30-2-3/4 1672 1 672 2585 56 6 1 W 21 X44 29-8-3/4 1349 1 349 4684A 66 6 1 W 21 X44 30-1-1/2 1351 1351 4281 72 6 1 W 21 X44 30-2-3/4 1672 1 672 6481 87 6 1 W 21 X68 28-1 1- 2064 2064 6583 91 ,92 6 2 W 21 X44 28-8-3/16 1312 2624 6581 112 6 1 W 21 X50 28-11- 1489 1489 6585 1 16,1 17 6 2 W 21 X44 29-9—1/4 1332 2663 NUMBER OF PIECES 26 WEIGHT (LBS) 39569 161 9238a 88 Ems: 35:8: 8 8:2: 5 5:5 63m 38 .832on we wars—ED ; fl 233m .303. 3:50:33 mo 32 some ouzfifim can 288 8 80285 on $3: wEmEm—o Bargain: ”mHOZ com 5:9? 162 Table 26: Organized steel with 16 inches as nominal height (Truck 1) MARK ORDER SEQ QTY SHAPEIDESCRIPTIONILENGTH AVG-WT TOT-WT 4482 4 1 1 W 1 6X26 28—1 0-3/4 799 799 2281 5,6,7 1 3 W 16X26 31-3-5/16 815 2446 4482 8 1 1 W 1 6X26 28-1 0-3/4 799 799 4581 9 1 1 W 16X26 31-3-5/16 816 816 2282 10,11 1 2 W 16X26 31-3-5/16 815 1630 2281 12.13.14 1 3 W 16X26 31-3-5/16 815 2446 2284 19,20,21 1 3 W 16X26 29-8-5/8 777 2331 4481 22 1 1 W 1 6X26 28-1 0-3/4 803 803 2383 27 1 1 W 1 6X26 23-2-3/4 632 632 2285 34 ,35,36 1 3 W 16X26 29—8—5/8 777 2331 4484 40 1 1 W 1 6X26 28-1 0-3/4 802 802 2381 41 ,42,43 1 3 W 1 6X26 29-8-5/8 777 2330 4481 44 1 1 W 1 6X26 28-1 0-3/4 803 803 2382 45 1 1 W 16X26 29—8-5/8 778 778 2384 46 1 1 W 1 6X26 29-8-5/8 778 778 2286 51 ,52,53 1 3 W 16X26 29—8-5/8 777 2330 2381 5,6,7 2 3 W 16X26 29-8-5/8 777 2330 4481 8 2 1 W 1 6X26 29-1 0-3/4 803 803 2385 27.28.29 2 3 W 16X26 29-8-5/8 777 2330 4485 33 2 1 W 1 6X26 29-1 0-3/4 803 803 2381 34,35,36 2 3 W 16X26 29-8—5/8 777 2330 4481 37 2 1 W 1 6X26 29-1 0-3/4 803 803 2386 38,39,40 2 3 W 1 6X26 29-8—5/8 777 2331 2381 41 ,42,43 2 3 W 16X26 29—8-5/8 777 2330 4484 47 2 1 W 1 6X26 29-1 0-3/4 802 802 4584 48,49 2 2 W 16X26 29-8-5/8 777 1554 NUMBER OF PIECES 50 WEIGHT (LBS) 39267 163 Table 27: Organized steel with 16 inches as nominal height (Truck J) MARK ORDER SEQ QTY SHAPEIDESCRIPTION LENGTH AVG-WT TOT-WT 4584 50 2 1 W 16X26 29-8-5/8 777 777 4481 51 2 1 W 1 6X26 29-10-3/4 803 803 4584 52 2 1 W 1 6X26 29-8-5/8 777 777 2381 53,54 2 2 W 16X26 29-8-5/8 777 1553 4584 55.56.57 2 3 W 16X26 29-8-5/8 777 2331 2283 59.60.61 2 3 W 16X26 31 -3-5/16 815 2446 4483 62 2 1 W 1 6X26 29-8-3/4 801 801 2781 64 2 1 W 16X26 22-7-1/2 616 616 2283 67.68.69 2 3 W 16X26 31 -3-5/16 815 2446 2883 9.10.11 3 3 W 16X26 30-1-9/16 805 2415 4486 12 3 1 W 1 6X26 29-8-3/4 799 799 2885 1 3 3 1 W 16X26 30-1-9/16 806 806 2884 14,15 3 2 W 16X26 30-1-9/16 805 1610 4486 16 3 1 W 1 6X26 29-8-3/4 799 799 2883 17.18.19 3 3 W 16X26 30—1-9/16 805 2415 2284 35.36.37 3 3 W 16X26 29-8-5/8 777 2331 4481 39 3 1 W 1 6X26 29—10-3/4 803 803 2987 44 3 1 W 16X26 23-2-3/4 632 632 2285 53.54.55 3 3 W 16X26 29-8-5/8 777 2331 4481 58 3 1 W 1 6X26 29—10-3/4 803 803 2381 59.60.61 3 3 W 16X26 29-8-5/8 777 2331 4481 63 3 1 W 16X26 29-10—3/4 803 803 2382 64 3 1 W 1 6X26 29-8-5/8 778 778 2384 65 3 1 W 16X26 29-8-5/8 778 778 4981 73 3 1 W 16X26 29-8—5/8 792 792 2286 74,75 3 2 W 16X26 29-8-5/8 777 1554 4486 81 3 1 W 1 6X26 29-8—3/4 799 799 2883 82.83.84 3 3 W 16X26 30—1-9/16 805 2415 4486 90 3 1 W 1 6X26 29-8-3/4 799 799 NUMBER OF PIECES 50 WEIGHT (LBS) 39342 164 Table 28: Organized steel with 16 inches as nominal height (Truck K) MARK ORDER SEQ QTY SHAPEIDESCRIPTIONILENGTH AVG-WT TOT-WT 2885 91 3 1 W 16X26 30-1-9/16 806 806 2884 92.93 3 2 W 16X26 30-1-9/16 805 1610 2883 1 00 3 1 W 16X26 30-1-9/16 805 805 2381 1 13.1 14.1 15 3 3 W 16X26 29-8-5/8 777 2331 4481 1 16 3 1 W 1 6X26 29-1 0-3/4 803 803 31 83 1 21 3 1 W 16X26 23—2-3/4 632 632 31 82 1 27a 3 1 W 1 6X26 29-8-5/8 777 777 4481 1 33 3 1 W 1 6X26 29-1 0-3/4 803 803 2381 134,135,136 3 3 W 16X26 29-8-5/8 777 2331 4481 1 37 3 1 W 1 6X26 29-1 0-3/4 803 803 2382 1 38 3 1 W 16X26 29-8-5/8 778 778 4982 144 3 1 W 1 6X26 29-8—5/8 786 786 2286 145,146 3 2 W 1 6X26 29-8-5/8 777 1 554 2381 A 4.5.6 4 3 W 16X26 29-8-5/8 773 2319 4481A 8 4 1 W 16X26 29-10-3/4 798 798 2385A 22.23.24 4 3 W 16X26 29-8-5/8 773 2319 4481 A 27 4 1 W 1 6X26 29-10—3/4 798 798 2381A 28.29.30 4 3 W 16X26 29-8-5/8 773 2319 4481A 32 4 1 W 16X26 29-10-3/4 798 798 238 1 A 38.39.40 4 3 W 16X26 29—8-5/8 773 2319 4484A 43 4 1 W 1 6X26 29-1 0-3/4 798 798 4584A 44.45.46 4 3 W 1 6X26 29-8-5/8 773 2319 4481 A 48 4 1 W 1 6X26 29-1 0-3/4 798 798 4584A 49 4 1 W 16X26 29-8-5/8 773 773 2381A 50,51 4 2 W 16X26 29-8-5/8 773 1 546 4584A 54.55.56 4 3 W 16X26 29-8-5/8 773 2319 2585 59 4 1 W 16X26 29-8-3/4 1 349 1 349 3181 60,61 .62 4 3 W 16X26 30-1-1/2 805 2415 4487 68 4 1 W 16X26 29-8-3/4 807 807 NUMBER OF PIECES 50 WEIGHT (LBS) 39613 165 Table 29: Organized steel with 16 inches as nominal height (Truck L) MARK ORDER SEQ QTY SHAPEIDESCRIPTIONI LENGTH AVG-WT TOT-WT 31 B1 76 4 1 W 16X26 30-1-1/2 805 805 3181 79,80 4 2 W 16X26 30-1-1/2 805 1610 2381 A 86.87.88 4 3 W 16X26 29-8-5/8 773 2319 4481 A 90 4 1 W 16X26 29-1 0—3/4 798 798 2385A 105,106,107 4 3 W 16X26 29-8-5/8 773 2319 4481 A 1 10 4 1 W 16X26 29-1 0-3/4 798 798 2381A 111,112,113 4 3 W 16X26 29-8-5/8 773 2319 44B 1 A 1 1 5 4 1 W 1 6X26 29-1 0-3/4 798 798 2381A 121,122,123 4 3 W 16X26 29-8-5/8 773 2319 4484A 1 26 4 1 W 1 6X26 29-1 0-3/4 798 798 238 1 A 127,128,129 4 3 W 16X26 29-8-5/8 773 1546 4481 A 1 31 4 1 W 1 6X26 29-1 0-3/4 798 798 4584A 132 4 1 W 16X26 29-8-5/8 773 773 2381A 133.134 4 2 W 16X26 29-8-5/8 773 1546 2381 A 137,138,139 4 3 W 16X26 29-8-5/8 773 2319 2385A 142 4 1 W 1 6X26 29-8-5/8 773 773 3181 143,144,145 4 3 W 16X26 30-1-1/2 805 2415 4487 1 51 4 1 W 1 6X26 29-8-3/4 807 807 3181 158,159,160 4 3 W 16X26 30-1-1/2 805 2415 4486A 6 5 1 W 16X26 29-8-3/4 799 799 2883A 7.8.9 5 3 W 16X26 30-1-9/16 799 2397 4486A 1 5 5 1 W 1 6X26 29-8—3/4 799 799 2885A 1 6 5 1 W 1 6X26 30-1 -9/ 1 6 799 799 2884A 17.18 5 2 W 16X26 30-1-9/16 800 1599 2883A 2526.27.28.29 5 5 W 16X26 30-1-9/16 799 3995 NUMBER OF PIECES 50 WEIGHT (LBS) 38663 166 Table 30: Organized steel with 16 inches as nominal height (Truck M) MARK ORDER SEQ QTY SHAPEIDESCRIPTION LENGTH AVG-WT TOT-WT 2883A 30 5 1 W 16X26 30-1-9/16 799 799 2381 A 35.36.37 5 3 W 16X26 29-8—5/8 773 2319 4481 A 39 5 1 W 1 6X26 29-1 0-3/4 798 798 4682 44 5 1 W 16X26 23-2-3/4 632 632 31 82A 50.51 .52 5 3 W 16X26 29-8—5/8 773 2318 4481 A 55 5 1 W 16X26 29-1 0-3/4 798 798 238 1 A 56.57.58 5 3 W 16X26 29-8-5/8 773 2319 4481 A 60 5 1 W 16X26 29-1 0-3/4 798 798 2382A 61 5 1 W 16X26 29-8-5/8 773 773 2384A 62 5 1 W 16X26 29-8-5/8 773 773 2286A 70.71 ,72 5 3 W 16X26 29-8-5/8 773 2318 7081 82 5 1 W 16X26 30-1-5/8 805 805 6984 1 00 5 1 W 1 6X26 30-1 -5/8 805 805 5387 1 1 5 5 1 W 1 6X26 29-8-3/4 777 777 5483 130 5 1 W 16X26 29-8-3/4 777 777 5388 137 5 1 W 16X26 29-8-3/4 777 777 4481 A 1 6 1 W 16X26 29-1 0-3/4 798 798 2381 A 4.5.6 6 3 W 16X26 29-8-5/8 773 2319 4481 A 8 6 1 W 16X26 29-1 0-3/4 798 798 2385A 19.20.21 6 3 W 16X26 29-8-5/8 773 2318 4481A 24 6 1 W 16X26 29-10-3/4 798 798 2381A 25.26.27 6 3 W 16X26 29-8-5/8 773 2319 NUMBER OF PIECES 36 WEIGHT (LBS) 27936 167 Table 31: Organized steel with 16 inches as nominal height (Truck N) MARK ORDER SEQ QTY SHAPE IDESCRIPTION] LENGTH AVG-WT TOT-WT 4481 A 29 6 1 W 1 6X26 29-1 0-3/4 798 798 2386A 30,31 .32 6 3 W 16X26 29-8-5/8 773 2318 2381 A 35.36.37 6 3 W 16X26 29-8-5/8 773 2319 4484A ' 40 6 1 W 1 6X26 29—1 0-3/4 798 798 2381A 41 ,42,43 6 3 W 16X26 29-8-5/8 773 2319 4481 A 45 6 1 W 16X26 29-1 0-3/4 798 798 238 1 A 46.47 6 2 W 16X26 29-8-5/8 773 1546 4584A 48 6 1 W 1 6X26 29—8-5/8 773 773 2381 A 51 ,52,53 6 3 W 16X26 29—8-5/8 773 2319 3181 57.58.59 6 3 W 16X26 30-1-1/2 805 2415 4487 65 6 1 W 1 6X26 29-8-3/4 807 807 2781A 67 6 1 W 16X26 22-7-1/2 609 609 3181 73.74.75 6 3 W 16X26 30-1-1/2 805 2415 5389 83 6 1 W 1 6X26 29-8-3/4 777 777 5485 1 01 6 1 W 1 6X26 29—8-3/4 777 777 5481 108 6 1 W 16X26 29-8-3/4 777 777 5486 123 6 1 W 1 6X26 29-8-3/4 777 777 5387 1 30 6 1 W 1 6X26 29-8-3/4 777 777 5483 142 6 1 W 16X26 29-8-3/4 777 777 7082 1 70 6 1 W 1 6X26 30-1-3/4 805 805 NUMBER OF PIECES 33 WEIGHT (LBS) 25701 168 Ems: =2:an 33 85E 2 5:3 603 3.“ 398325 .3 wEBSQ ”Q 8&5 .363 530:3 mo 32 some 3:533 can 833 2 82>th on 3:8 means—o 03338395. $0.02 8m 6:33 333.85 as l/ OL'66 '—°‘ i. -ll- ,1 I. .1! i. L 169 Table 32: Organized steel with 18 inches as nominal height (Truck 0) MARK ORDER SEQ QTY SHAPE DESCRIPTION LENGTH AVG-WT TOT-WT 4383 18 1 1 W 18X4O 28-10-3/4 1221 1221 2783 23 1 1 W 18X40 29-8-5/8 1200 1200 2881 47 1 1 W 18X55 29-8-5/ 8 1 794 1794 4383 34 3 1 W 1 8X40 29-1 0-3/4 1222 1222 2783 40 3 1 W 18X40 29-8-5/ 8 1200 1 200 2881 66 3 1 W 1 8X55 29—8-5/8 1 795 1 795 4383 1 1 2 3 1 W 18X40 29-1 0-3/4 1222 1222 2783 1 1 7 3 1 W 18X40 29-8-5/8 1200 1200 3184 128 3 1 W 18X55 29-8-5/8 1847 1847 2881 139 3 1 W 18X55 29-8-5/8 1 795 1795 4383A 34 5 1 W 18X4O 29-10-3/4 1216 1216 2783A 40 5 1 W 18X40 29-8-5/8 1 1 89 1 189 2881A 63 5 1 W 18X55 29-8-5/8 1781 1781 6682 77 5 1 W 18X35 29-2-1/2 1066 1 066 6684 98 5 1 W 1 8X35 29-2-1/2 1066 1 066 6784 1 1 0 5 1 W 18X35 29-2-3/4 1071 1071 6783 1 28 5 1 W 1 8X35 29—2-3/4 1080 1 080 6881 135 5 1 W 18X35 29-3- 1072 1072 6681 144 5 1 W 18x40 29-8-5/16 1 194 1 194 6683 145 5 1 W 18X40 29-8-5/16 1 193 1 193 6882 81 6 1 W 18X35 29-2-3/4 1071 1071 6781 99 6 1 W 1 8X35 29-2-3/4 1071 1071 6884 106 6 1 W 18X35 29-2-1/2 1070 1070 6883 121 6 1 W 18X35 29-2-1/2 1070 1 070 6983 1 28 6 1 W 1 8X35 29-2-3/4 1067 1067 6982 134 6 1 W 18X35 28-1 1- 1045 1045 6981 140 6 1 W 1 8X35 29-2-3/4 1 067 1 067 NUMBER OF PIECES 27 WEIGHT (LBS) 33884 170 Ems: 3888 mm 3658 M2 at? $63 38 88328 mo @83me “E 8&5 .333 88083 mo 33 some 3:533 can 233 8 @0288 com 528,—. on 3:8 $88830 033983.34 ”mHOZ 335.85 as l 1 171 Table 33: Organized steel with 19 inches as nominal height (Truck P) MARK ORDER SEQ QTY SHAPEIDESCRIPTION LENGTH AVG-WT TOT- 2582 24 1 1 W 14x22 23—2-3/4 539 539 2583 48 1 1 W 14x22 13-0-1/4 315 315 2583 50 1 1 W 14x22 13-0-1/4 315 315 2684 10 2 1 W 14X22 23-6-3/4 636 636 2782 13 2 1 W 14x22 23-6-3/4 639 639 2584 65,66 2 2 W 14X22 19-1-3/4 440 880 2582 41 3 1 W 14x22 23-2-3/4 539 539 2583 67 3 1 W 14X22 13-0-1/4 315 315 2583 69 3 1 W 14X22 13-0-1/4 315 315 2582 1 18 3 1 W 14x22 23-2-3/4 539 539 2583 140 3 1 W 14x22 13-0-1/4 315 315 2583 142 3 1 W 14x22 13-0-1/4 315 315 3081 10 4 1 W 14x22 23-6-3/4 619 619 3082 13 4 1 W 14x22 23-6-3/4 619 619 2386A 33.34.35 4 3 W 14X22 29-8-5/8 773 2319 3081 92 4 1 W 14x22 23-6-3/4 619 619 31 85 96 4 1 W 14X22 23-6-3/4 619 619 2386A 116,117,118 4 3 W 14x22 29-8—5/8 773 2319 2582A 41 5 1 W 14x22 23-2-3/4 531 531 2583A 64 5 1 W 14X22 1 3-0-1/4 307 307 2583A 66 5 1 W 14x22 1 3-0-1/4 307 307 71 85 78 5 1 W 14x22 29-8-1/2 682 682 71 86 79 5 1 W 14X22 30-2-1/4 698 698 7281 80 5 1 W 14x22 30-2-1/4 698 698 7282 81 5 1 W 14x22 30-2-1/4 698 698 71 84 88 5 1 W 14X22 29-8-1/2 682 682 7084 89.90.91 .92 5 4 W 14x22 30-1-5/16 684 2736 71 B1 101 5 1 W 14x22 30-2-1/2 698 698 71 82 1 02 5 1 W 14X22 30-2-1/4 698 698 71 83 103 5 1 W 14X22 30-2-1/4 698 698 7085 1 1 1 5 1 W 14X22 29-10-1/2 678 678 7085 1 17 5 1 W 14X22 29-10-1/2 678 678 5582 1 18,1 19 5 2 W 14X22 29-8—7/1 6 658 1315 7283 122 5 1 W 14X22 1 1 -3-1l4 282 282 7284 123 5 1 W 14X22 1 1-3-1/4 276 276 NUMBER OF PIECES 44 WEIGHT (LBS) 25437 172 Table 34: Organized steel with 14 inches as nominal height (Truck Q) MARK ORDER SEQ QTY SHAPE IDESC RIPTION LENGTH AVG-WT TOT-WT 7085 136 5 1 W 14x22 29-10-1/2 678 678 7085 142 5 1 W 14X22 29-10-1/2 678 678 5583 143 5 1 W 14x22 29-8-7/16 657 657 7681 146 5 1 W 14x22 15-11-1/2 391 391 2684A 1 0 6 1 W 14X22 23-6-3/4 562 562 4683A 1 3 6 1 W 14X22 23—6-3/4 639 639 2584A 68,69 6 2 W 14X22 19-1-3/4 432 863 7086 82 6 1 W 14X22 29-1 0-1/2 678 678 7086 88 6 1 W 14x22 29-1 0-1/2 678 678 5584 89,90 6 2 W 14X22 29-8-7/16 658 1315 7283 93 6 1 W 14x22 1 1 -3-1/4 282 282 7284 94 6 1 W 14X22 1 1 -3-1/4 276 276 7086 107 6 1 W 14X22 29-10-1/2 678 678 7086 1 13 6 1 W 14x22 29-10-1/2 678 678 5585 1 14,1 15 6 2 W 14X22 29-9—1/2 672 1344 7283 1 18 6 1 W 14x22 1 1 -3-1/4 282 282 7085 129 6 1 W 14X22 29-10-1/2 678 678 7085 135 6 1 W 14x22 29-10-1/2 678 678 7382 148 6 1 W 14x22 29-8-1/2 685 685 7384 149 6 1 W 14x22 30-2-1/2 698 698 7386 1 51 6 1 W 14x22 30-2-1/2 698 698 7383 160.161 .162 6 3 W 14x22 30-2-1/4 698 2094 7381 1 73 6 1 W 14x22 30-2-1/2 698 698 NUMBER OF PIECES 28 WEIGHT (LBS) 16908 173 com 8:“; 33:85 as Ems: 3882: mm 8:08 3 8:5 663 8: 32:8,: .5 wEBSQ ”3 2:9,: :33 38383 .5 use: :30 3:533 88 2:03 9 @6288 0: 3:8 88826 288089: HmHOZ L OZ'ZL 174 Table 35: Organized steel with 10 inches as nominal height (Truck R) MARK ORDER SEQ QTY SHAPEIDESCRIPTION LENGTH AVG-WT TOT-WT 2481 25,26 1 2 W 1 0X1 2 3-3-3/4 50 100 2482 28.29.30 1 3 W 10X12 15-3-11/16 194 582 2483 49 1 1 W 10X12 1-5-3/4 28 28 2484 54 1 1 W 10X12 3-1-11/16 48 48 2485 11.12 2 2 W 10X12 9—5-7/1 6 116 232 2487 14 2 1 W 10x12 10-5-3/8 128 128 2581 15 2 1 W 10X12 10-5-3/8 141 141 2488 18 2 1 W 10x12 10-5-3/8 141 141 2487 21 2 1 W 10X12 10-5-3/8 128 128 2486 24.25.26 2 3 W 10X12 9-3-5/16 1 14 342 2981 20 3 1 W 10X12 7-4-3/4 99 99 2983 21 .22 .23 3 3 W 10X12 7-3-3/4 90 270 2982 24.25.26.27 3 4 W 10X12 7-2-3/4 89 356 2983 28.29.30 3 3 W 10X12 7-3-3/4 90 270 2984 31 3 1 W 10x12 7-4-11/16 99 99 2481 42 .43 3 2 W 1 0X1 2 3-3-3/4 50 1 00 2482 45.46.47 3 3 W 10X12 15-3—1 1/16 194 582 2483 68 3 1 W 10X1 2 1-5-3/4 28 28 2484 70 3 1 W 10X12 3-1-11/16 48 48 2981 85 3 1 W 10X12 7-4-3/4 99 99 2983 86.87.88 3 3 W 10X12 7-3-3/4 90 270 2982 94.95.96.97 3 4 W 10X12 7-2-3/4 89 356 2983 103,104,105 3 3 W 10X12 7-3—3/4 90 270 2984 106 3 1 W 10x12 7-4-11/16 99 99 2481 1 19.120 3 2 W 10X12 3-3-3/4 50 100 2482 122,123,124 3 3 W 10X12 15-3-11/16 194 582 2483 141 3 1 W 10X12 1-5—3/4 28 28 2484 143 3 1 W 10X12 3-1-11/16 48 48 2988 11.12 4 2 W 10X12 9-6—1/2 125 250 2989 14.15.16 4 3 W 10X12 9-4-5/16 123 369 2981A 63 4 1 W 10X12 7-4-3/4 109 109 2983A 64,65 4 2 W 1OX12 7-3-3/4 88 176 2985 66 4 1 W 10X12 7-3-1 1/16 90 90 2986 70 4 1 W 10X12 6-11-13/16 87 87 2781A 71 4 1 W 10x12 22-7-1/2 609 609 2984A 77 4 1 W 10X12 7-4-1 1/16 '96 96 2983A 78 4 1 W 10x12 7-3-3/4 88 88 2983A 81 .82 4 2 W 10X12 7-3-3/4 88 176 2988 93.94 4 2 W 10x12 9-6-1/2 125 250 2989 97.98.99 4 3 W 10X12 9-4-5/16 123 369 175 Table 35: Organized steel with 10 inches as nominal height (Truck R) (Continuation) MARK ORDER SEQ QTY SHAPE DESCRIPTION LENGTH AVG-WT TOT-WT 2985 146 4 1 W 10X12 7-3-11/16 90 90 2983A 147.148 4 2 W 10X12 7-3-3/4 88 176 2981A 149 4 1 W 10X12 7-4-3/4 109 109 2781 A 153 4 1 W 10X12 22-7-1/2 609 609 2983A 161 ,162,163 4 3 W 10X12 7-3-3/4 88 264 2984A 164 4 1 W 10X12 7-4-11/16 96 96 2981A 10 5 1 W 10X12 7—4-3/4 109 109 2983A 1 1 .12.13 5 3 W 10X12 7-3-3/4 88 264 2982A 19.20.21 .22 5 4 W 10X12 7-2-3/4 87 347 2984A 31 5 1 W 10X12 7-4-11/16 95 95 2481 A 42.43 5 2 W 10X12 3-3-3/4 47 93 2482A 45.46.47 5 3 W 10X12 15-3-11/16 190 571 2483A 65 5 1 W 1 0X1 2 1-5-3/4 24 24 2484A 67 5 1 W 10X12 3-1-11/16 44 44 5381 83 5 1 W 1 0X1 2 5-9-3/4 80 80 5382 84 5 1 W 10X12 5-9—3/4 72 72 5383 85.86 5 2 W 1 0X1 2 5-9-3/4 72 144 5384 93.94,95.96.97 5 5 W 10X12 5-8-3/4 71 357 5383 104,105,106 5 3 W 10X12 59—3/4 72 216 5385 1 07 5 1 W 1 0X1 2 5-9-3/4 72 72 5386 108 5 1 W 10X12 5-9-11/16 80 80 7487 125 5 1 W 10X12 7-1-15/16 90 90 7486 1 26 5 1 W 10X12 6-9-1/2 92 92 7581 127 5 1 W 10X12 10-11-7/16 142 142 7484 147 5 1 W 10X12 7-11-3/16 177 177 2485A 11,12 6 2 W 10X12 9-5-7/16 114 227 2486A 14.15.16 6 3 W 10X12 9-5-7/16 111 334 2981A 60 6 1 W 1 OX1 2 7-4-3/4 1 09 109 2983A 61 .62 6 2 W 1 0X1 2 7-3-3/4 88 176 2985 63 6 1 W 10X12 7-3-1 1/ 16 90 90 2986 70 6 1 W 10X12 6-11-13/16 86 86 2984A 76 6 1 W 10x12 7-4-1 1/16 95 95 2983A 77.78.79 6 3 W 10X12 7-3-3/4 88 264 7485 96 6 1 W 10x12 13-3—1/2 162 162 7486 97 6 1 W 10X12 6-9-1/2 92 92 7583 98 6 1 W 1OX12 4-10-1/8 69 69 7584 119 6 1 W 10X12 14-1-3/16 172 172 176 Table 35: Organized steel with 10 inches as nominal height (Truck R) (Continuation) [MARK ORDER SEQ QTY SHAPE DESCRIPTION LENGTH AVG-WT TOT-WT 7585 120 6 1 W 10X12 15-5-1/2 191 191 5482 1 53 6 1 W 1 0X1 2 5-9-3/4 80 80 5384 163.164,165.166,167 6 5 W 10X12 5-9—3/4 71 357 5386 178 6 1 W 10X12 5-9—1 1/16 80 80 NUMBER OF PIECES 143 WEIGHT EBS) 15240 177 Ewfi: 3880: 33 8:08 2 5:5 .063 :5.“ 3030:: .5 wEBEQ “2 8&5 :33 8:383 .5 32 :30 3:533 93 8:83 8 8:58: 5 3:8 9.5820 63:38:15: umHOZ com 3:351 3:532: $8 _ /. I L8'OS ‘ 178 Table 36: Organized steel with 24 inches as nominal height (Truck S) MARK ORDER SEQ QTY SHAPEIDESCRIPTIONILENGTH AVG-WT TOT-WT 3231 1 3 1 w 24X76 29-8-3/4 2625 2625 3232 2 3 1 w 24X76 29-10-3/4 2625 2625 3233 3 3 1 w 24X76 29-8-3/4 2631 2631 3231 76 3 1 w 24X76 29-8-3/4 2625 2625 3232 77 3 1 w 24X76 294034 2625 2625 3233 78 3 1 w 24X76 29-8-3/4 2631 2631 3331 58 4 1 w 24X76 29-8—3/4 2631 2631 3332 67 4 1 w 24X68 29-10-3/4 2385 2385 3234 74 4 1 w 24X76 29-8-3/4 2625 2625 3331 141 4 1 w 24x76 29-8-3/4 2631 2631 3332 150 4 1 w 24X68 29-10-3/4 2385 2385 3234 156 4 1 w 24X76 29-8-3/4 2625 2625 3231A 1 5 1 w 24X76 29-8-3/4 2616 2616 3232A 2 5 1 w 24X76 29-10-3/4 2615 2615 3233A 3 5 1 w 24X76 29-8-3/4 2616 2616 6031 73 5 1 w 24X68 29-8-3/4 2641 2641 6032 74 5 1 w 24X68 2910-314 2649 2649 NUMBER OF PIECES 17 TRUCK 44181 179 Table 37: Organized steel with 24 inches as nominal height (Truck T) MARK ORDER SEQ QTY SHAPE IDESCRIPTION LENGTH AVG-WT TOT-WT 6083 75 5 1 W 24X68 29-8-3/4 2644 2644 6182 76 5 1 W 24X55 30-2-3/4 2289 2289 6084 99 5 1 W 24X55 30-2-3/4 2289 2289 61 B4 1 09 5 1 W 24X55 29-1 0-3/4 2257 2257 6281 129 5 1 W 24X55 29-1 0-3/4 2261 2261 61 B4 134 5 1 W 24X55 29-10-3/4 2257 2257 3381 55 6 1 W 24X76 29-8-3/4 2631 2631 33 82 64 6 1 W 24X68 29-1 0-3/4 2385 2385 3284 71 6 1 W 24X76 29-8-3/4 2625 2625 61 84 80 6 1 W 24X55 29-1 0-3/4 2257 2257 6282 1 00 6 1 W 24X55 29-1 0-3/4 2257 2257 61 B4 1 05 6 1 W 24X55 29—1 0-3/4 2257 2257 6283 1 22 6 1 W 24X55 29-1 0-3/4 2257 2257 61 84 127 6 1 W 24X55 29-1 0-3/4 2257 2257 62 83 141 6 1 W 24X55 29-1 0-3/4 2257 2257 6383 146 6 1 W 24X55 30-2-3/4 2293 2293 6584 147 6 1 W 24X68 29-8-3/4 2655 2655 6284 1 69 6 1 W 24X55 30-2-3/4 2293 2293 NUMBER OF PIECES 18 TRUCK 42421 180 580: 3880: 3 30:08 em 8:: _003 .5: 83502.: 5 wEBEQ “m: 8&5 :003 8:00:03 5 :32 :30 3:503 :3 00:03 9 3:38: 0: 33:8 @5830 0033:0893 “HP—.02 com 00:89 II/ 4393,, .- HE; 58: H I :m- m: E "'— 00'98 ' 181 APPENDIX E 182 LEAN PRODUCTION: ASSEMBLY PLANT In mass production workers performed only simple tasks repetitively. The foreman was in charge of giving orders given by the industrial engineer that had the duty of improving the process. Housekeepers periodically cleaned the work area and repairmen were in charge of the maintenance. Inspectors checked for quality and large numbers of utility workers had to be on hand to cover for the high absenteeism rate that could not be prevented even with high wages. Managers were evaluated according to the number of cars produced and their quality. It was crucial to meet the production target. That is why the lines were almost never stopped unless absolutely necessary. Mistakes in the production line could be fixed at the end in the rework area. Ohno thought this system was full of muda, the Japanese word for waste. He believed that the only personnel adding value to the product were the assembly workers and they could do most of the work performed by the specialists even better. The first step he took was to group workers into teams with a team leader instead of a foreman. The team leader would coordinate the team and fill in for any absent worker. The team was given a set of assembly steps and they had to determine what was the best day to perform them. Then, Ohno assigned the team the job of housekeeping, minor repairs and check for quality. At last, the team had to give suggestions of how to improve the process in collaboration with industrial engineers. This was known as kaizen, a Japanese word for continuous incremental improvement, and was done periodically. Probably one of the biggest accomplishments of Ohno’s production line was the approach taken to prevent errors. In mass production the assembly line almost never stopped and mistakes grew even bigger as parts were added to the car in the line. The 183 problem was discovered and reworked at the end of the line. Since the line never stopped and problems were discovered near the end of the line a large number of vehicles had the same problem. The only person that could stop the line was the senior line manager. Ohno, on the other hand, placed a cord above every workstation so that workers could stop the line given any problem. Then the team got together to fix the problem before it advanced in the line. Production workers would then systematically trace the root cause of the problem using Ohno’s “five whys” (asking “why” for every layer of the problem in order to unveil the root cause by the fifth time) and solve the problem once and for all. At the beginning the line stopped all the time but as the workers gain experience and problems were completely removed the line started to run continuously almost 100 percent of the time. Toyota’s assembly plants have almost no rework or rework areas. Defects are also treated differently in each production system. In lean production the line stops when a defect is detected in order to find the root cause and fix it, while in mass production the defective products are repaired in a rework area near the end of the production line. Table 37 is a summary of lean assembly characteristics in contrast with the characteristics of mass assembly. The first characteristic is that instead a foreman giving orders to a group of workers a team leader directs the group and covers for any absent worker. In addition, lean assembly workers are given more duties than in mass production. Some of the duties include determining the best way of performing different assembly steps, specific tasks, minor repairs and quality checks. Another characteristic of lean assembly workers is that they have the responsibility of recommending improvements to the process, which is done on a periodic basis. Ohno thought that 184 workers knew better than management how the process works and gave them the responsibility of refining it. Defects are also treated differently in each production system. In lean production the line stops when a defect is detected in order to find the root cause and fix it, while in mass production the defective products are repaired in a rework area near the end of the production line. Table 38: Mass vs. Lean Assembly Plant characteristics (Information from Womack et al. 1990) CHARACTERISTIC N0. ELEMENT MASS PRODUCTION LEAN PRODUCTION 1 Direction Foreman Team leader Specific tasks, minor 2 Worker Dutles Specrfic tasks repairs, and quality check Improvement 3 Responsibility Management Worker teams 4 Worker Low High Empowerment 5 Defects Repair defective Remove root cause when products detected 185 LEAN PRODUCTION: SUPPLY CHAIN The assembly of the major components to produce a vehicle is the task of the final assembly plant, which constitutes about 15 percent of the total manufacturing process. Most of the work involves engineering and fabricating more than 10,000 parts that will be assembled into maybe 100 major components. Coordinating this process to have everything on time, at a low cost and with high quality is the challenging job of the final assembler. In mass production, the tendency was to integrate the complete production system into one bureaucratic command structure with orders coming from the top. At Ford and GM, engineers designed almost all the approximately 10,000 parts of the vehicle. Then they entered a bidding process with suppliers that could be part of the assembler or independent companies. Success for suppliers depended on price (lowest bid), quality (defective parts per 1,000) and delivery reliability. The assembler often switched between firms, it was considered to be a short-term relationship. Ohno and others observed many problems of this approach. Suppliers could not suggest improvements because they were already given the designed parts and did not have information on the vehicle. Competition limited communication between suppliers, especially information about advances in manufacturing techniques. Given the inflexibility of tools in the supplier plants and strict delivery schedules, the suppliers produce large number of parts that were warehoused. Defective parts were detected in the assembly plant. 186 To solve these problems Toyota started by organizing its suppliers into functional tiers. The first tier suppliers were involved in product development. The products developed had to work in harmony with other systems of the car. First tier suppliers were encouraged to share information. They did not compete because they were specialized in one type of component. Within first tier suppliers were second tier suppliers in charge of fabricating all the individual parts. First tier suppliers fabricated approximately 100 major components while second tier suppliers fabricated all the small parts that went into those components. Toyota’s first tier suppliers were independent companies. Toyota retained part of the equity of its first tier suppliers. In addition, first tier suppliers shared their equity between each other. Toyota shared personnel with its suppliers group to deal with workloads and would transfer senior managers not running for top management positions in Toyota to senior positions in the supplier firms. Supplier firms were also encouraged to perform outside work because it generated higher profit margins. Finally, Ohno created the famous just-in-time (JIT) system called kanban at Toyota. It was a way to coordinate the flow of parts within the supply system on a daily basis. Parts were only produced to supply the immediate demand of the next step. The fragility of the just-in-time system, considered by many to be a disadvantage because it could bring the whole system to a stop, was considered by Ohno to be a strength because in this way every member of the production system was forced to think proactively before the system came to a stop. 187 It took Eiji Toyoda and Ohno more than twenty years to fully implement these ideas within Toyota’s supply chain with excellent results in productivity, quality and responsiveness to changing market demands. Table 38 summarizes lean supply chain characteristics and contrasts them to mass supply chain characteristics. To begin, the first element describes how lean suppliers are given the responsibility of designing the parts while in mass production the assembler designs parts. Under the lean philosophy assemblers have a long-term relationship with suppliers and they both work as a team sharing information. Moreover, communication between suppliers is encouraged so that they help each other in the advancement of their processes. The last element in the table describes how the needs of the main customer determine the parts and finished products to be fabricated. Table 39: Mass vs. Lean Supply Chain characteristics (Information from Womack et al. 1990) CHARACTERISTIC No. ELEMENT MASS LEAN PRODUCTION PRODUCTION 1 Parts Design Assembler Supplier Assembler-Supplier 2 Relationship Short-term Long-term 3 Assembler-Supp her .HOId back Share information Communication information 4 Communication between Low High suppliers . Stock Satisfy Demand 5 Production 0f goods (Mass Production) (Just in Time) 188 LEAN PRODUCTION: CUSTOMER RELATIONSHIPS By the 19205 a system of dealers who maintained a large inventory of vehicles was in place. Each dealer was an independent company on itself. The assembler used the dealer to absorb the fluctuations in demand. The assembler-dealer relationship was that of mistrust in which the dealer holds back information about the product in order to maximize its bargaining position. After studying this process, the Toyota Motor Sales Company started building a network of distributors. Some of the were wholly owned and in some cases Toyota owned some equity. The idea was to develop a life long relationship between assembler, dealer and consumer by building the dealer into the production system. Gradually the dealer became the first step in the just-in-time system, sending orders of pre-sold vehicles that were manufactured and delivered in two to three weeks. The dealer had to work closely with the assembler to sequence the orders appropriately. Sales staff did not wait in the show room for potential buyers; instead, they approached the customer directly through phone calls. Toyota built an enormous database on households and their preferences. With this information Toyota could predict what type of car would the consumer want next as their income, family size, driving patterns and tastes changed. In this way the consumer was directly integrated in the production system and was considered in the development of new products. By the 19605 Toyota had fully worked out the principles of lean production and the other Japanese automakers adopted them as well. 189 THE LEAN PROJECT DELIVERY SYSTEM The Lean Construction Institute is developing the Lean Project Delivery System (LPDS) as a philosophy, a set of independent functions, rules for decision-making, procedures for execution of functions, and as implementation tools. According to LCI, it will be a holistic approach applied to the development of facilities, a new and better way to design and build capital facilities. The LPDS concept is explained by Ballard (2000a) and is the basis for this section. Design Criteria \ \7 Needs Design Product “d Concepts Design Values 7 Fab. and Testing Logistics and Turnover Project Lean Design Lean Supply Lean Assembly Work Flow Control PRODUCTION CONTROL Production Unit WORK STRUCTURING @cupancy EvaDA V Figure 17: Lean Project Delivery System (Ballard 2000a) 190 The LPDS model (figure 17) consists of four interconnecting phases: Project Definition, Lean Design, Lean Supply and Lean Assembly. Three modules form each phase. The project definition phase consists of the modules: needs and values determination, design criteria, and conceptual design. Lean design consists of conceptual design, process design and product design. Lean supply is made of the modules product design, detailed engineering and fabrication and logistics. Lean assembly consists of fabrication and logistics, site installation and testing and turnover. Production control extends throughout all project phases and consists of workflow control and production unit control. The work structuring module also extends throughout the duration of the project. There is also a post occupancy evaluation module that links the end of one project with the beginning of the next. In total LPDS is formed by 13 modules. Essential characteristics of the LPDS include: o The project is structured and managed as a value generating process 0 Downstream stakeholders are involved in front end planning and design through cross functional teams 0 Project control has the job of making sure work is executed as opposed to reliance on afier-the-fact variance detection 0 Optimization efforts are focused on making work flow reliable as opposed to improving productivity 0 Pull techniques are used to govern the flow of materials and information through networks of cooperating specialists 0 Capacity and inventory buffers are used to absorb variability 191 E- '1‘er {Ain‘t-G "D a'l..' 0 Feedback loops are incorporated at every level, dedicated to rapid system adjustment; i.e., learning. 192 THE LAST PLANNER SYSTEM OF PRODUCTION CONTROL There have been several lean construction methodologies developed to remove waste from the construction process. Probably one of the most important is the Last Planner System of Production Control by Ballard (2000b). Contrary to traditional project controls that focus in after the fact detection of variances, Last Planner focuses on causing activities conform to plans. It has the objective of improving work flow reliability. In other words it tries to improve how work is handed from one crew or trade to another. As a result the cost and duration of projects is reduced. The “last planner” is the person in charge of producing the assignments communicated to the construction crew. The assignments are the requirements to be performed by the crew. As explained by Ballard (2000), who developed it, the Last Planner is a mechanism for transforming what SHOULD be done into what CAN be done, therefore creating an inventory of ready work from which weekly work plans can be created. The SHOULD represents the originals plans for the project, the CAN is determined by the capacity of the crew and the WILL is the commitment made by the last planner to perform the job. The Last Planner System has two components: production unit control and work flow control. The goal of production unit control is to make progressively better assignments to direct workers through continuous learning and corrective action. To achieve this goal assignments should be well defined, in the right sequence, in the right amount, its prerequisites completed and the resources to perform it available. A production unit is a person or group of people performing the assignments. The standard to be controlled at the production unit level is Percentage Plan Complete (PPC). PPC can 193 be calculated by dividing the number of planned activities completed by the total number of planned activities. PPC measures how much of the work assigned by front line supervisors was realized. Then non-conformances are tracked to reveal root causes that are used for future improvements. Higher PPC results in higher productivity and progress. The goal of work flow control is to proactively cause work to flow across production units in the best possible sequence and rate. It advocates the use of a lookahead process that has the function of activity definition, constraint analysis, pulling work form upstream production units, and matching load and capacity. Figure 18 is a representation of the Last Planner System of production control. The SHOULD results from project plans. Then the last planner proactively removes the constraints for performing these plans. PPC can be calculated by dividing the WILL by the DID. The Last Planner is based on the principle that by improving work flow reliability the duration and cost of a project can be reduced as explained in the Parade Game (Tommelein et al. 1998). Previous implementations of the Last Planner reduced project duration by up to 55% and improved productivity by up to 37% (Kartam 1995). 194 Project Objectives Planning of Work Last Planner Process Resources Production Figure 18: The Last Planner System (Ballard, 2000b) 195 WORK STRUCTURING Another lean construction component is work structuring. Work structuring is developing a project’s process design and at the same time aligning engineering design, supply chain, resource allocation and assembly efforts (Howard and Ballard 1999). Ballard (1999) explains that work structuring has two goals: deliver value to the customer and make work flow reliable and quick. Work structuring involves answering the following questions (Tsao et a1. 2000): 1. In what chunks will work be assigned to specialists? 2. How will work chunks be sequenced? 3. How will work be released from one production unit to the next? 4. Will consecutive production units execute work in a continuous flow process or will their work be de-coupled? 5. Where will de-coupling buffers be needed and how should they be sized? 6. When will different chunks of work be done? A work chunk is a quantity of work that is passed through production units. When successive production units have different processing rates de—coupling buffers are placed between them so that work can be performed continuously. 196 1113111111111! 1293 1111111111