‘.. . — ~ . , . 1.! $025- 3... .6135: v: 3.5.1.... I... .113. Inwnesmre . 1v; . ....l. 14.“. .1 Huang...“ 2. sh _ . «u. . re. r 5-. ‘ 7.. . a ,t C. .33... ‘ 11.x): . x. .1?!” 52.5.5.2. .7 x... I}. 21.21%. : l I. . If...» 7.5:i13: ,I l I $35 - ..!ltvi, «r g z 2.... 2.4.2:..." ”.3: a J... #5»§..mbfl :. irfifithfifl 5.... a... n ... z: .. I u”. \«l 4“ ‘ V 0“. .. s '» . .H‘ : 5.4.2. .63: Pl. :5: a K 5'32... Jr}: 150L331 .32....m1 g ~pl~1.5.ri . V II War ‘N‘ui l V... 15.. a“ .3. .. . - sin, .. .iba, hi. .. 5.. 1m 5: 3. 3 a .. ...M...._H.«... ..h».nL¥an&.2 visa... V . .. ”5a » 5:13,. 3.9 vs It...» ‘ .t 8).. . .1 :v firlnhxfihhfllz hun‘Hw‘vzqu )1: 13.40.»... agsvwli>flur¢ . .. . ‘ TAh. . .. . .1 I??? z .1... ‘3’3‘, .113 Q's! (PIA l m 3 Dow This is to certify that the thesis entitled Productivity analysis of microtunneling pipe installation using simulation 2 y g g, presented by g i: 2 a o a 39.2 q a :3 Yu Luo 2 has been accepted towards fulfillment of the requirements for the MS. degree in Construction Management Pmram Major Professor’s Signag’dre L.» fll-fflfif L4]! 20;: 5 Date MSU is an Affirmative Action/Equal Opportunity Institution - —--_-—.—.-.—.—.—.—a-o--o-o—.—. PLACE IN RETURN Box to remove this checkout from your record. To AVOID FINES return on or before date due. MAY BE RECALLED with earlier due date if requested. DATE DUE DATE DUE DATE DUE NOV 0 7 2007 2/05 c:/ClRC/DateDue.lndd—p. 15 PRODUCTIVITY ANALYSIS OF MICROTUNNELING PIPE INSTALLATION USING SIMULATION By Yu Luo A THESIS Submitted to Michigan State University In partial fulfillment of the requirements for the degree of MASTER OF SCIENCE Construction Management Program 2005 ABSTRACT PRODUCTIVITY ANALYSIS OF MICROTUNNELING PIPE INSTALLATION USING SIMULATION By Yu Luo Microtunneling is a construction method in the family of trenchless technology, which is used to install underground utilities with minimum impacts on ground surface. Microtunneling is a complex operation that requires the integration of several systems, a variety of supporting equipments and experienced personnel, and is heavily influenced by subsurface conditions. The use of this technology is increasing as the underground infrastructures become more complicated and denser. As a result, the need to better understand the operations involved becomes crucial to improve planning, cost estimating, resource selection, and productivity. Simulation can be used to study microtunneling operations before they are actually performed, thereby identifying problems at the different stages of the project. Simulation can be used to aid in the decision-making process to control costs and shorten project duration. The objective of this research is to analyze and to evaluate the factors that affect the productivity in microtunneling operations. For this purpose, an actual microtunneling project was selected. Based on the data collected from the project, this research developed a CYCLic Operations NEtwork (CYCLONE) model with highlight on the impact of variations in soil compositions on the productivity of the operation. Simulations were repetitively conducted with different soil compositions. The results were used in a regression analysis to find a function of productivity and soil compositions. Various combinations of resource utilization were also simulated with the model to optimize the productivity. This Thesis Is Dedicated To My Wife Huixia For Her Love, Affection, And Encouragement To Successfully Complete The Graduate Study, And To My Parents For Their Encouragement And Continued Support Throughout My Entire Education iii ACKNOWLEDGEMENTS It is my pleasure to extend my appreciation to all those who helped me to accomplish this master thesis work. Gratitude must be personally extended to the following key individuals. Most importantly, I am greatly indebted to my advisor and mentor, Dr. Mohammad Najafi, P.E., Director, Center for Underground Infrastructure Research and Education (CUIRE), for his invaluable support, precious advice, and constant guidance as a mentor, major professor, and thesis committee member. I would also like to thank my committee members, Dr. Tariq Abdelhamid and Dr. Rigoberto Burguefio for their valuable suggestions. My sincere thanks to all the Board Members of Center for Underground Infrastructure Research and Education (CUIRE), Michigan State University, for all the support and help. I would like to thank Michigan Department of Transportation for funding my research. Especially thanks to Mr. Mark Dionise, MDOT real estate division manager. Mr. Mark Bruce, president of CanClay Corporation, and Mr. David Abbott, principal of Jason Consultants Group, deserved of a heartfelt appreciation for providing technical details. Thanks to my wife, Huixia (Judy) Wang, for her patience, and emotional support. I would like to thank all my friends for all their help, constant support, and encouragement. iv TABLE OF CONTENTS LIST OF TABLES- - - - - - VII LIST OF FIGURES - - - - -- IX 1 INTRODUCTION - -- - ...... -- - - - - - - - -- 1 1.1 OVERVIEW ........................................................................................................... l 1.2 PROBLEM AND NEED STATEMENT ........................................................................ 3 1.3 GOAL AND OBJECTIVES ....................................................................................... 4 1.4 METHODOLOGY .................................... 6 1.5 SCOPE AND LIMITATIONS OF THE THESIS ............................................................. 8 1.6 ORGANIZATION OF THE THESIS ............................................................................ 9 2 LITERATURES AND PROJECT REVIEW-- ............ - 10 2.1 MICROTUNNELING METHODS ............................................................................ 10 2.1.] Method Description .................................................................................. I 1 2.1.1.1 Slurry Microtunneling Boring Machine (MTBM) ................................ 12 2.1.1.2 J acklng System ...................................................................................... 15 2.1.1.3 Automated Spoil Transportation ........................................................... 17 2.1.1.4 Guidance and Remote Control System ................................................. 18 . 2.1.1.5 Active Direction Control ....................................................................... 22 2.2 JACKING PIPE MATERIALS USED IN MICROTUNNELING ..................................... 23 2. 2. 1 General Requirements .............................................................................. 23 2.2.2 Material Types .......................................................................................... 24 2.2.3 Material Selection ..................................................................................... 25 2.3 SOIL CONDITIONS .............................................................................................. 27 2.3.1 Soil Classifications .................................................................................... 27 2.3.2 Soil Classification Common Systems ........................................................ 28 2.3.3 The Unified Soil Classification (USC) System .......................................... 30 2.3.4 Soil Selection in the Candidate Project .................................................... 33 2.4 SIMULATION CANDIDATE PROJECT DESCRIPTION .............................................. 35 2.4.1 Project Location and Soil Profile ............................................................. 35 2.4.2 Jacking Forces .......................................................................................... 38 2.4.3 Microtunneling Pipes ................................................................................ 38 2.4.4 Microtunneling Equipment ....................................................................... 41 2.4.5 Other Equipments ..................................................................................... 43 2.4.6 Labor Crews .............................................................................................. 44 2. 4. 7 Project Site Layout .................................................................................... 45 2.5 CONSTRUCTION SIMULATION ............................................................................. 49 2.5.1 Computer Simulation Overview ................................................................ 49 2.5.2 Construction Simulation ........................................................................... 52 2.5.3 Simulation Modeling ................................................................................. 54 2.5.4 Tunneling and Microtunneling Simulation Tools and Applications ......... 5 7 2.6 SUMMARY OF LITERATURE REVIEW .................................................................. 60 3 CYCLONE METHODOLOGY AND APPLICATION 62 3.1 CYCLONE METHODOLOGY ................................................................................. 62 3.2 MICROTUNNELING OPERATION PROCEDURES .................................................... 66 3.3 FLOW UNIT AND RECOURSES IDENTIFICATION .................................................. 71 3.4 INTEGRATION OF INDEPENDENT RESOURCE CYCLES ......................................... 80 3.5 RESOURCES INITIALIZATION .................................................................... 87 3 .6 MODELING ASSUMPTIONS .................................................................................. 88 3.7 MODEL ENHANCEMENT WITH SOIL COMPOSITION CHANGES ............................ 90 4 STATISTICAL ANALYSIS OF OBSERVED DURATION DATA .................. 94 4.1 DATA COLLECTED FROM THE PROJECT .............................................................. 95 4.2 INTRODUCTION To STATISTICAL DISTRIBUTIONS IN WEBCYCLONE ............... 96 4.3 KOLMOGOROV-SMIRNOV GOODNESS-OF-FIT TEST .......................................... 103 4.4 DISTRIBUTIONS SUGGESTED FOR THE DURATION TIME RANDOM VARIABLES. 104 ‘ 4.5 COMPARE THE DURATION TIME OF JACKING PIPE SECTION IN DIFFERENT SOIL CONDITIONS ................................................................................................................. ‘ 108 5 SIMULATION RESULTS AND DISCUSSION - - - 111 5.1 SIMULATION RESULTS WITH PROTOTYPE CYCLONE MODEL ........ ’ ................ 111 5.2 VALIDATION OF THE PROTOTYPE SIMULATION MODEL ................................... 114 5.3 SIMULATION RESULTS WITH ENHANCED MODEL CONSIDERING SOIL COMPOSITION CHANGES .............................................................................................. 115 5.4 SENSITIVITY ANALYSIS .................................................................................... 124 5.5 IMPACTS OF DIFFERENT SOIL CONDITIONS ...................................................... 127 6 SUMMARY AND CONCLUSIONS - -- - -- - -- 132 6.1 OVERALL SUMMARY ........................................................................................ 132 6.2 CONCLUSIONS BASED ON THE SIMULATION ..................................................... 133 6.3 LIMITATIONS OF THIS RESEARCH ..................................................................... 136 6.4 RECOMMENDATIONS AND AREAS OF FUTURE RESEARCH ................................ 137 APPENDICES - - - - 141 BIBLIOGRAPHY -- -- ...... - - -- - 206 vi LIST OF TABLES TABLE 2.1 -TYPICAL LENGTHS OF PIPE SECTIONS USED IN MICROTUNNELING ................ 26 TABLE 2.2 -APPLICABILITY OF SLURRY MICROTUNNELING FOR DIFFERENT SOIL CONDITIONS ....................................................................................................... 27 TABLE 2.3 —SOIL CLASSIFICATION SYSTEMS ..................................................................... 29 TABLE 2.4 —PRINCIPAL SOIL GROUPS IN USC ................................................................... 30 TABLE 2.5—DESCRIPTIONS OF GROUP SYMBOLS IN USC ................................................... 31 TABLE 2.6 —COARSE-GRAINED SOILS ................................................................................. 32 TABLE 2.7 — SOIL CLASSIFICATIONS IN THE CANDIDATE PROJECT .................. . ................... 35 TABLE 2.8 —LIST OF MICROTUNNELING EQUIPMENT PROVIDED FOR THE PROJECT ............ 42 TABLE 3.1 —CYCLONE MODELING ELEMENTS ................................................................ 64 TABLE 3.2 —CYCLONE ELEMENTS PRECEDENCE TABLE ................................................. 65 TABLE 4.1—DISTRIBUTIONS, PARAMETERS, TEST STATISTICS, AND P-VALUES ................ 105 TABLE 4.2 —DURATION INFORMATION ............................................................................. 108 TABLE 4.3 — SAMPLE MEANS AND STANDARD DEVIATIONS OF JACKING DURATIONS IN DIFFERENT SOILS ............................................................................................. 109 TABLE 4.4 — PAIRWISE COMPARISON RESULTS FROM TWO SAMPLE T-TEST ...................... 1 10 TABLE 4.5 - PAIRWISE COMPARISON RESULTS FROM WILCOXON RANK TEST .................. 1 10 TABLE 4.6 —JACI 50 percent H Peat Pt A verbal description should accompany the classification symbols, e.g., brown, coarse, well-graded sand with trace of gravel, SW. The ASTM D-2487 should be consulted for 30 any requirements for classifying the soil. In general, soils that have the same classifications tend to have the same engineering behavior (Bowles, 1984). Table 2.5—Descriptions of Group Symbols in USC (Bowles, 1984) Group Typical Names Symbols GW Well-graded gravels, gravel-sand mixtures; little or no fines. GP Poorly graded gravels, gravel~sand mixtures; little or no fines. GM Silty gravels, poorly graded gravel—sand-silt mixtures. GC Clayey gravels, poorly graded gravel-sand-clay mixtures. SW Well-graded sands, gravelly sands; little or no fines. SP Poorly graded sands, gravelly sands; little or no fines. SM Silty sands, poorly graded sand-silt mixtures. SC Clayey sands, poorly graded sand-clay mixtures. ML Inorganic silts and very fine sands, rock flour, silty or clayey fine sands with slight plasticity. CL 1 Inorganic clays of low to medium plasticity, gravelly clays, sandy clays, silty clays, lean clays. 0L Organic silts and organic silt-clays of low plasticity. MH Inorganic silts, micaceous or diatomaceous fine sandy or silty soils, elastic silts. CH Inorganic clays of high plasticity, fat clays. OH Organic clays of medium to high plasticity. Pt Peat, muck, peat-bog, etc. A soil is well graded or nonuniform if there is a Wide distribution of grain sizes present, i.e., if there are some grains of each possible size between the upper and lower gradation limits. A soil is poorly graded, or uniform, if the sample is mostly of one grain size or is deficient in certain grain sizes. A beach sand is an example of a unifome graded soil. The Unified Soil Classification System defines a soil as: 1. Coarse-grained if more than 50 percent is retained on the No. 200 sieve 31 2. F ine-grained if more than 50 percent passes the No. 200 sieve The coarse-grained soil is either: 1. Gravel if more than half of the coarse fraction is retained on the No. 4 sieve 2. Sand if more than half of the coarse fiaction is between the No.4 and No. 200 sieve Size The coarse-grained soil is shown in Table 2.7. Table 2.6 —Coarse-grained Soils (Bowles, 1984) GW, GP or SW, SP 3 5% passes No. 200 sieve GW—GM, GP-GM, GW-GC, GP-GC or SW-SM, SP-SM, SW-SC, SP-SC ‘ GM, GC or SM, SC > 12 percent passes No. 200 sieve 5 < Percent passing No. 200 sieve .<_ 12 Classification of coarse-grained soils depends primarily on the grain-Size analysis and particle size distribution. A major classification change with a small increase or decrease in the percent passing the No. 4 or NO. 200 sieve is another reason why a verbal description is included along with the symbols, i.e., very sandy gravel, very gravelly sand, etc. Only the sieve analysis and the Atterberg limits are necessary to classify the soil in USC system. A sieve analysis is performed and a plot of the grain-size distribution curve is made. When less than 12 percent passes the No. 200 sieve, it is necessary to obtain Cc and Cu to establish whether the soil is well or poorly graded. When more than 12 percent of the material passes the No. 200 sieve, the uniformity coefficient Cu and the coefficient 32 of curvature Cc have no significance and only the Atterberg limits are used to classify the soil. 2.3.4 Soil Selection in the Candidate Project The main goal in determining the four different soil types to be used in the project was to obtain a consistent soil so that the effects of different types of soil on LLB microtunneling system could be determined (Najafi, 1993). Although encountering such a soil variety would be probably rare in actual practice for a single microtunneling operation, it was assumed that the results of the microtunneling test could be used for simulation of impacts of similar types of soils so that the performance of the microtunneling LLB system could be predicted for different subsurface conditions. Moreover, the simulation result could add knowledge of different subsurface conditions’ impacts on general microtunneling productivity and cost. Therefore, in order to simulate soil materials mostly encountered in real situations, samples of sand, clay, silt, and clayey gravel were selected. Eleven different soil samples were tested for possible use in the microtunneling project. These included sands, silts, clays, gravels, and various combination of each. Out of these 11 samples, three most desirable for optimum compaction were selected for backfilling in 14,6-meter (48-foot) lengths in the test trench. Each sample was tested for particle size distribution and Atterberg limits so that it could be properly classified (N aj afi, 1993). The soil specimens were prepared for the appropriate tests in accordance with either ASTM D-2217 (Standard Practice for Wet Preparation of Soil Samples for Particle-size 33 Analysis and Determination of Soil Constants) or ASTM D-421 (Standard Practice for Dry Preparation of Soil Samples for Particle-Size Analysis and Determination of Soil Constants). guide-Size AnglysLsL Each of the samples was subjected to a particle-size analysis in. accordance with ASTM D-422 (Standard Method for Particle-Size Analysis of Soils). A representative ample was taken from each of the 11 samples. A sieve analysis was conducted on the portion retained on the #10 sieve, while the portion passing the #10 sieve was subjected to hydrometer analysis. After the hydrometer analysis was completed, the specimen was washed over a #200 sieve, and the retained material was dried overnight and subjected to a sieve analysis. Atterberg Limits Testip_g._1n order to classify the samples containing clay and silt, it was also necessary to conduct tests to determine the Atterberg limits of the samples. The procedures Used for finding these limits were in accordance with ASTM D-4318 (Standard Test Method for Liquid Limit, Plastic Limit, and Plasticity Index of Soils). The liquid limit of each sample was found by preparing a representative portion of that sample passing the #40 sieve and testing it in a standard liquid. limit device. The plastic limit of each sample was found by rolling a portion of the sample into%-inch thick threads as required by the standard test. The plasticity index was then found by subtracting theplastic limit from the liquid limit. 34 Each of the 11 samples was subjected to tests to that it could be properly classified. according to the USC system. Table 2.20 is a list of the results of the classification procedures conducted on each of the samples. Table 2.7 — Soil Classifications in the Candidate Project (Najafi, 1993) Sample Number Group Symbol Group Name #1 SP Poorly graded sand #2 SC Clayey sand #3 SP Poorly graded sand #4 CL Sandy lean clay #5 GP Poorly graded gravel #6 CL Sandy lean clay #7 SM Silty sand #8 CL Lean clay #9 CL Lean clay with sand #10 SP Poorly graded sand #11 GC Clayey gravel with sand To select the four samples of sand, clay, silt, and gravel, to be used in the project, sample #7, a. grayish brown, very fine material, was chosen as the silt to be used; a combination of samples #8 and #9, which were taken from the jobsite at different depths, was chosen as the best clay sample to used; sample #10, a light brown material, as chosen as the sand to be used; sample #11, a sample of pit-run} gravel, a mixture of 19- to 25.4- mm (% - to 1- inch) top Size gravel, sand, and clay, was obtained and chosen as the gravel to be used. 2.4 Simulation Candidate Project Description 2.4.1 Project Location and Soil Profile 35 For this study, data was collected on the Louisiana Tech University LLB Microtunneling Field Test Project, located in Ruston, Louisiana. This project was conducted in order to evaluate workability of the LLB system in actual field conditions. As a technology transfer project, details of the test were finalized between the LLB system manufacturer- Kidoh Construction Company, Iseki Inc., and Trenchless Technology Center at Louisiana Tech University. A 58.52 meters (192 feet) long test bed was constructed on the Louisiana Tech University campus. An excavation of 43.89 meters (144 feet) in length and 2.13 meters (7 feet) wide and 3.05 meters (10 feet) deep was constructed. It was backfilled with equal sections of clay, silt, sand, and clayey gravel. An additional 14.6- meter (48-foot) section of the test bed was undisturbed stiff clay. The length of each section of the test bed was chosen to be the equivalent of Six 2.438-meter (8-foot) pipe seCtions. The depth of installation was unifome 2 meters (6.6 feet), which is the minimum requirement for slurry microtunneling method to provide enough pressure to prevent slurry loss. The ground water level was found to be 1.5 meters (5 feet). Figures 2.14 to 2.16 illustrate the test bed construction. 6 M ‘ 14.6 M I 14.6 M I 14.6 M I 14.6 M ' me «a an “R ‘flfl gig“ CLAY SILT SAND CLAYEY GRAVEL Figure 2.14 - Test Bed Plan (Najafi 1993) _ 36 Figure 2.15 — Test Bed Cross Section (Najafi 1993) Figure 2.16 —Test Bed Construction (Najafi 1993) 37 M /fi — Ground Surface s/ (/ 0.5M 0.66M 0.5M 1.2M(4FT)/‘ I // j l: \ j / 2 0.6 M 2 FT - /x/ ( ) E II 0.66 M (2.2 FT) ” A 0.34M (1.2 FT) II 7 f / PVC PIPE “*4 LINE F EXCAVATION 1.5 1101 slo 2.4.2 J acking Forces The jacking forces in this project varied from a range of 9 tf to 14 if when jacking through clay, from 10 tf to 20 tf when jacking through silt, from 11 tf to 21 tf when jacking through sand, from 23 tf to 41 tf when jacking through Clayey gravel. Detailed jacking force information was obtained for 24 of the PVC pipe drives. 2.4.3 Microtunneling Pipes The project consists of the installation of 58.5 meters (24 drives) of OD 620 mm PVC sanitary sewer pipe using Iseki Unclemole (TCC 500) microtunneling machine. PVC is a suitable product for sewer system construction. Some of the advantages of PVC pipes include the following: 1) light weight and easy to handle, 2) good impact resistance and toughness, 3) excellent resistance to a wide range of corrosive environments found in sewage and soil, 4) good hydraulic flow characteristics, 5) easy to work with, 6) economical, 7) durable, 8) availability of different joint systems which are extremely reliable against leakage, 9) excellent abrasive resistance, 10) excellent dimensional control, and 11) not biologically degradable (Najafi, 1993). The use of PVC sewer pipe has decreased infiltration and exfiltration and accompanying tree-root problems. The surface of the pipe is very smooth and resists buildup of deposited materials and other solids. Compared to other types of pipe materials available for microtunneling such as reinforced concrete, steel and glassfiber reinforced plastic mortar pipe (GRP), PVC sewer pipe has 38 ,less unit cost (Najafi, 1993). However, in the past, the following factors were the main obstacles to the utilization of PVC pipe in microtunneling: 1. Axial thrust load limitations, 2. Higher cost of thick-wall PVC pipe to resist the thrust load, and 3. Lack of a suitable joint compatible for microtunneling. In the LLB system, the above obstacles have been removed with a method of transmission of the thrust force by the addition of a liner casing and gripper system. This system transfers the face resistance of the machine to the liner casing inserted in the pipe. 1 Also, the circumferential frictional resistance of the product pipe transfers to the gripper systems which are installed at certain interVals along the length of the pipe. These gripper systems expand with air pressure and connect the liner casing with the inner surface of the pipes to transmit the thrust 'force of the liner casing to the pipes. Therefore, the maximum thrust force exerted to the product pipes is equal to the circumferential fiictional resistance of the portion of product pipes between the gripper locations. Consequently, with utilization of the LLB system, pipes with relatively low compressive strength can be installed with microtunneling methods. In addition to reducing the thrust force on the plastic pipe, the gripper system also has the following Characteristics: 1.- There is minimal possibility of damaging pipes because the contact is made by pneumatically inflated rubber tubes. 39 2. Conventional microtunneling methods require product pipes of special wall thicknesses. The LLB system does not have these requirements. 3. The grippers can be installed at desired locations depending on the level of circumferential resistance of the pipes. 4. Long-distance thrusting with minimal restriction to pipe compressive strength is possible with LLB system. Some of the characteristics to consider when selecting a pipe for microtunneling operations are stiffness, smoothness of the pipe and joint design, joint watertightness, . dimensional consistency, weight, resiliency and absorbency. After reviewing the available options of different PVC products for water and sewer construCtion, Vylon PVC Sewer Pipe manufactured by Lamson Vylon Pipe, Cleveland, Ohio, was selected for this evaluation program. The Vylon pipe provided suitable characteristics and eliminated both of the major obstacles other PVC pipes experience when used for microtunneling, that is, cost and suitable joint. The Vylon pipe utilizes a new joint system developed by Lamson Vylon Pipe for microtunneling. The joint provides a smooth outside and inside transition from one pipe section to another, making the pipe suitable for microtunneling application. This connection permits the pipe and joint system to mate up with the machine. Additionally, and air-tight seal is formed at the joint with a multi-fin gasket wrapped around a fiberglass insert ring. For economy, Vylon utilizes a profile wall. Vylon’s I-Beam design / 40 reduces the amount of PVC required when compared to the same size solid-wall pipe, yet maintains smooth surface inside and outside. The pipe sections selected for use in the project were each 2.438 meters (8 feet) in length and weighed approximately 29.76 kg/m (20 pounds per foot). The Vylon PVC sewer pipe is manufactured according to ASTM F-794 for pipe requirements and ASTM D-3212 for joint requirements. A special adapter was designed and manufactured by Iseki Poly-Tech for the pipe/microtunneling machine connection. This connection provided the necessary tolerance for the PVC jacking pipe and LLB propulsion system. This adapter was located at the tail of the boring machine and provided the necessary tool to transfer face resistance of the boring machine to the liner casing while the PVC pipe mated up with the adapter. 2.4.4 Microtunneling Equipment An Iseki Unclemole machine (TCC 500) was used for this program. The Iseki Unclemole is a small-bore tunneling machine designed to meet the demand for a wide range of ground conditions. This machine has an actual outside diameter (OD) of 655 mm (25.787 inches) and can construct a borehole equivalent to 660 mm (25.984 inches) in diameter. The Unclemole is basically a mechanical earth pressure counter balance (MEPB) shield that utilizes slurry to counterbalance hydrostatic head and to transport excavated material. The Unclemole uses a unique built-in cone—shaped crusher to crush cobbles and gravel up to 30 percent of the outside diameter of the shield into small particles for transportation as slurry. Figure 2.18 illustrates the mechanism of the cone-shaped crusher. 41 Figure 2.17 — Cone-shaped Build-in Crusher (Herrenknecht 2000) The Unclemole was modified to accommodate the LLB system and Lamson Vylone pipe. The necessary microtunneling equipments were provided by Iseki Poly-Tech, including boring machine, jacking equipment and guide rails, charging and discharging slurry pumps with necessary pipes and hoses, laser transit, desandman, entrance ring, hydraulic unit and control panel. The desandman is a slurry container which has a Vibratory screen and hydrocyclone to separate slurry from spoil material. A list of equipment provided by Iseki Poly-Tech for this evaluation program is provided in Table 2.9. Table 2.8 —List of Microtunneling Equipment Provided for the Project (Najafi, 1996) Net Description Quantity Weight Size (kg) 600 mm diameter, 2,390 mm Tunnel Boring Machine, TCC-500 (LC) 1 length 1,040 Thrust Jacking Equipment, 3-Stage 1 Width 1,300 mm, Length 4,400 Molemeister, M3-150T—30 (I) m 42 Table 2.8 (cont’d) Diameter 670 mm, Length 170 Load Meter 1 mm Air Bleeding Valve, SAP02-000J l 29 x 14 x L53 Check Valve, S6AT-KI-0 l 28 x 24 x L80 Thrust Ring Assembly 1 Operation Board, B05-I, including Power Cables, 1 W1,000xH1,270xL700 Operation Cables and TV Cable 1,040 Power Pack, MP-7.5k-320 A 1 Straub Coupling, Connecting Pipes, Hydraulic Hose, Power Cables, Operation Cables, Jack 1 set 80 Speed Cable Diameter 646 mm, Length 630 Adapter Ring 1 mm Diameter 640 nrrn, Len 950 Special Collar l gth . mm Pit By-Pass Unit, TRW-2 1 1,100 Entrance Ring , l Slurry Pump, SC-28WES, 5.5 kw-4p l Inventor Pump, SC-28WES 5.5 kw-4p 1 Flexible Hose 8 Distribution Boards, ELCB 200A, MCCB30A x A 2 3-100A and ELCB 200A, MCCB75A x 3 + 50A Flow Meter, Pipe, Flexible Hose, Elbow Pipe, 1 set 270 Victualic Joint, etc. Operation Cable, Laser Theodolite (LTL-ZODP), 1 210 Diagonal Eye Piece, Funnel Viscosimeter PC Bar r ----------------------------- % ' Swag : a“ T —————— ‘::::::::—_::: l __________ J 1‘ T New Cm, I. decaooessfirdeliveryof Figure 2.18 -Typical Layout for Small Microtunneling System (Abbott 2005) In larger microtunneling projects, which commonly install large diameter pipelines in inurbane areas, the space constrain is less an issue because of the location of projects and larger equipment requirements. Figure 2.20 illustrates a typical larger microtunneling 46 project layout around driving shaft area. The construction site is accessible from two sides, which reflects more delivery material needs. Truck Access for Muck Removal from Slurry Separation Tanks Slurry Separation Tanks Pipe advance L1 { ”digitsuntrrq [— Crane > ---—-— ------ Jacking pit l' -------- l . : Pipe & Materials I Control Cabin. and I S I Shop Facrlrtres . torage . | I <— Truck Access for Delivering Pipes and Materials Figure 2.19 - Typical Layout for Large Microtunneling System (Abbott 2005) In the project in Ruston, Louisiana, the microtunneling operation was conducted in a test area on campus. Congestion was not a serious issue in such a test project as in urban area. In order to generalize the simulation model, the site layout of the candidate project is slightly modified to reflect common pattern of microtunneling operations. Figure 2.21 shows the site layout of the project. Equipments’ lay out was next to the 58.52 meters (192 feet) long test bed on the Louisiana Tech University campus. Driving and receiving shafts were located at both ends of the test bed. 47 806E mcxoquEEE 836.80 2: we Seas 86.. ¢~.~ Paar-m 65880 3.580 MES. E5 MESS—60 Boceo>o academmom $me . . 598A Mama. oofiomm owfioum zomm e34 wfigoq x695. . mom—saegm do mmfinm ea... FEE ow 383m 698252 «Em 53.5 0:80 L _I use“: wcfiso BEE; 62.5 mo :28th IV mobs deem ommeoem 03m notoom / 8305500 II a? 48 2.5 Construction Simulation 2.5.1 Computer Simulation Overview Computer simulation is a valuable management tool that is well suited to the study of resource—driven processes. It gives the analyst an insight into resource interaction and assists in identifying which factors in a problem domain are important. Simulation allows the modeler to experiment with and evaluate different scenarios. Normally, such experimentation and study would be too costly to be carried out in the real world. Real world systems are so complex that some these systems are virtually impossible to model and solve mathematically (Banks and Carson II, 1984). In these instances, numerical and computer-based simulation can be used to imitate the behavior of the system over time. A model is defined as a representation of a system for the purpose of studying the system. Although Mihram and Miharam (1974) and many other simulationists stated that it is not necessary to consider all the details of a system because thereby a model is a substitute and a simplification of a system, the model should be sufficiently detailed to permit valid conclusions to be drawn for the real system. The Simulation model building process involves many steps. Problem formulation, setting up of objectives, model design and building, data collection, programming and validation, and implementation are the major steps. The art of modeling is enhanced by an ability to abstract the essential features of a problem, to select and modify basic assumptions that characterize the system, and enrich and elaborate the model until a useful approximation 49 results. However, the model complexity need not exceed that required to accomplish the purpose for which the model is intended (Banks and Carson II, 1984). Computer simulation is defined as the process of designing a mathematical-logical model of a real world system and experimenting with the model on a computer (Pristker 1986). Early simulation users were required to build a model by writing programming code, mainly in FORTRAN, and experimenting by directly manipulating the computer program. This was followed by the invention of simulation specific programming environments where users write simulation specific code or access a provided function library. “Modeling” is the term used to describe the process of specifying a given simulation model. In the next phase of development, a host of systems were introduced that allowed for alternative model development. This meant that modelers no longer had to write code directly. Graphical modeling made it possible to define the simulation model by creating, manipulating and linking a number of available basic building blocks. This meant that users no longer had to be proficient in programming. A detailed account of the history of simulation concepts and systems is detailed in Kreutzer (1986). Computer simulation can be Classified as either deterministic or stochastic depending on its uncertainty content (Wilson 1984). Since construction operations are subject to a wide variety of fluctuations, changes, interruptions, and uncertainties, most simulation applications use probabilistic simulation methods in simulating construction operations. The input modeling, model. design, and output modeling are critical issues in simulation modeling for any given situation. AbouRizk (1990) conducted in-depth research on 50 modeling input data for the simulation of construction operations. There are many problems faced by the model designers and users when creating simulation models. When a real system is converted into a simulation model, several logical assumptions are applied. Sometimes these assumptions do not represent the correct nature of the real system. Uncertainty and unpredictable events in a real system are usually modeled using statistical distributions to reflect the actual occurrence of those events. A lack of historical data and its applicability to a statistical distribution may fail to successfully model such random events. Because of the high uncertainty involved in construction operations and the unavailability of historical quantitative data, various researchers have hypothesized the determination of activity durations for most construction operations. AbouRizk et a1. (1994) divided certain input parameters for “certainty portions” and “uncertainty portions” based on the uncertainty content of the input parameters: deterministic analysis to estimate the certainty potion and probability and conceptual analysis to estimate the uncertainty portion. Construction simulation Can be of great assistance to decision makers in analyzing various construction operations and alternatives. Simulation of construction operations allows analysts and construction industry personnel to experiment with different construction technologies, and estimate their possible consequences and impact on scheduling and costs. Although simulation has been considered a very powerful tool for construction, its application to real life construction projects has been minimal (Ruwanpura 2001). The use Of computer simulation for planning construction projects 51 has been limited to academia and a few large contractors who can afford to employ dedicated simulation professionals (Haj jar 1999). 2.5.2 Construction Simulation Possibly due to the uniqueness of constructed facilities and the perceived lack of repetition, the concept of studying work processes did not receive much attention until the late 1960s. At this time, work sampling and various graphical techniques related to bar Charting were considered. It was recognized that although projects are typically unique, many construction processes are repetitive (e.g. earth hauling, tunneling, road construction, glass installation on a tall building, etc.) and amenable to closer investigation. Due to the comparatively short "half life" of construction processes, sophisticated analytical methods were viewed as being too complex for most situations. With the emergence of the desktop computer, application of more sophisticated methods has become more accessible. In particular, simulation of construction processes to establish anticipated levels of production and solve some of the problems related to the randomness of construction operations has become a more widely accepted as a tool available for use in planning and estimating. Random number techniques to solve stochastic problems encountered in construction have been used to establish ranges of expected cost (e. g. range estimating), evaluate project time duration (PERT simulation), and model and evaluate expected production of 1 various construction processes. One of the earliest applications of random number methods was in a gaming context. AI, Parti, and Bostleman developed a construction 52 bidding game in the late 603 which in Various configurations is still used at several universities for teaching purposes (Au et a1, 1969). Following this, the CONSTRUCTO project management game was developed at the University of Illinois by Halpin to integrate the effects of weather and labor productivity into the management of projects in a network format (Halpin, 1976). A similar simulation was developed by Borcherding (1977) of the University of Texas. Recently, the concepts of the bidding game and the project management format have been integrated into an educational game (Superbid) by AbouRizk at the University of Alberta, Edmonton (AbouRizk, 1992) In order to be accepted in the construction environment, simulation has to be presented in a very simple and graphical context. Contact with construction professionals indicates that formats which appear to be too theoretical or analytical tend not to be accepted of utilized. Therefore, ideally simulation systems should be pictorial of schematic emphasizing graphical input and graphical output. The early systems designed to study construction operations utilized simple bar Charting concepts. With the advent of simulation methods in construction, simple networking concepts were introduced as a modeling framework for studying construction operations. The earliest of these methods was the so-called "link node" model adapted by Teicholz (1963). After that, Halpin (1973) developed the CYCLONE format at the University of Illinois that has become the basis for a number of construction simulation systems. CYCLONE simplified 53 the simulation modeling process and made it accessible to construction practitioners with limited Simulation background. 2.5.3 Simulation Modeling There are many ways of modeling a given problem and these generally fall into two categories: continuous and discrete-event. Continuous or time-dependant algorithms are often represented with a system of equations or mathematical models and then solved for steady state performance using differentiation, integration, or approximation. In discrete event simulation utilizes “next event processing” of activities based on logical relationships between process components and availability of resources (AbouRizk, 1998) Users can typically Change the behavior of a simulation model after it is constructed. This is the concept of the reusability where the model can be used for a multitude of scenarios. The degree to which users can change the pre-defined simulation behavior is dependent on the development strategy utilized. Simulation systems can generally be classified according to this feature as follows (Ulgen et a1, 1991): 1. Fully documented simulation models, 2. Parameterized simulation models, 3. Special purpose simulation program generators, and 4. General-purpose Simulation program generators. With fully documented simulation models, users are required to modify the simulation models by manipulating them at the same level used to originally develop them. This 54 assumes end users are knowledgeable with the way the simulation system works. Parameterized simulation models allow for model re-use by exposing a set of parameters that users can modify each time the model is simulated. The values of the parameters can be used to modify routing strategies, resource values and entity attributes. With special- purpose program generators (SPSPG), users are able to create models by selecting from a list of available domain specific constructs and defining their parameter values as well as their relation to other elements. Examples of such systems include WITNESS and SIMFACTORY (Mathewson 1989), Ap2Earth (Hajjar et a1. 1998). The advantages of special purpose simulation program generators are outlined in AbouRizk and Hajjar (1998). General-purpose simulation program generators (GPSPG) are like SPSPG; only expert users can add new modeling constructs to the system. Halpin (1977) popularized the use of simulation in construction research with his invention of a system called CYCLONE (CYCLiC Operation NEtwork). CYCLONE allowed-the user to build models using a set of abstract but simple constructs. The system became the basis for a wide range of construction simulation research efforts with the objective of enhancing the basic system fimctionality and most construction simulation work was motivated by the success of CYCLONE (AbouRizk, 1998). This included MicroCYCLONE (Halpin, 1978), INSIGHT (Paulson et al., 1978), UM-CYCLONE (Ioannou, 1989), and RESQUE (Chang and Carr 1987). STROBOSCOPE (Martinez and Ioannou, 1994) was another development based on CYCLONE which allowed for dynamic simulations based on the definition of entity and resource attributes using 55 programming - like syntax. DISCO (Huang et al., 1994) developed to allow the use of graphical-based modeling for CYCLONE models. Simphony is another simulation platform for building general and special purpose simulation tools, which was developed in the University of Alberta. It is a Microsoft 3 Windows based computer system developed with the objective of proViding a standard, consistent, and intelligent environment for both the development and utilization of special purpose simulation (SPS) tools (Hajjar and AbouRizk, 1999). AbouRizk and Hajjar (1998) also defined SPS as “a computer-based environment built to enable a practitioner who is knowledgeable in a given domain, but not necessarily in simulation, to model a project within that domain in a manner where symbolic representations, navigation schemes within the environment, creation of model specifications, and reporting are completed in a format native to the domain itself” A detailed introduction can be found in Hajjar and AbouRizk (1999). MicroCYCLONE is chosen as the base for this simulation study, due to the accessibility and ease of use. Specifically, a web based version of MicroCYCLONE, namely, WebCYCLONE maintained by Purdue University is used to run simulations. The use of WebCYCLONE requires coding of the model in a format set by MicroCYCLONE and upload to the website. The interface of WebCYCLONE is shown in Figure 2.22. MicroCYCLONE is a microcomputer based simulation program designed specially for modeling and analyzing site level processes which are cyclic in nature. In broader terms, it can be used to model construction operations which involves the interaction of tasks 56 with their related durations, and the resource unit flow routes through the work tasks are the basic rationale for the modeling of construction operations. 1 )1"HIUI‘[I‘lwvrlltbllnlll IKWI l‘lll - Hum-inn I‘m flu Wmmewmweassmm undead-d Auoo more “races a Welcome 00 Pudse CEM Web-Cyclone Smlhfion Iab' V -L 44‘ bflvm \Yr 1:; mu sumac PM!” I-I'CTI 1.000 mu! 30 II In!" 'LOLDII '1" warm: '1" 'LOAD TWCK' “'1‘ 3 PI] 1 t '01. 1 4 ‘I’M‘ "I 1 '0]. 5 ii?! I O ' 'I'OT‘I’II ITA‘IIW' 'llfl‘l L DW' 8" 7 III I 6 I01. 6 O l udniouNV-E i§§i b In! war at! 3 lol. 2 Donna: I'm Fl! 3 I‘ll 1 1.3 2 n! 1 ru 5 c 1 s" 7 on LI nr a nr 4 s 6 owner nmrr z mourn: A! I. In so to 'Tmr AT z "x 2! .l ‘SPOH'II' A! 6 10¢ 30 ‘. Compile I uTJacaRunfj _Runw/and.lnio I Run 1 Figure 2.21 -A glance at WebCYCLONE User Interface 2.5.4 Tunneling and Microtunneling Simulation Tools and Applications Similarities exist between tunneling and microtunneling construction methods. Microtlmneling is considered as tunneling with special features (ASCE, 2001). As having much longer history, researches have been approached on all aspects of tunneling. The significant amount of previous tunneling simulation projects can nourish the development of microtimneling simulation, which is rarely found. 57 In general, the term “tunneling” can be used to describe a wide range of underground excavation operations. Tunnels can be used to serve a variety of functions, including subways, utility corridors, and sewer lines. Tunnel construction projects are particularly suitable for simulation due to the many repetitive construction cycles that occur during construction. Simulating the process of tunnel advancement can guide the engineers, planners, and constructors to plan and control the project more efficiently. It is generally accepted that tunneling projects are typically high-risk. Successful project planning can save both cost and time, resulting in a productive tunnel construction project (Ruwanpura, 2001 ). Touran and Asai (1988) predicted the tunnel advance rate in the construction of a several- mile-long, small-diameter tunnel in soft rock using CYCLONE. Tanaka (1993) presented a tunnel simulation using CYCLONE for shielded tunnel boring machines. AbouRizk et a1. (1997) applied tunnel simulation using Visual SLAM to analyze the productivity of construction activities for a tunnel constructed under a river to validate a productivity claim. Olufa et al. (unpublished) presented a library-based simulation modeling development with an implementation in shielded tunnel construction projects in University of Alberta. They used an object-oriented simulation programming language called MODSIM to simulate the tunneling projects. Salazar (1987) presented a simulation model based on the eVent scheduling approach to generate probabilistic descriptions of the advance rate of tunnel excavation and the corresponding demand for resources. It used linked lists to dynamically schedule construction activities as the excavation takes place through difficult ground conditions and provided two case studies comparing two 58 tunneling methods to illustrate the model. Abd Al—Jalil (1998) developed a decision support system- Decision Aids in Tunneling (DAT) to predict the performance of Tunnel Boring Machine (TBM) based excavation systems in hard rock geological conditions. These tunnel simulation models have catered to particular situations and cannot be used for other types of tunnel or microtunnel construction projects. Ruwanpura et al. (2000b and 2000c) discussed the independent studies conducted by two graduate students Hajjar (1997) and Ruwanpura (1998) of the University of Alberta as part of their course work, to model TBM-based tunnel construction using Visual SLAM (Pritskar 1994). However, both models were not flexible enough to model for any given tunnel construction project using a TBM, and were not validated using a constructiOn project. In both cases, they concluded that simulation could be a very useful tool for project planning. As an improvement, Ruwanpura (2001) developed a Special purpose simulation (SPS) template for tunnel construction operation, which included a modeling technique to predict the soil types in the tunnel path in City of Edmonton, Alberta, Canada. The prediction of soil types in the tunnel path was realized by using Markov Chain probabilistic theory on historical geological bore data from City of Edmonton. Research on microtunneling using simulation is very limited. Nido et al. (1999) simulated an actual rrricrotunneling project in Montgomery COunty, Ohio, using CYCLONE methodology. The analysis highlighted the impact of variations in soil compositions on the productivity of the operation and on the utilization of labor resources. The project selected for Simulation used centrifugally cast fiberglass mortar pipes, which is 59 significantly more expensive than PVC pipe used in the Louisiana Tech University LLB Microtunneling Field Test Project. Since the pipe cost constitutes a big portion of microtunneling cost, the effect on cost reduction by using PVC pipe is one of the goals of this simulation research. Nido et al. selected an actual microtunneling project with predominantly variety of clays encountered along the path, based on which simulation was conducted to analyze the impact of variations in soil compositions on the productivity. The soil compositions were limited by the actual geological conditions on the job site; therefore, the simulation could not reveal potential impacts of a wide range of soil conditions. However, in the Louisiana Tech University LLB Microtunneling Field Test Project, to simulate soil materials mostly encountered in real situation, samples of sand, Clay, silt, and gravel were selected artificially. Although encountering such a soil variety would probably be rare in actual practice for a single microtunneling operation, it was assumed that the results of the microtunneling test could be used for similar types of soils so that the performance of the LLB system could be predicted for different subsurface conditions (Najafi, 1993). This feature of the data collected will enhance the simulation analysis. 2.6 Summary of Literature Review The literature review in this Chapter indicates that simulation can be used for study on the productivity of cyclic microturmeling operation. Backgrounds and elements need for an Operational simulation on microtunneling have been reviewed. Various aspects of microtunneling methods in general and the candidate project in specific were descried in details. The possibility of the application of CYCLONE simulation on microtunneling was discussed. Also, pipe materials used in microtunneling and soil condition 60 Classifications were documented to develop a broad-based understanding of the method. The literature review indicates that there is a good possibility to develop a succeszul CYCLONE model if the microtunneling operation procedures are well understood. In following chapters, simulation models will be developed based on operation procedure and duration data analysis. 61 3 CYCLONE METHODOLOGY AND APPLICATION Previous chapters dealt with the literature review that gave the necessary background for pursuing this thesis. This chapter presents the methodology used in this research for microtunneling productivity analysis. The productivity simulation models are built with CYCLONE (C YCLic Operations NEtwork) techniques. A detailed description of CYCLONE methodology is presented in this chapter, along with the model development. 3.1 Cyclone Methodology For the analysis of the microtunneling operation productivity of the candidate project, Web-Cyclone, a web-based Simulation program that is based on the CYCLONE methodology, was selected for modeling and simulation of the process. The CYCLONE (CYCLic Operations NEtwork) methodology is a modeling technique that allows the graphical representation and simulation of discrete systems that deals with deterministic or stochastic variables. Construction processes simulation using the CYCLONE methodology, abstracts the reality into a graphical representation'by dividing the process into discrete pieces or work task and by representing how these interact. It focuses on resources and their interactions. The purpose and ideal objective of computer simulation is to optimize system performance, in the thesis research, is to study to improve and estimate microtunneling productivity. Steps involved in CYCLONE simulation are: 0 Defining the system (well defined boundaries) 0 Modeling the system (system of equations, graphical modeling) . 62 0 Input & Output Analysis 0 . Validation/Verification To define the Network model: 0 Define work task composing a process 0 Establish logical relationship between the work tasks 0 Work task use resources and require time to be completed, this fact is accounted into the model by supposing that entities flow thorough the network, are delayed by work tasks, wait for processing, etc. When they are served (or used) by each work task they continue flowing through the network. The basic modeling elements used in the CYCLONE methodology are shown in Table 3.1. The precedence rules of CYCLONE elements are shown in Table 32 Resources can be in one of two states — active (denoted by a square element) or idle (represented by a circle element). Resources will move between these two states, as they “traverse” from one activity to another. A flow unit traverses a CYCLONE network with the following effects: 0 Waits in QUEUE nodes for processing 0 Initiates (or signal) the processing of a work task 0 Generate other entities where they traverse a QUEUE-GEN node . Get consolidated with other flow units when they pass a CONSOLIDATE Function 63 0 Register productions where they pass a function COUNTER Table 3.1 —CYCLONE Modeling Elements (Division of Construction Engineering and Management Simulation Homepage, Purdue University, 2005) Name Symbol Function Combination (COMBI) Activity This element is always preceded by Queue Nodes. Before it can commence, units must be available at each of the preceding Queue Nodes. If units are available, they are combined and processed through the activity. If units are available at some but not all of the preceding Queue Nodes, theSe units are delayed until the condition for combination is met. Normal Activity This is an activity similar to the COMBI. However, units arriving at this element begin processing immediately and are not delayed. Queue Node This element precedes all COMBI activities and provides a location at which units are delayed pending combination. Delay statistics are measured at this element. Function Node It is inserted into the model to perform special function such as counting, consolidation, marking, and statistic collection. It is used to define the number of I‘v. . Accumulator times the system cycles. Indicates the logical structure of Arc the model and direction of entity flow. 64 Table 3.2 —CYCLONE Elements Precedence Table (Division of Construction Engineering and Management Simulation Homepage, Purdue University, 2005) - Q Q P Q M N N N N O P N 1 I 1 N M = required or mandatory 0 I = immaterial o N = nonfeasible Active states or work tasks can either be unconstrained (NORMAL modeling element — represented by a rectangle) or constrained (i.e., certain initial conditions must be satisfied). The constrained active states are named COMBI (depicted by a hatched rectangle) modeling elements. “The NORMAL and COMBI work tasks have user- defined time delay functions that represent the time period during which resource entities are delayed while processing through these work tasks. The idle state represented by the QUEUE node, has the potential for storing in a waiting state or queue format the resource entities held up by system requirements pending the satisfaction of COMBI work task ingredients or initializing logic” (Halpin et al., 1992). The sequence of work tasks 65 undertaken by the resource entities together with their idle states indicates the level of the use of resource. Two basic resource flow patterns are commonly used. The slave entity pattern is produced whenever a resource entity is used by a single active work task, such that the resource entity cycles between the active state and the idle state. When a resource entity is Shared between two or more work tasks, the resulting flow pattern is called a butterfly pattern. In such cases, Once the resource entity is in the idle state, its subsequent active work state may depend on other factors, such as the availability of other resources, the priority system adopted for the work tasks in the construction operation, etc. Units can be generated into the system by defining a GENERATE fimction (abbreviated as GEN) which is associated with a selected QUEUE node. When a work task is initiated after a specified number of cycles of the system or system subcomponent, a CONSOLIDATE function (abbreviated as CON) is defined. The GENERATE function is a discrete event multiplier, while the CONSOLIDATE function can be considered a discrete event divider. 3.2 Microtunneling Operation Procedures The microtunneling procedures for the simulation candidate project are as follows: 1. Excavate and prepare the driving shaft. 2. Set up the control container and any other auxiliary equipment beside the jacking shaft. 3. Set up the jacking frame and the hydraulic jacks. 66 4. Lower the MTBM (Unclemole) into the driving shaft and set it up on the guide rails. 5. Set up laser guidance system. 6. Set up the slurry lines and hydraulic hoses on the MTBM as illustrated in Figure 3.1. ‘ . r“TIT f » . ~ sf ,. “1 .. _ a? ‘ ‘ '7 ‘1 I ‘QM 7' ' “a. m 3‘ it ' "a“ a. I, o... _ ' .i . .-_ ._'.'_ "‘» - Hoses Connected ‘ (I i — A}, ~ :. ‘. i I H 'I g- {is g . , . . , ‘w‘ x ,- . ». r_ ‘-. E Slurry , . ' ‘ Communicatlons ti .1 Slurry _. Charge . .1 J. ischarge ms. ._ ; 1. m .. Figure 3.1 - Slurry Lines and Hydraulic Hoses (Najafi, 2005) 7. The main jack pushes the MTBM. 8. After the MTBM is pushed into the ground, the slurry lines and hydraulic hoses are disconnected from the jacked section (or MTBM). 9. The hydraulic jacks are retracted. 10. A new pipe section is brought from the storage and liner casing with two slurry steel pipes, air hose and cables are placed inside the pipe as shown in Figure 3.2. Air grippers are installed on certain sections as shown in Figure 3.3. 67 1 Figure 3.2 -Inside View of PVC Pipe Showing Liner Casing, Slurry Pipes, Bentonite Hoses and Cables (Najafi 1993) Figure 3.3 — Air Gripper Used in the Project (Najafi 1993) 11. The pipe section is attached to crane and lowered into the driving shaft as shown in Figure 3.4. 68 Figure 3.4 — Lower Pipe Section into Driving Shaft (Najafi 1993) 12. Connect the slurry lines and hydraulic hoses in the new pipe segment to the ones in the previously jacked segment (or MTBM). 13. Jack the new pipe section, while removing the spoil, adding lubrication, and filling water as shown in Figure 3.5. Figure 3.5 — PVC Pipe Joint Being Pushed in (Najafi 1993) 14. Excavate and prepare the receiving shaft. 69 15. Repeat step 8 to 12 as required until the pipeline is installed. The CYCLONE simulation model will be built based on this cyclic process. 16. Remove the MTBM through the receiving shalt. Figure 3.6 illustrates the MTBM entering the receiving shaft. Figure 3.6 - MTBM at the receiving shalt (Kerr Construction Inc.) 17. Remove jacking frame and other equipment from the driving shaft. I 18. Grout the annular space between the exterior pipe surface and the tunnel. 19. In case of sewer applications, install manholes at the shaft locations. 20. Remove shoring, lining, or casing from the shaft and backfill them. The major procedures in the candidate project are also applied in slurry type microtunneling in general. Therefore, possibility exists that the simulation model based on the specific project can be generalized to other slurry type microtunneling projects with modification. 70 Microtunneling is a complex operation process, which includes multiple types of resource cycling and interacting in the overall system. Due to the limited supply of resources, interactions between various resource cycles create the major limitation on productivity of microtunneling operation. To optimize the productivity, single resource cycles must be modeled first and integrated with the logic among them to truly reflect the microtunneling operation. On the both levels of modeling, the CYCLONE model building procedure need to be followed, which involves four basic steps: 1. Define resources; '2. Identify work tasks in the process (work tasks with which resources are involved); 3. Determine the logic of the processing of resources; 4. Build a model of the process. The next section will follow the four steps to identify flow units and resources in each resource cycles. 3.3 Flow Unit and Recourses Identification The resource identification stage is extremely important since it will dictate the degree of detail of the finished model. In order to portray the resources in the model, important activity duration information must be measured in the field. The most important resources were identified as the following: the pipe sections, the jacking system, two labor crews (called Labor A and Labor B), the lubrication mixture, the water in the spoil removal system and the spoil that was removed from the borehole (these resources will be called leading resources thereafter). Other resources were identified, but they were 71 considered as secondary resources, these included construction equipment such as backhoe, crane, dump trucks, water truck, air grippers for the PVC pipes, and the ingredients for the lubrication (bentonite and polymer). The most important resource in the system is the pipe section. A pipe section is defined as a 8 feet long section of PVC sewer pipe. The pipe sections are brought to the site and are placed on a storage place showing on Figure 3.1, as they are unloaded from the truck. When needed, the Labor A rolls one section to the base of the crane where it will be prepared for installation. This preparation includes the placing of a liner casing with two slurry steel pipes, air hoses and cables inside the PVC pipe Section. Air grippers need to be installed on every four sections. Then, the prepared section will be attached to the crane and lifted, lowered into the shaft and laid on the guardrail. Labor B crew sets up the pipe for installation. The setup activity includes installing slurry pipes, air hose and cables, joining the thrust ring with the liner casing and the PVC pipe, and installing laser guidance. Once the pipe has been set up, the jacking of the section may begin. After the pipe section has been fully jacked, slurry lines and the hydraulic lines may be dismantled. At this point, one production cycle is complete. For the models developed in this study, the production unit was defined as the jacking of one 8 feet long section of PVC sewer pipe. The installation of each section was deemed to be completed after the slurry and hydraulic lines have been dismantled from the jacked section. Figure 3.1 illustrates the resource cycle for pipe section. 72 Air gripper installation as a secondary resource is required on certain pipe sections in the preparation activity. Due to the material characteristic of PVC pipe used in the project, air grippers have to be installed on some pipe sections for the air hoses in order to adapt the PVC pipe to the microtunneling system. The project used air grippers on section number 4, 9, and 14 in 24 sections installed, which was based on the engineer’s experience. Assumption is made to model air gripper installation on every 5 sections. Based on the notes in Appendix B, after installations, approximately 67% of times the air grippers are ready to use, and 33% of times it needs to be adjusted, which occupies resources (Labor A, Supervisor) for certain time. Fig. 3.8 illustrates the air gripper installation on the pipe section that is necessary. POSITION OCCUPIED / . . Bnng section from ‘ storage& prepare SECTION ON / . Dismantle cables STORAGE and hoses / . SECTION IN Attach section to PLACE crane Jack pipe Lift section to section position ' fipe section setup SECTION firwer section into SECTION on guard rail READY shaft READY Figure 3.7 —Pipe Section Resource Cycle 73 . . / Egg): 2633153; Assessments . g . crane liner casmg NEED AIR /|nsta|| and check P=0.67 AIR GRIPPER GRIPPER air gripper QADY P=0.33 Adjust air gfipper Figure 3.8 - Air Adaptor Installation on Pipe Section Resource Cycle The jacking system is another leading resource; its cycle is shown in Figure 3.9. The jacking process is the main component of the microtunneling operation. The cycle begins when jacking flame completely retracted and ready to accept a pipe section, this state is called jacking system idle. After a pipe section is setup then the jacking system “jacks” (or pushes) the pipe. After the jacking pipe takes place then the slurry and hydraulic lines are dismantled and jack flames are retracted once again ready to begin another cycle. The jacking system consists of: the jacking flame, one worker who is always inSide the shaft cleaning and observing the jacks, the MTBM and its operator who also controls the jacks, the spoil separation unit. Production unit was defined as jacking system went through one cycle flom retracted status to next retracted status. 74 fipe section setup Jack pipe Jacking system idle on guard rail section /. DIsmantIe cables , SECTION and hoses READY Figure 3.9 -Jacking System Resource Cycle The “Labor A” resource is defined as a one-worker crew. This worker is assigned to various activities as shown in Figure 3.10. This worker does not directly interact with the jacking system cycle since he does not perform any jacking related activity. This worker is involved in the mixing of the lubrication, attachingthe pipe section to the crane and preparing the section for installation. Bring section from /Attach section to storage & install crane liner casing LABOR A - - - IDLE MIX lubrIcatIon /lnstall and Check / , , , air gripper Adjust aIr ngpper Figure 3.10 —Labor A Resource Cycle The next resource is called “Labor B”. Labor B is defined as a two-worker crew with one labor and one technician, who are involved mainly in jacking related activities like setting 75 up the pipe in the shaft, dismantling the slurry and hydraulic lines and lowering the section into the shaft. This crew is also involved in the task of discharging and refilling the desandman (Figure 3.11). The crew members have to work together. {ower section into ape section setup shaft on guard rail Discharge and Dismantle cables refill desandman and hoses Figure 3.11 —Labor B Resource Cycle The lubrication cycle (Figure 3.12), starts with the lubrication in its storage tank. This resource is used to set up the pipe in the jacking flame. It is also required through the entire jacking process until the slurry lines and hydraulic lines are dismantled. After five cycles, the lubrication is consumed and more is needed, so the ingredients (polymer liquid, bentonite powder and water) must be mixed in the mixing tank and then stored. The flow unit is defined as one lubricatiOn mix process is finished and ready for use. 76- The slurry (water based) in the system is a very important resource, as shown in Figure 3.13. Slurry is needed in all phases of the jacking process, flom the setting up of the pipe, / Pipe section setup on guard rail / Mix lubrication Figure 3.12 —Lubrication Resource Cycle JaCk pipe section through the jacking itself until the slurry and hydraulic lines are dismantled. Slurry can be recirculated through the system only a certain number of times, which is a function of the composition of the soil being ,exCavated. The flow unit is one time of discharging the desandman and refilling water for use. WATER READY During the pipe jacking process spoil is removed through the slurry return lines in the 4 refill desandman ipe section setup Jack pipe on guard rail section /Discharge and READY TO DISCHARGE Figure 3.13 —Water Resource Cycle SECTION IN PLACE /Dismantle cables and hoses form of a slurry suspension (Figure 2.7). It is then separated flom the water and dumped 77 into the storage tank before it is loaded into dump trucks for hauling to disposal sites, as depicted in Figure 3.14. Flow unit is the spoil tank is emptied once. SPOIL TANK flpe section setup Jack pipe NOT FULL on guard rail section / Empty spoil tank SPOIL TANK FULL I Figure 3.14 —Spoil Cycle After leading resource cycles have been defined, secondary resources need to be identified. One of them is the supervision provided by Kidoh staff flom Osaka, who is responsible for Checking air gripper installation, pipe section setup on guardrail including laser setup and connection of cables and hoses, desandman operation, and dismantling cables and hoses. Figure 3.15 shows the resource cycle of supervision. One supervisor is asSumed and he must be available at the beginning of each activity which need to be supervised. The supervisor can only present at one activity a time. 78 /lnstall and Check air gripper Discharge and refill desandman / Adjust air gripper Pipe section setup on guard rail /Dismantle cables . and hoses Figure 3.15 — Supervisor Resource Cycle The crane cycle is another secondary resource cycle, as shown in Figure 3.16, the crane returns when pipe section is setup on guardrail, and ready to be attached next pipe section. Flow unit is defined as a cycle that flom attaching pipe to crane idle'completes. . CRANE IDLE / Lift section to position L SECTION READY Figure 3.16 - Crane Resource Cycle -I Crane returns _‘ / Lower section into shaft -\ \ \ SECTION / READY Pipe section setup on guard rail There are other secondary resources not forming independent cycles, such as backhoe, crane, dump trucks, water truck, and the ingredients for the lubrication. Those secondary resources will be included in next section of integrating independent resource cycles into one microtunneling simulation model. 79 3.4 Integration of Independent Resource Cycles The second step in building the model is the integration of the independent resource cycles. When all the flow unit cycles have been identified, they can be integrated at the COMBIS for development of the comprehensive process model. Those COMBIS that appear in different resource cycles will be joints on the comprehensive process model connecting the independent resource cycles. Such a model structure reflects logic nature behind the operation process. For instance, COMBI Pipe Section Setup on Guard Rail appears in eight independent resource cycles. Resources including pipe section, labor B, supervisor, water, lubrication, spoil tank, jacking system, cables, hoses, and laser must be ready before pipe section can be setup on guard rail. Basically we need the following information in order to simulate the actual process: 1. When can a work task be scheduled to start? 2. What resources are necessary for its processing? _3. Time consumed by processing the resource Item 1 and 2 are discussed in this section, which explains the structure and logic of the model. Time consumed by processing the resource will be studied in chapter 4, Statistical Analysis of Observed Duration Data. Figures 3.17 and 3.18 present the complete prototype CYCLONE model for microtunneling operation without consideration of soil impacts. The purpose of this prototype model is for validation of the modeling structure and logics. Alter building and 80 validating this prototype model, enhancements of different soil composition impacts will be included in next section. The complete description of the prototype simulation model elements is shown in Table 3.3 to 3.6. Figure 3.17 —Combination Elements in Prototype Model COMBI elements Element number (Priority) Description 1 Discharge and refill desandman lMix lubrication Disrrrantle cables and hoses Empty spoil tank (desandman) Setup pipe sectiOn on guard rail Lower section into Shaft Adjust air gripper Install and check air gripper 2 3 4 5 6 7 8 9 Attach section to crane Bring section flom storage and install liner casing In order to prioritize activities sharing the same resource, thorough analysis has been conducted to follow the microtunneling practice. In CYCLONE modeling, lower ntunbered COMBI elements receive priority (Halpin et al. 1998). For example, resource Labor A is responsible for five activities in priority of: Mix lubrication, Adjust air gripper, Install and check air gripper, Attach section to crane, and Bring section from storage and install liner casing. Slurry is ranked first because it is the most important among five, without lubrication the operation could be jeopardized and fail. Other four activities are prioritized following a general rule: later positioned activity in the cycle 81 takes higher priority. The logic of the rule is that there is only one situation later and earlier positioned activities fight for the resource: later activity deals with previous pipe section while the early activity deals with next pipe section. For instance, Bring section from storage and install liner casing must happen before Attach section to crane, but they share resource Labor A, which means normally two activities won’t occupy Labor A simultaneously. However, the only possibility comes when Labor A is to attach pipe section to crane, the next section need to be brought and prepared. Obviously, Labor A should attach section to crane first in order to keep the whole operation running and come back to bring more sections and prepare. Thus, if any two of these activities need Labor A at the same time, higher numbered activity has to wait for lower numbered activity finish and release Labor A to idle status. 82 5:825 m:=0:550§2 3:030 05 no.“ 582 mZOAUNrU RESET 45838 5 own—m 358% me ~on 02 ESE unsure . >§EDD mmnEEO N:< \/ .895 .__m . Fwd xooco a __m«mc_L I mwnEEO m=< Dmmz 3 8 owEDOOO I x I/ :o_ Goa mcmno ZOEmOn. mEmmo 5:: Cit ZWJWWWW 2 condom a... 9 8:03 comz< :92: $3905 Wofimww 4 m._.m<.=<>< E0: cozoow warm zOEmOn \ l/ A =\ 22 6:90 €2.anan 3:230 mew—unnaeumz 32030 05 .8.“ $602 ”“2040qu 09382.7, and «Sufi memo: was 338 ozcmEmIL < j och 6:80 0.2 EBm>m mciom... :8 23m :0 9:8 8:03 mark / vzmwg >Qo< e L :m ZOEmOQ \ I / A :x 22 9.90 \ l / A N _ 92 ,’\ l I R Control Crane ‘ (62) Backhoe \\ ,-\‘ Idle '83; ' I' \ SPOIL TANK SPOIL TANK NOT FULL ‘g’ i \\ GEN 4 l I ,l“ ‘ \_ \l ' CON4 I ‘ z‘x‘ / \‘ x \\ / \‘ [/4 \ll/ \II/ 'l\\(/ \\ I KEDKEEAEEAE‘EI \E’lnf’E/f;/\E’iz I ’—\ /_\ x r"\ /"\ I 4 SECTION IN PLACE \ r, Ilsmantle cables and hoses /‘\ KI}, \ Jack pipe section SECTION IN PLACE ,-,‘ ,-\‘\_, \l l ‘57, \Ca I / SECTION IN PLACE Discharge 8. refill desandman DISCHARGE Figure 3.25 ~ CYCLONE Model Considering Soil Types (Continued) 4 STATISTICAL ANALYSIS OF OBSERVED DURATION DATA In order to conduct simulations in WebCYCLONE with built model, task duration data obtained flom the candidate project need to be analyzed. Each task element should be accompanied with a duration set number that defines the duration category of the task and the population flom which the duration of the task will be sampled. MicroCYCLONE / WebCYCLONE recognizes two categories of tasks based on duration-stationary tasks and nonstationary tasks. From data collected during the operation, only duration- stationary tasks are defined. Figure 4.1 illustrates the time consuming process of the simulation program and the works presented in Chapter 3 and 4. Check if work task can be MODEL processed (logical and <:7 DEVELOPMENT(logics resource constraints are met) and resource constraints) No Yes , , STATISTICAL Get trme required to ANALYSIS ON ”“655 this “‘5“ DURATION DATA (finding durations) Calculate the time taken to complete this task Update the resource/ entity allocation Advance time Figure 4.1 - Time Consuming of the WebCYCLONE Simulation Program 94 4.1 Data Collected from the Project Appendix B shows the duration data collected flom the candidate project. 24 sets of data are recorded for activities: 0 Durations of COMBI (node 1) Discharge and Refill Desandman, 0 COMBI (node 3) Dismantle Cables and Hoses, 0 COMBI (node 5) Pipe Section Setup on Guard Rail, 0 COMBI (node 7) Adjust Air Gripper, 0 COMBI (node 8) Install and Check Air Gripper, 0 COMBI (node 10) Bring Section flom Storage and Install Liner Casing, 0 And NORMAL (42) Jack Pipe Section. The distributions of recorded activity durations will be found using goodness-of-fit testing on CDFS (Cumulative Density Function). Activity duration of jacking pipe section will be further analyzed to find distributions in four types of soil conditions. All the analyses are done with R190. R, which is a flee version of S-plus and can be downloaded flom http://www.r-project.org/. Non-record activity durations such as crane returning, attaching pipe to crane are not critical in the project, and are assumed as having same distributions as other recorded slurry microtunneling project (Nido et al. 1999). 95 4.2 Introduction to Statistical Distributions in WebCYCLONE The Statistical distributions for the duration time random variables recognized by the input module of WebCYCLONE program are: 0 Exponential distribution, 0 Triangular distribution, 0 Uniform distribution, 0 Log normal distribution, 0 And Beta distribution. 1. Exponential distribution: “13(6) The probability density function (PDF) of the exponential distribution “13(6) is f(x) :16“, x > 0, 6 > 0 I9 , where 9 is the scale parameter. Both the mean and the standard deviation of “13(9) equal to ‘9 . The cumulative distribution function (cdf) is the probability that the variable takes a value less than or equal to x. That is F (x) : Pr(X S x). Therefore, the cdf of exponential distribution CXp(9) iSF(x) = l—e’x’g, x > O, 6 > 0. The exponential pdf is always convex, and is stretched to the right as 9 increases in value. The following in Figure 4.2 are the plots of the probability density fimctions ofexp(0.5), exp(l) and exp(2)_ 96 PDF of exp Q P 9=0.5 ‘0 6— '¢ 6 \1 6:2 0 d — I I I I I I I O 1 2 3 4 5 6 Figure 4.2 -PDFs of Exponential Distribution (Shao, 2003) 2. Triangular distribution: Triangular-(a, 9,13) The probability density function (pdf) of the Triangular distribution Triangular(a, 6’ b) is r 2(x-a) a0, 0'>O, 6 where is the location parameter, A is the scale parameter, and 0' is the shape parameter. The case where ,u = O and ’1 =1 is called standard lognormal distribution. . 2 0,2 The mean of lognormal(6,l,o* ) equals t09+3~305 . The standard deviation of lognormal(6,/1,0’2) equals to 1W6"2 (6"2 -1). The lognormal distribution is a distribution skewed to the right, and the degree of skewness increases as 0' increases, for a given (9 , A ). Therefore, lognormal distribution is used to model continuous random quantities when the distribution is believed to be skewed, such as certain income and lifetime variables. The following in Figure 4.5 is the plot of the standard lognormal probability density function for four values of 0' . 100 PDF of lognonnaKO, 1 , 0.2) PDF of lognorrnaKO, 1, 0.5) a) a o m In 0 — 8 ~ 3 — N _ q 0 0 ° .. C -‘ l l l l T l C l l l l l 0.5 1.0 1.5 2.0 2.5 3.0 0 2 4 6 8 X X PDF of lognorrnal(0, 1, 1.5) PDF of Iognormal(0, 1, 6) a - 8 — J .— r 3‘ r 3 ‘ 8 — 8 ~ _. .4 O O o l l l l l l l C d l l l T l l. 0 2 4 6 a 10 12 0 5 10 15 20 25 X X Figure 4.5 -PDFs of Lognormal Distributions 5. Beta distribution: '6 (a, b, c, d) The probability density function (pdf) of the beta distribution ,8(a, b’ c’ d) is x-a b—a 1 .F(c+d) (1_x—a b—a r(c)r(d) '17—? )c- f (X) = )‘H( a_<_x_<_b; a>0, b>0, c>0, d>O, where c and d are the shape parameters, a and b are the lower and upper bounds, rm i respectively of the distribution. Here 5 the gamma function, which is defined as I‘(x) = It“‘e”dt ° . If x is an integer n = 1, 2, 3, ..., then F(n)=(n—l)(n—2)(n—3)---1=(n—l)!. 101 The case where a = 0 and b = ,1 is called the standard beta distribution. The uniform distribution U(a,b) is a special case of beta distribution when 0 = d = 1. c a + (b — a) The mean of 16(0’ 1” C’ ‘1) equals to C + d , and its standard deviation equals to (b—a)‘/ 2cd (c+d) (c+d+l). The shape of the beta distribution is quite variable depending on the values of the parameters. As illustrated by the plot below, when C <1 and d <1, the distribution is U- shaped; when the two parameters are equal, the distribution is symmetrical, and a special case is uniform distribution when; if C < d , then the distribution is skewed to the left; if C > d , then the distribution is skewed to the right. The beta distribution is often used to estimate the proportion of defective items in a shipment or model time to complete a task. Figure 4.6 shows the plot of the beta probability density function for different values. 102 PM PM PDF of beta(0, 1, 0.75, 0.75) ' PDF of beta(0, 1, 2, 2) ‘7. _ 8 - 0 ~ ._ 5 8 CL (0 j 0' $2 — q N .._ _J o' r o I I F I I I I I I I I I 0.0 0.2 0.4 0.6 0.8 1.0 0.0 0.2 0.4 0.6 0.8 1.0 x x PDF of beta(0, 1, 2, 5) PDF of beta(0, 1, 5, 2) o o N _ N T —I g d O. .0 0- q _ ‘- s- —I -i o 0. .. 0' I I I I I o I I I T I 0.0 0.2 0.4 0.6 0.8 0.2 0.4 0.6 0.8 1.0 x x Figure 4.6 — PDFS of Beta Distributions 4.3 Kolmogorov-Smirnov Goodness-of-Fit Test To decide the distributions for the duration time random variables, we follow the below steps. First we assume a pre-specifred distribution based on the statistical properties, for instance the histogram plot, of the duration data. Then we estimate the distribution parameters from the data using the Maximum Likelihood Estimation (MLE) method. Next we test the assumed distribution using Kolmogorov-Simimov test. If the assumed distribution is rejected, we will choose another distribution, and repeat the above steps until we find an appropriate distribution. 103 The Kolmogorov-Smirnov test was developed by Kolmogorov and Smirnov in the 19305 to to determine if a sample comes from a given hypothesized distribution. The Kolmogorov-Smimov test is based on the empirical cumulative distribution function (ECDF). Given n ordered data points x“) S x“) S. H S x‘") , the ECDF is defined as [0, x < x“) 1 < “r x“) - x < M) n F" (x) = < i n (I, xm S x The Kolmogorov-Smirnov test statistic D is defined as the maximum difference between the empirical distribution function and the theoretical cumulative distribution function (cdf) of the hypothesized distribution. The hypothesized distribution is rejected when D is large enough, or equivalently when the p-value is smaller than the significance level a , which is commonly chosen as 0.05. 4.4 Distributions Suggested for the Duration Time Random Variables Table 4.1 summarizes the distributions determined, the correspondent estimations of parameter, the test statistics D and the p-values of the Kolmogorov—Smimov test. 104 Table 4.1—Distributions, Parameters, Test Statistics, and P-values D-statistic of P-value of Distribution Variables Parameters Kolmogorov- Kolmogorov- Comment Determined Smirnov test Smirnov test Lognormal ‘ NOR 42 log normal(6, 2., 0'2) (8, 30.177, 0.0917 0.988 GOOD 0.756) BETA (Par1)(Par2) Beta(12, 102, OK NOR 42 0.159 0.579 (Par3) (Par4) 0.854, 1.403) (suggest) , Triangular(12 OK NOR 42 Trrangular(a, 6, b) 0.168 0.507 , 31, 92) , (suggest) BETA (28, BETA (Parl) (Par2) Good COMBI 5 (P 3) (P 4) 80, 0.761, 0.1129 0.920 ( ) ar ar su est 1.841) g . Lognormal COMBI 5 log normal (6, 11, 0'2) (25, 14.062, 0.1021 0.964 Good 0.783) Lognormal COMBI 2 10 log normal(6, 2., a ) (0, 6.838, 0.1615 0.559 Good ' 0.377) COMBI BETA (Par1)(Par2) Beta (3, 23, Worse than 0.2059 0.261 10 (Par3) (Par4) 1.481, 5.353) Triangular COMBI , Trian ar 2, OK Trrangular(a, 19, b) gul ( 0.1891 0.357 10 5, 15) (suggest) Lognormal COMB13 log normal(6, 2., 0'2) (5, 5.537, 0.1226 0.880 Good 0.650) BETA (Par1)(Par2) BETA (7, 33, Good COMBI 3 0.1304 0.8288 (Par3) (Par4) 0.643, 3.020) (suggest) , Triangular (3, OK (worse COMBI 3 Trrangular(a, 6, b) 0.1696 0.5228 7, 27) than beta) Figures 4.7 to 4.10 show the CDFS of the determined distributions for NORMAL 42, COMBI 5, COMBI 10, COMBI 3 respectively. 105 Foo ' F(X) Normal 42 Jack Pipe Section, Beta(12, 102, 0.854, 1.403) ,_/_°—°_ .T /' / 7/ / ,4“— / /°_.._ 0:0 0:2 0:4 0:6 0:8 Studentized x Figure 4.7 —CDF of NORMAL 42 Jack Pipe Section COMBI 5 Pipe Section Install on Guardrail, beta(28, 80, 0.761, 1.841) 1.0 1.0 0.6 0.4 0.2 0.0 —--------.-- 1 1 0.6 0.8 l l 0.2 0.4 Studentized x Figure 4.8 —CDF of COMBI 5 Install Pipe Section on Guardrail 106 COMBI 10 Bring Section 8. Install Liner Casing, Triangular(2, 5, 15) q _ - «é _ o "D. - o 3? / u": ‘12 _ o N. _ o 0. _ - o 1 l l I F l - l 2 4 6 8 10 12 14 16 x Figure 4.9 — GDP of COMBI 10 Bring Section and Install Liner Casing COMBI 3 Dismantle Cables 8: Hoses! Retrack Jack Frame, beta(7, 33, 0.643, 3.020) 0 - / 0——°_ / (0 o “ 72/ co _ /i_ o 2 .._ 3 11. V. - o N o' - 0. o l l l l l 0.0 0.2 0.4 0.6 0.8 Studentized x Figure 4.10 -CDF of COMBI 3 Dismantle Cables & Hoses/ Retrack Jack Frame Activity duration distributions used in the simulation are shown in Table 4.2. It was discovered that lognormal distribution was not implemented in WebCYCLONE. Thus, I 107 any statistically suggested lognormal distribution was replaced by the second good distribution in the simulation as shown in Table 4.1. Table 4.2 —Duration Information Activity number Description Probabilistic distribution 1 Discharge and refill desandman TRI (10,12,15) 2 Mix lubrication TRI (25,30,35) 3 Dismantle cables and hoses BETA (7,33,0.643,3.020) 4 Empty spoil tank TRI (20,30,35) 5 Setup pipe section on guard rail BETA (28,80,0.76l,1.84l) 6 Lower section into shafi UNI (1,2) 7 Adjust air gripper UNI (10,15) 8 Install and check air gripper UNI (10, 15) 9 Attach section to crane DET (2) 10 Bring section from storage and install liner casing TRI (2,5,15) 40 Lift section to position DET (1) 41 Crane returns DET (2) 42 Jack pipe section BETA (12, 102, 0.854, 1.403) 43 Dummy DET (0) 4.5 Compare the Duration Time of Jacking Pipe Section in Different Soil Conditions In this section, the differences between the jacking pipe activity durations in four types of soils are compared. When microtunneling in different types of soils, the major productivity difference comes from the activity COMBI 42 Jack Pipe Section, which is the direct interaction between soil composition and microtunneling productivity. If the differences of durations are significant, then building model with different soils 108 enhancement is a valid approach. In addition, distributions of jacking pipe sections in different soils need to be found. Table 4.3 shows the sample means and sample standard deviations for each soil. From Table 4.3, we see that the mean jacking time in clay is the largest, which is mainly due to the incompatibility of slurry system and clay soil; the next largest is clayey gravel; silt and sand takes the shortest times. Table 4.3 — Sample Means and Standard Deviations of Jacking Durations in Different Soils Soils Sample Mean Sample Standard Deviation Clay 70.67 22.89 Silt ‘ 29.167 8.40 Sand 26.83 . 10.87 Clayey Gravel 57.5 17.56 To test further whether the differences are significant, we perform the pairwise comparisons between the pushing times on four different soils using Welch’s two sample t-test where equal variances are not assumed, and Wilcoxon rank sum test. The t-test is a popular test used to compare the means of two populations, and it assumes that the two populations are both normal distributed. The Wilxocon rank sum test is a nonparametric version of the two sample t-test, and it tests the equality of the medians of two populations. The Wilxocon rank sum test is very commonly used when the sample size is very small or when the normality assumption is violated, which is the case of this study. Table 4.4 and 4.5 summarize the pairwise comparison results from t-test and Wilcoxon rank tests, respectively. Both t-test and Wilcoxon rank tests give the similar results. 109 There is no statistical significant difference between clay and clayey gravel, neither between silt and sand. The mean jacking durations between the rest 4 pairs: clay and silt, clay and sand, clayey gravel and silt, clayey gravel and sand are significantly different. More specifically, the jacking time in clay and clayey gravel are significantly longer than those on silt and sand. Table 4.4 — Pairwise comparison results from two sample t-test Pair Test statistic p-value Significant Clay vs Silt 4.1694 0.005243 Yes Clay vs Sand 4.2374 0.003676 Yes Clay vs Clayey gravel 1.118 0.2914 No Silt vs Sand 0.416 0.6867 No Silt vs Clayey gravel -3.5656 0.008783 Yes Sand vs Clayey gravel ~3.6375 0.00616 Yes Table 4.5 — Pairwise comparison results from Wilcoxon rank test Pair Test statistic p-value Significant Clay vs Silt 34 0.01291 Yes Clay vs Sand 34 0.008658 Yes Clay vs Clayey gravel 25 0.3095 No Silt vs Sand 20.5 0.7479 No Silt vs Clayey gravel 0.5 0.0063 Yes Sand vs Clayey gravel 0.5 0.006392 Yes found as shown in Table 4.6. Using the Kolmogorov-Smirnov test, jacking duration distributions in different soils are Table 4.6 —Jacking Pipe Duration Distributions in Different Soils Activity Soil Condition Probabilistic distribution Jack PipeSection Clay BETA (19, 92, 0.781, 0.323) ‘ Jack Pipe Section Silt BETA (17, 51, 0.989, 1.775) Jack Pipe Section Sand BETA (12, 46, 0.613, 0.793) Jack Pipe Section Clayey Gravel BETA (26, 88, 1.075, 1.041) 110 5 SIMULATION RESULTS AND DISCUSSION In chapter 3, the prototype model and soil impacts enhanced model of microtunneling have been developed. In addition, chapter 4 studied the activity duration data in both models. Combining previous work, this chapter presents simulation results from two models subsequently. Firstly, simulations with the prototype model are conducted and the validation of the prototype model is discussed with simulation results. Afier the validation, considerations of different soil compositions are added into the model, which was presented in chapter 3 (section 3.7). Simulations have been conducted again with enhanced model. Simulation results from enhanced model are validated and conducted sensitivity analysis to optimize the productivity. Finally in this chapter, different soil composition impacts on microtunneling productivity are studied. 5.1 Simulation Results with Prototype CYCLONE Model A total of 30 simulation runs were performed with the prototype CYCLONE microtunneling model. Appendix C has the coding for prototype model with duration data distribution discussed in chapter 4. Appendix E presents the full set of data from simulation results, which) includes productivity information for each cycle, duration statistics for CYCLONE active elements, idling percentage and waiting time statistics for CYCLONE passive elements, and elements trace information. For validation purpose, the productivities generated from the simulations are studied thoroughly. Other results as resource idling and limitations will be analyzed with soil enhanced model. Table 5.1 and 5.2 show the productivities obtained from the simulation. 111 .4-..” Table 5.1 —Simulated Microtunneling Process Productivity Information by Cycle 1 Mflfl- EiSirn. Time (Accumulative) Cycle No iPer “3:224:11: (min.) Productivity Per Time Unit 1 160.4 41 1 41 160.4 1 0.006234 ' 280. 9 1 2 ' 140.45 $444444 0.007120 4 44434347144 44 4 ; 3 112 3666667 1444 0.008899 44 4444434946184 4 :4 4 4444444 49494424444 4,1444 44404041068044" 4 629.7 44444 44 5 123 49444 44444441 0.007940 751.5 44 4144446 125.25 1 0.007984 898.1 {44447444 4444444 441248.434 4444444441 0.007794 967.9 4444 441 8 120.9875 :4 0.008265 1066.1 9 1184555556 14 0.008442 1195.2 4 4 i 4414044 119.52 414444 4 0.008367 1271.2 44; 11 115.5636364 ‘1' 0.008653 1343.9 4' 4E4 12 4 4 111. 9916667 1 0.008929 4 4 444144425442 4 4 4 ‘ 13 10963074649424 4474 4 0.009121 4444 41496.9 441444414444 106.9214286 444! 0.009353 1550.4 44 14544 444444 103.36 {4444 0.009675 44 4 4 1607.3 4 444 444164 4 10045625 1444 0.009955 1706.7 44 4 Q 4147444 4444 100.3941176 1 0.009961 18025 4 444 4418 44 1001388889 1 0.009986 4444149346404 44 414441494 4 101.8947368 4441' 0.009814 2031.1 4 20 .3 101.555 1 0.009847 2199.3 21 1. 104.7285714 4) 0.009549 {4 2374.4 4 442244 107.9272727 '1' 0.009265 (4 2501.4 44;} 23 4 108.7565217 14 44 4 0.009195 1 2629.1 4 4 42444 4 109.5458333 1 0.009129 14 2715.54 4 4 4144442344 4144 108.62 414 0.009206 1' 2818.7 1 26 ‘ 108.4115385 1 0.009224 2908.8 ; 247 4444‘ 107.7333333 1 0.009282 1 3013.0 4 444 4, 44428 1 107.6071429 1 0.009293 1' 444 3170.4 4; 29 109.3241379 0.009147 1 ‘4 30 107.8466667 4444 ‘ 0.009272 .- m ...,...“ .-m~. -_~ _ Table 5.2 —Overall Simulated Microtunneling Process Productivity Information [Total Sim. Time Unit C cle No Productivity Productivity (in minute) , y (per pipe section) (per time unit) 3 3235.4 ’ 30 144107 867 0 009272409316360385 ' 112 Figure 5.1 shows the change of productivities in thirty cycles. A pattern can be easily observed on the plot. The duration time decreasing steeply on the initial four pipe sections reflects the preparation work has to be done at the beginning stage of the project. Moreover, it can be explained as following productivity learning curve (Abdelhamid 2004), which predicts productivity will increase as units being constructed, and the increase rate is slowing down to zero eventually. There always is a limit of productivity increase through learning. Abnormal pattern appears after pipe section number four that cycle duration climbs suddenly. This abrupt change can only be explained as resource limitation. Rearranging resource might release this bottleneck. With the soil-enhanced model, resources will be studied to find the sensitive ones (bottlenecks) and different alternative resource allocations will be simulated to optimize the operation. The rest parts of the plot in Figure 5.1 show the same pattern, afier a short platform of pipe section 6, productivities increase from pipe 7 to 16, following exactly the learning curve. Then another platform starts from section 16 to 20, which could reflect the bottom of productivity improving. Duration jumps from section 20 to 24, not as sharp as the previous but still indicates some resource arrangements need to be adjusted. A platform from section 25 to 30 finishes the curve. Overall, the productivity simulation results are in reasonable patterns. The validation of the prototype model with these results will be discussed in next section. 113 170 165 160 155 150 3 145 ‘5 140 .E 135 c 130 4; 125 E 120 fi 115 110 105 100 95 SI) 12 3 4 5 6 7 8 9101112131415161718192021222324252627282930 Smlation0/cles Figure 5.1 -Simulation Cycle Durations with Prototype Model 5.2 Validation of the Prototype Simulation Model In Appendix B, the actual production measured in the field was recorded as follows: Table 5.3 -Actual Cycle Time Measured in the Field Average cycle time for installation of an 8-ft section of PVC pipe in: Clay 169 min. Silt 97 min. Sand 91 min. Clayey Gravel 130 min. For a soil composition of 25% clay, 25% silt, 25% sand, and 25% clayey gravel, the average duration for installing one 8 feet pipe section is 121.75 minutes. Consulting with expert, it was found that the production rates of the project for jacking pipe were within acceptable range of a microtunneling project for the specified type of soil (Najafi 1993). However, the average rate of production for the candidate project was 8.5 meter (28 feet) 114 per day, while the reported rates for typical microtunneling projects are about 12 to 15 meters (36 to 45 feet) per day (Kramer et a1. 1992). The main reason for overall- production being lower than a standard microtunneling project is due to the experimental nature of the candidate project (Najafi 1993). The averaged simulated productivity from 30 cycles is 13% higher than the productivity observed in the field, which is clearly in a reasonable range of typical microtunneling project. Therefore, the logic and structure of the prototype model and accuracy of input data have been validated. Afier verifying the simulation results with actual data the model can be enhanced with soil compositions and used for experimentation. Using a soil composition of equal portions of clay, silt, sand, and clayey gravel, the simulations are conducted to identify the resource bottlenecks. Alternative resource arrangements are simulated to find the optimized productivity of the operation. The enhanced model is also modified for testing the impacts of different soil compositions on productivity, which is discussed in Section 5.5. 5.3 Simulation Results with Enhanced Model Considering Soil Composition Changes A total of 30 simulation runs were performed with the soil enhanced CYCLONE microtunneling model. Appendix D has the coding for soil enhanced model with duration data distribution discussed in chapter 4. Appendix F presents the full set of data from simulation results, which includes productivity information for each cycle, duration statistics for CYCLONE active elements, idling percentage and waiting time statistics for 115 CYCLONE passive elements, and elements trace information. Table 5.4 and 5.5 show the productivities obtained from the simulation. Sim. Time (Accumulative) Duration 44 1Cy4cle No ’Per Pipe Section (min. ) Table 5.4 -Simulated Microtunneling Process Productivity Information by Cycle Productivity Per Time Unit 155.7 1 1 . 303.5 441 6 550.5 702.9 4831.644 4 934.6 5 —. ._._.., . .2-. -.._. . ., . . 1 . : 1 3 1 1042.2 444141444642 44 444 1246.1 44441345. 6 1403.1--...-,_. .... 1482.3 1 1 1 1 1 1 1 I 1616.2 44444441464941.3444 1762 8 4 1887.1 . 441980. 04 4 4 2129.9 2230. 7 2372 3 2546.8 2679.9 2822442 4 1; 1 l l 1 134N1— l l l 1 l 155. 739 4 151.7681 147.2104 '4 137.6084 0.006421 0 006589 ' 44400046793444 0.007267 140.5877 14386001 4 0.007113 0.0072154 4 4 Wo oo.’\150~4u~34>1 133.5113 0.007490 130.2762 12744344561 0.007676 4 040074854244444 ' 1 ~ ~ ~ 1:: 124.6106 122.3242 4 44116.9414844 __ . 114.0251 115.4468 4411247542344 110.1686 111.0001 ' 4140944998494 4 0.008025 44440004817454 4 0.008553 4 0.008770 0.008662 WM“ -W~-~ .am... ..._ - -_. --m. ._.- -.«-..............J... __2 ....__.__... ... ..., w ...,".-. .--, m. 40. 04088694 '4 " 0.009077 112.0951 111.5325 114249468844 4 0.008921 0.008966 0008852 1 15.7675 1 16.5094 44411745917444 0.008638 -,_.-. -._... _‘——-~v— 0. 00845483444 440. 0085044 2926.7 3063.1 44434175484444 1 17.0686 117.8134 117 464194 3304.1 3456.5 4 ' 4434544144344 118.008 119.1895 44141840498444 4 0.008542 0.008488 40.008502 4 4 ’ 0.008474 44404004484390 4 0.0084714 4' 116 Table 5.5 —Overall Simulated Microtunneling Process Productivity Information 1Total Sim. Time Unit 14C cle No 4 Productivity 1 Productivity (in minute) 1 y ' (per pipe section) 1 (per time unit) 1 1 3541.3 41 30 1 1 18.043 10.008471404967265655 The averaged duration time of 118.043 minutes is longer than simulation result from the prototype model of 107.867 minutes by 9.4% due to the modified model structure and input jacking duration data. However, it is closer to the average of actual measured durations in the field, 121.45 minutes. Only 3% difference exists between the soil enhanced simulation results and actual measured data, which indicates an improved accuracy of modeling. Figures 5.2 to 5.16 show the trace information for QUEUE elements, where resource units wait until the successive activity starts. The trace information for all QUEUE elements is recorded in Appendix F. 35 28 2. “a M 4E 7 E . 47% 3323.5 Figure 5.2 —Trace Chart for QUEUE-1 1 Section on Storage 117 4||||11|ll llll 3458.5 Figure 5.3 -Tracc Chart for QUEUE-12 Position Available 3458.5 Figure 5.4 -Trace Chart for QUEUE-13 Labor A Idle Figure 5.5 -Trace Chart for QUEUE-14 Supervisor Idle 118 10 Figure 5.6 --Trace Chart for QUEUE-15 Air Gripper Ready Figure 5.7 ——Trace Chart for QUEUE-16 Crane Idle Figure 5.8 —Trace Chart for QUEUE-17 Control Crane 119 3491.2 3541.3 3541.3 Figure 5.9 —Trace Chart for QUEUE-18 Labor B Idle 3319.1 Figure 5.10 -Trace Chart for QUEUE-19 Truck Idle 3319.1 120 Figure 5.11 -Trace Chart for QUEUE-20 Backhoe Idle ll , 3321.5 Figure 5.12 —Trace Chart for QUEUE-22 Bentonite Ready ' 4 ' 4 ‘ 4 f ' 3541.3 Figure 5.13 -Trace Chart for QUEUE-23 Jacking System Idle 3355.5 121 Figure 5.14 -Trace Chart for QUEUE-25 Need Air Gripper 2747.9 Figure 5.15 —Trace Chart for QUEUE-26 Air Gripper Need Adjust ll llHlllllHHl l1 |JJ| Figure 5.16 —Trace Chart for QUEUE-28 Position Occupied 3456.5 As shown in Figure 5.2, thirty pipe sections were brought fi'om storage and prepared with different durations. The overall pattern is linear with reasonable variations. From Figure 5.3 and 5 .16, we can see there is less waiting time in QUEUE 12 than QUEUE 28, which could be explained as attaching section to crane takes long time to put next pipe section on wait. While on the contrary, the only position on the crane is filled immediately when it is emptied. The limitation resources of attaching section to crane activity are cranes and Labor A, which need sensitivity analysis. From Figure 5.4, 5 .5 and 5.9, we found Labor A, Supervisor and Labor B are idling very frequently, which is proved in Appendix F, 122 where Labor A has 80.87% idling time, Labor B and supervisor has 50.43% and 47.81% idling time, respectively. Apparently, they are not bottleneck resources compared with crane in Figure 5.8 with 3.93% idle time. However, in sensitivity analysis of next section, when crane number is added, it may trigger labor shortage. For air gripper installation, in Figure 5.14, when the pipe section need air gripper, only in 5.1% of the time it need to wait; in Figure 5.15, when air gripper need adjust, 100% of the time adjustment is in time; in Figure 5.6, air gripper is in 97.6% of the time ready when pipe section need to be attached to crane. Conclusion can be drawn that air gripper installation is efficient and create no delays for the operation. Truck, backhoe, and bentonite are three resources that follow the same pattern, because of the assumption made in model development. Every four times of jacking pipe sections activate the truck, backhoe, and bentonite preparation once. These three resources are idling for 88.17% of the time in microtunneling operation, which have no effect on delaying the productivity. In Figure 5.13, the jacking system is regarded busy. Only in 8.93% of the time, it is idling. This may indicate that jacking system is one of the limiting factors. Jacking system is the resource with one of the highest utilization rate. By changing the Microtunnel Boring Machine cutting head design to more appropriate, production can be 4 increased. This change can be reflected in the model by changing the jacking pipe section 123 activity duration. The optimization of MTBM with the soil conditions will increase the productivity. 5.4 Sensitivity Analysis In this section, the numbers of crane and labor crews will be analyzed as discussed in the previous section. Different combinations are simulated to find the optimization plan. As Shown in Table 5.6 and 5.7, all combinations of one to two Cranes, one to three Labor A crews, one to three Labor B crews, and one to three Supervisors have been simulated. Due to the space limitation on the site, no more than two cranes have been simulated. The highest productivity appears with one Labor A crew, three Labor B crews, two Supervisors, and two cranes. The second highest plan is to have three Labor A crews and three Labor B crews, one Supervisor, and two cranes. The third highest plan is to have three Labor A crews, two Supervisors, one crane and one Labor B crew. The productivity of the second and third plans are both very close to the first plan. The fourth highest plan is to add two Supervisors to the original. This indicates the supervisor is one of the bottleneck resources, who is responsible for too many activities. The maximum productivity plans do not consider cost factor. Therefore, it can not be concluded that which one is the optimized. By adding one Labor A crew, one Labor B crew, one Supervisor, or one Crane to the system, production improves. Coincidently, the productivity improvements due to adding one Labor A crew or one Labor B crew are the same. When adding both to two or three, the productivity slightly decreases. Labor A and B crews reach the limitation of improving productivity when used without adding other resources. When jointly used 124 with one new crane, the Labor A and B crews contribute more to productivity improvement. The productivity improvements due to adding one supervisor or one crane are the same, which are higher than adding One labor crew. Both of them are bottlenecks of the original operation. Consideration of cost factor should be taken to judge which plan is more feasible. Figure 5.17 —Sensitivity Analysis Results Resource Information 11 or # of 1 LABOR' SUPERVISOR' at LABOR at SUPERVISOR A IDLE IDLE .2.-.3 M01 1 # of CRANE' 131 CRANE # of CRANE CONTROL SIGNAL at CONTROL CRANE Productivity Information #of 1LABOR'1 at LABOR; B IDLE 1 (Section/ min) Installation 1 Productivity Duration Per Per Unit Time Pipe Section Time (min) 1 l l 1 1 0.0101 4440200947444 4 44103 0928 0.0092 108.6957 1 1 i 1 . i I i ‘1 I ‘ 1 . 1 ; .21 -2....” 2......“ w,- Wfi w... 1 1 1 1 1 1 0. 0092 1.2--222- 0.040494044444 41141414144141 108.6957 9.... 1 1 “...,...“ l 1 1 1 ._. .— ~11» 1» 1.33141» 1» who N N1N N twin: 1 ‘ N N Ngu— — I-‘i 2.22.} 2.... 1 1 0.0091 1 IDLE 1 1141 1111 1444444 44414444444444 4440 0086 441 141642791 444 14 1 1 1 1 1 1 1 0.0091 109.8901 1 41 41 144441 4144 4441 4f; 0.0093 107.5269 1 1444 1 1 2-1-2.2. 14 2 000940 14141411114 1 1 1 1 14 2 1 2 1 0.0092. 108.6957 1 1441 44 4 4 12444 4441 2 1 0.0092 108.6957 1-.--- _ _ 1 1 1 1 - 4000904 11111114 1 . 1 1 1 0.0093 107.5269 1 44 1444144444441 1 41 4 1 0.0091 4 109.8901 1 - _ -_ 1 2‘ .2-2 2;.- 404404090444 1141.44411414144444 1 1 2 1 2 ‘4 ; 0.0087 114.9425 1 2 --1 2 222. 1 -14 1 14 1 109.8901 1 111.1111 109.8901 1 r ; 5 1 \ 1 . 14 ( 1 -W -u—aw. Mae—2] W. w. . 1 125 111.1111 117.6471 ..—.. .‘ -_-—..-.~_....4 Figure 5.187 (cont’d) _~.-. “0 Productivity Information ..-.2.--.--.--.2.-22222._ 2. 4414 2 2 Time Duration 1 44 Resource Information 2 .# ofC E44 #of CONTROL # f #of 1 ° SUPERVIS # of 1LABOR' at LABOR A SUPERVIS IDLE OR‘ at C atCRANE OR IDLE 1 IDLE '1-1 m-.. 1 2444 NN4 .1 1 1 1 1 1 1 1 1 1 - 1 4 ‘1 1 1 . I m... -‘-‘-1 w.“ ...,.— -ml .32.... i 1 1 1 1 1 .-3 ...,-1 1 1 1 1 SIGNAL at CONTROL -..,-2.1 CRANE 1 1 1 1 1 1 1 1 1 1 1 IDLE 1 L ABOR' at 1 Productivity LABOR B ' Per Unlt TIme (Section! min) 1 Per Pipe Section Installation (min) 44441031263244 4 1 1 1 1 1 1 19.—1 1 1 1 1 1 1 104.1667 1 116. 2791 4 4 116. 27491 111.1111 1 111.1111 107.5269 1 1 1 1 . 1 i 5 . i 3 1 N11» 191-— -- r—{N1 1 1 1 1 1 1 1 1 1 1 1 1 109.8901 14162791 41062383444444 1 1 1 1- . A»... 1 u... «0.. ..~.... .2 __ u 1 I N 1915.111»: ~11» N ~1~1 1 1 1 1 1 1 1.: 111 1 1 1 1 1 1 ”...,.-.2‘ 1 105.2632 "v-..- 107. 5269 4 104. 1667 1 1 1 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1 116.2791 --§1»§1» waiw W1N1NEN1N 1» 165—1.— 1 .1 : 1'1: -. 1 4 : 1 . y z . 1 7 1‘ ; “...,... 44444—41 .w— u... -2.. ...,.-. ..M». ...... . ‘ 3 1 3 ‘ . 1 1 1 i : 1 1 1 ; . i 1' i , 1 2 1 L»1M§N N1N1 1 1 1 1 1 1 1 1 1 1 I h~wv~l I 1 b.) 1 1 1 1 1 1 6911» en”... ..2 ..2‘ - 2.-.. . _.. .- .21.... .2.. -2... 1 1 . 1 1 1 l . | I . . z 1 1 e s 1 ‘r 1 ‘. 1 - _1 1 1 2 I 1 4 :4 1 1 . M. 1 ”—1 -4.“ M». m m.— mp...‘ .m...) ”1 m1 M...» ””441 ..———-—‘_ M w...‘ ”.1 ——o~—- ... *1 .m.‘ 1 ‘ . 1 _ : : 1 1 ; 1 .j -t ‘; ' s 1 1 . 1 1 1 1 .1 . : 1 1 1--=U)1 a 1 1 1 ...,»! 2...... ., -— W! -_.. ~v~_ . ”‘1‘ 1 .1 1 1 1 1 1 -' 1 I 1 ‘ 1 1 1 ~ ~ 1 H 1 _ fl ‘ 1 .‘ fl . 1 1 109.8901 106.383 N ~11» N 1—1» N ~3w§~ --1» N --§L».; 1 1 1 . .. ...,-.. mW—WW 1 1 ’.--2 1 1 1 1 1 112.3596 44116. 2791 4 108.6957 126 444443444444 4 444 44442444441444444442444444414444442444444E 0.0093 ,44 107.5269 ;4 3 2 1 2 1 3 4 0.0100 1 ' 100 2-3.-- -4 442 - 4144 1 1 - 1.. .2- 1 40.040949444441444 414014 0414041444444 1 3 1 2 1 14444 1 1 42444 44 4 0.0092 14 108.6957 1 3 ; 2 . 1 1 1 1 3 0.0091 1444 109.8901 4 34 4 41 24 2 44144 4 44424444 11' 40.400874 4.4 414141492425 4 3 1 2 2 1 2 1444442 0.0092 1 108.6957 14444434444414 442 2 1 2 1 3 0.0091 1 109.8901 14 W313 2 4414 2-1-22-212 11 0.0095 105.2632 1 3 414 3 1 1 1 1 2 4 0.0093 1 107.5269 ; 3 414 3 1 4444144 41444444441444 3 0.0095 44444441052632 144 3 13- 2 2.-.! - 25-2- .-2.12-----.1. - - 40140093 1414671.45424594444444 1444 3 1 3 2 1 1 2 441 2 4 4 44014109474444 1444 144034.404494248444 444 1 3 1444 3 2 1444444244444414444444344444 4 4 40404049424441 44104869457444 5.5 Impacts of Different Soil Conditions Afier analyzing the resource limitations, productivity changes in the operation due to different soil composition are introduced as shown in Figure 5.19. The soil compositions have been modified from 25% of each soil type to variety of combinations. Simulation runs with the soil enhanced model generate corresponding productivities. A linear regression is conducted to find the correlations between microtunneling productivity in the candidate project and soil compositions. All the analyses are done with R190. R is a free version of S-plus and can be downloaded from http://www.r-project.org/. Figure 5.19 —Productivity in Different Soil Compositions Percentage of Percentage of Percentage of Percentage 0f Productivity Time Duration Clayey Gravel in Sand in the Silt in the (3:23: Per Unit Time Per Pipe Section the Operation Operation Operation (X4 = 100-Xl- (l/Y) Installation (Y) (X1) (X2) (X3) X2-X3) (Section! nun) (min) 10 10 10 70 0.00819 122.1 10 10 20 60 0.008266 120.98 10 10 30 50 0.008554 116.9 10 10 40 40 0.008586 116.4733 10 10 50 30 0.008849 113.0033 10 10 60 20 0.009123 109.6133 10 20 10 60 0.008242 121.3333 10 30 10 50 0.008595 116.3533 10 40 10 40 0.0086 1 16.28 10 50 10 30 0.008809 113.5233 10 60 10 20 0.009028 1 10.7633 10 20 10 60 0.008242 121.3333 10 20 20 50 0.008531 117.22 10 20 30 40 0.008505 117.58 10 20 40 30 0.00873 114.5533 10 20 50 20 0.008969 11 1.5 10 20 60 10 0.009766 102.3933 127 Figure 5.19 (cont’d) 10 30 20 40 0.008615 1 16.08 10 40 20 30 0.008858 112.8933 10 50 20 20 0.009066 110.3 10 30 30 30 0.008767 1 14.06 10 30 40 20 0.00896 1 1 1.6067 10 30 50 10 0.009692 103.18 10 40 3o 20 0.009139 109.4167 20 10 10 60 0.00817 122.4 30 10 10 50 0.007969 125.4933 40 10 10 40 0.007856 127.29 50 10 10 30 0.007793 128.3267 60 10 10 20 0.007888 126.78 20 10 10 60 0.00817 122.4 20 10 20 50 0.008454 118.2867 20 10 30 40 0.008428 1 18.65 20 10 40 30 0.008628 1 15.8967 20 10 50 20 0.008884 1 12.5667 20 10 60 10 0.009637 103.77 30 10 20 40 0.007986 125.22 40 10 20 30 0.008055 124.15 50 10 20 20 0.007993 125.1033 30 10 30 30 0.008117 123.2 30 10 40 20 0.008282 120.7467 30 10 50 10 0.008903 1 12.32 40 10 30 20 0.008287 120.6733 20 20 10 50 0.008457 1 18.24 20 30 10 40 0.008399 1 19.0667 20 40 10 30 0.008629 1 15.8933 20 50 10 20 0.008865 1 12.8067 20 60 10 10 0.009349 106.96 30 20 10 40 0.008051 124.2033 40 20 10 30 0.008098 123.4933 50 20 10 20 0.007951 125.77 60 20 10 10 0.008342 1 19.8767 128 Figure 5.19 (cont’d) 30 30 10 30 0.008182 122.2133 30 40 10 20 0.008349 119.77 30 50 10 10 0.008826 113.3033 40 30 10 20 0.008262 121.0433 50 30 10 10 0.008484 117.8733 25 25 25 25 _ 0.008475 118 - Linear regression of Y vs X1, X2, X3 and X4 The estimated coefficients are shown in Figure 5.20, where the estimated value are the coefficients, and Pr(>|t|) is the p-value. All the p-values are significant small, which means the data plots follow linear patterns on different dimensions. Such patterns are also shown in Figure 5. 21. Figure 5.20 —Confmements Estimation Estimate Std. Error t value Pr(>|t|) Significance (Intercept) 129.32946 1.30947 98.765 < 2e-16 *** X1 0.06841 0.02386 2.867 0.00593 ** X2 -0.28765 0.02386 -12.054 < 2e-16 *** X3 -0.30163 0.02238 -13.480 < 2e-16 *** The residual standard error is 2.202 on 53 degrees of freedom. Multiple R-Squared is 0.8774; adjusted R-squared is 0.8704. F-statistic is 126.4 on 3 and 53 degree of freedom, where p-value < 2.2e-16. In Figure 5.17, X1, X2, X3, and X4 are plotted with Y separately. Clear linear patterns can be found on the plots. The application of linear regression on the data is appropriate. 129 l0 0 O 0 ID 0 $1“ 0 g e e 2!“ e -8 8 9 o .5 8 8 o 90 o 9 808 > 103 o >_ In 8 o a F— :— O O a-g a 8 e O O O 9 .. 10 o o o 0 £08 0 $70 0' o l l l T T l I .l I I I l 10 20 30 40 50 60 10 20 30 40.50 60 X1 )Q o o 3—3 8 gi~ 8 3 ° _ 0 o O -o 8 . 8 §08 0 o g 8 >- 1‘3 9 9 >- 53.. ° -1 0 O ‘- 8 o o g ‘- 8 a B -0 go o o .1 l0 0 m 0 O- o- ‘- 0 8 1- g l l l l T l I l I l [j 10 20 30 40 50 60 10 20 3040 5060 70 )0 X4 Figure 5.21 —Data Plots on X and Y The regression results are as following: Y=a0+ a1X1+ a2X2+ a3X3+ a4X4 =a0+ a1X1+ a2X2+ a3X3+ a4(1-X1-X2-X3) =aO+a4 +(a1-a4)X1 + (a2-a4)X2 + (a3-a4) X3, where the estimated coefficients: a0 + a4 = 129.32946 a1 — a4 = 0.06841 a2 — a4 = -0.28765 a3 — a4 = -0.30163 130 All three are significant, and this means that al, a2, and a3 are all different from a4. More specifically, a1 is significantly larger than a4, and a2, a3 are significantly smaller than a4. Because X4 can be expressed as 100-X1-X2-X3, a1, a2, a3, and a4 do not have unique values. However, the differences between them do have unique values. 131 6 SUMMARY AND CONCLUSIONS 6.1 Overall Summary In previous chapters, in order to analyze microtunneling technology an actual project was reviewed with other background information. The data collected at the Louisiana Tech University LLB Microtunneling Field Test Project in Ruston, Louisiana has been analyzed for modeling inputs. CYCLONE models have been built to reflect the microtunneling operation with soil impacts. Through WebCYCLONE simulations, the productivity of microtunneling operation has been analyzed and the limiting factors have been evaluated. Recommendations are given to optimize the productivity. In addition, the correlations between different soil compositions and microtunneling productivity have been studied. The following research objectives have been completed: 1. Portrayed the process of microtunneling operation in Chapter 2, 2. Identified resources and develop the model for simulation in Chapter 3, 3. Analyzed the production cycle data and find statistical distributions in Chapter 4, 4. Input the distribution data in the model and run simulation with WebCYCLONE, and presented the results in Appendix C and D. 5. Validated the simulated productivity results with actual observations at the project in Section 5.1 and 5.2 6. Performed sensitivity analysis and discussed the optimization of productivity in Section 5.3 and 5.4, 132 7. Enhanced CYCLONE model with consideration of soil compositions in Section 3.7, 8. Ran simulation with variety of soil compositions to obtain corresponding productivity and presented the results in Appendix E and F, 9. Researched the correlation between soil composition and microtunneling productivity in Section 5.5. 6.2 Conclusions based on the Simulation 1. CYCLONE models accurately represent the microtunneling process From the validation of simulation results, It is clear that the averaged simulated productivity is in a reasonable range of the productivity observed from the field. This indicates that the model developments are successful. Such models can be used as a base for future microtunneling productivity research. 2. Kolmogorov-Smirnov Goodness-of-Fit Test The Kolmogorov-Smimov Goodness-of-Fit Test generates valid distributions based on a relatively small set of duration data, which supported the success of the simulation. In construction simulation, data collected from the field is normally fewer than data collected from labs. Facing shortage of data, researchers have to perform well statistical analysis to obtain modeling input as accurate as possible. The accuracy of input duration data is critical to the validation of simulation results. 133 3. Soil Compositions Affecting Microtunneling Productivity Based on the successfulness of CYCLONE model building and the Kolrnogorov-Smirnov Goodness-of-Fit Test, the goal of studying correlations between soil compositions and microtunneling productivity become achievable. The proportions of four types of soil show strong linear correlations with productivity. Stemmed from such result, the coefficients of proportion of each type of soil and microtunneling productivity has been estimated. Through multi-linear regression, an experimental formula was developed to reflect the soil composition effects on microtunneling productivity: Y =129.32946 + 0.06841*X1 - 0.28765*X2 - 0.30163*X3, where Y is time duration in minutes of each 8- foot pipe section installation with microtunneling; X1 is percentage of clayey gravel in the soil composition; X2 is percentage of sand in the soil composition; X3 is percentage of silt in the soil composition. In the full-scale test in Louisiana Tech University, the proportion of clay (X4) can be expressed as 100% minus other three proportions, therefore only three coefficients have certain values, thus X4 does not exist in the expression. The result is for general knowledge of microtunneling productivity. Since it is highly associated with the candidate project’s conditions, it can not be used directly to predict another microtunneling project without considering operations and soil composition. Modifications have to be made to reflect any project condition variations. The durations of jacking pipe sections in four different soils have been studied.iThe conclusion is that clay and clayey gravel tend to have similar property, while the sand and silt don’t have significant difference. The clay and gravel differ mainly on soil property 134 and friction. Possible explanation of close productivities in clay and gravel is that jacking pipe speed in clay soil was impacted by other factors than soil property, for example, the slurry pump incompatible with clay as recorded in Appendix B. Changing of slurry pump could reflect shorter jacking time in clay in the model. The limited times of simulation inevitably brought in skewness to the research. In the simulations with the soil enhanced model, the portion of four different types of soil was set to 25% each. Due to the random nature of the modeling structure, only two pipe section went though silt, and eleven went through gravel, which skewed the simulation results. However, if large number of simulations performed, the pipe sections in each type of soil will be approximately 25%. The skewness is from the limit number of simulations, instead of model structures. 4. Resource Limitations Resource limitations have been studied through sensitivity analysis in WebCYCLONE. The Jacking System is the resource with the highest utilization rate, in 92.17% of the construction duration, it is kept busy. By changing the MTBM cutting head design more appropriate to the soil conditions, productivity can be increased. This change will be reflected in the model by decreasing J acking Pipe Section activity durations, instead of adding more resource. The supervisor was found another bottleneck of the Operation. That might come fi'om the candidate project’s scientific experimental nature. The supervisor in the project takes a » 135 serious of responsibilities, which should be shared by peers. Introducing of another supervisor will increase the productivity. In equipment, crane is the most significant resource limitation. However, from a practical perspective, adding one crane would be infeasible due to site limitation. In labor crews, crew B’s activities are mostly related to jacking system, which keeps crew B occupied. If the MTBM cutting head design can be improved to decrease J acking Pipe Section activity durations, adding Crew B will become unnecessary. Crew A works with supervisor on most activities. Productivity can be improved by adding Labor A with supervisor. The idling time of above bottle neck resources are about 50% except Jacking System, conclusion can be drawn that the microtunneling project in Louisiana Tech University was planned properly. There is no need to adjust resource usage but improve the MTBM cutting head design. 6.3 Limitations of this Research Major limitation of this study was introduced by the data collected. The data amount of the scientific experimental project in Louisiana Tech University was relatively limited, which is due to the high cost of microtunneling operation. Twenty-four pipe sections were installed in the project within four different types of soil. Consequently, twenty-four sets of data were collected, which are merely enough for distribution studies. Furthermore, the data set was divided by four; only six sets of data are available for installing pipe in each type of soil. Although the simulation results met the research objective, the chance of confidentiality can not be eliminated. The limitation of data could undermine the significance of this research. 136 Although cost factor is not considered in this research due to data limitation, cost must be analyzed when adding any resources to microtunneling operations to achieve optimization. 6.4 Recommendations and Areas of Future Research Every project manger strives to achieve three goals on any project — to complete the project on time with the highest possible quality at the lowest possible cost. Simulation is a powerful tool for microtunneling project managers. It provides an appealing approach to analyze and improve repetitive processes in microtunneling. The repetitive nature and the complexity of microtunneling operations make it an ideal candidate for simulation analysis. Simulation allows experimentation with costly microtunneling operations before they are actually performed in the field. By experimenting with multiple scenarios, equipment, labor force and materials, the operation may be streamlined to the project manager’s needs. By using simulation the requirements of the operation and the relationships between their resources can be studied in detail, thus enabling managers to make more informed decisions at different stages of the project. Through better planning and scheduling, the overall performance of a microtunneling project can be improved. Simulation modeling may be done at different levels of detail based on the project - manager’s needs. This allows the use of the same model for different operations since the basic work tasks are similar. Microtunneling operations share many similarities with respect to the pipe jacking process, the slurry removal process, the cleaning and recycle 137 of slurry, etc. Thus, a “template” model of a “standar ” microtunneling operation can be modified with ease to incorporate variations in specific projects. Since microtunneling operations are highly repetitive, small improvements in one cycle could lead to considerable cost and/or time reductions in the full process. A database containing activity durations and productivities on different soil conditions can be interacted with simulation models to continuously improve model results, hence making it an automated viable decision making tool for cost estimating and project planning purposes. When data is collected and such a database'built, graphic interface can be developed for microtunneling operation simulation. Each piece of key components in microtunneling as labor, equipment, and materials will be graphically represented on screen. A user interactive simulation program with graphical appearance and menu or click-and-drop commands can be developed. When microtunneling project managers choose different operation options from the menu, the coding module in the system is triggered to translate options into codes and integrate data from. the database. Such information tells the system what and how resources are altered and the corresponding duration distributions. It is sent to the simulation engine for simulating. The results will be returned to an animation generator to project altered activity duration into animation on the graphic user interface. Any changes made to the simulation model, resources, and duration input will be reflected into animation simultaneously. Such software can be loaded on the computer in microtunneling control unit, thus simplify the simulation use 138 for microtunneling project managers. Simulation tool will be popularized on microtunneling project management. Microtunneling productivity optimization will be achieved widely, fiirthermore lower the associated cost and improve microtunneling competitiveness. 139 APPENDICES 140 APPENDIX A Microtunneling Glossary1 Adapter Ring: In microtunneling, a fabricated ring usually made from steel, that serves to mate the microtunneling machine to the first pipe section. This ring is intended to create a waterproof seal between the machine and the spigot of the first joint. Auger MTBM: A type of microtunnel-boring machine that uses auger flights to remove the spoil through a separate casing placed through the product pipeline. gag: A principal module that is part of a shield machine as in microtunneling or tunnel- boring machines (TBMs). Trailing cans may be used, depending on the installation dimensions required and the presence of an articulated joint to facilitate steering. May also be referred to as a trailing tube. Cased Bore: A bore in which a pipe, usually a steel sleeve, is inserted simultaneously with the boring operation. QsLng: A pipe to support a bore. Usually not a product pipe. Control Console: An electronic unit inside a container located on the ground surface that controls the operation of the microtunneling machine. The machine operator drives the runnel from the control console. Electronic information is transmitted to the control console fi'om the heading of the machine. This information includes head position, steering angle, jacking force, progression rates, machine face torque, slurry and feed line pressures, and laser position. Some control consoles are equipped with a computer that tracks the data for a real-time analysis of the tunnel drive. ' ASCE (2001): Standard Construction Guidelines for Microtunneling 141 Crossing: Pipeline installation in which the primary purpose is to provide one or more passages beneath a surface obstruction. Compression Ring: A ring fitted between the end-bearing area of the'bell and spigot to help distribute applied loads more uniformly. The compression ring is attached to the trailing end of each pipe and is compressed between the pipe sections during jacking. The compression rings compensate for slight misalignment, pipe ends that are not perfectly square, gradual steering corrections, and other pipe irregularities. Also referred to as packers. Cutterhead: Any rotating tool or system of tools on a common support that excavates at the face of a bore. Driveshaft: See Jacking Shaft. Entrance Seal: See Launch Seal ’ Ent_ry Ring: See Launch Seal EPB Machine: Earth pressure balance type of microtunneling or tunneling machine in which mechanical pressure is applied to the material at the face and controlled to provide the correct counter-balance to earth pressures in order to prevent heave or subsidence. The term is usually not applied to systems in which the primary counterbalance of earth pressures is supplied by pressurized slurry. Exit Seal: Same as launch seal except for retrieval of the machine at the reception shaft. Used in high groundwater to prevent the loss of ground. Exit Shaft: See Reception Shaft. Grouting: The process of filling voids or modifying/improving ground conditions. Grouting materials may be cementitious, chemical, or other mixtures. In microtunneling, 142 grouting may be used to fill voids around the pipe or shaft or to improve ground conditions. Interiack Pipes: Pipes specially designed for use with an intermediate jacking station. Intermediate Jacking Station: A fabricated steel cylinder fitted with hydraulic jacks that is incorporated into a pipeline between two pipe segments. Its function is to distribute the jacking load over the pipe string on long drives. Jacking Frame: A structural component that houses the hydraulic cylinders used to propel the microtunneling machine and pipeline. The jacking frame serves to distribute the thrust load to the pipeline and the reaction load to the shafi wall or thrust wall. J acking Pipes: Pipes designed to be installed using pipe jacking techniques. J acking Shaft: Excavation fiom which trenchless technology equipment is launched for the installation or renovation of a pipeline, conduit, or cable. May incorporate a thrust wall to spread reaction loads to the ground. Jacking Shield: A fabricated steel cylinder fi'om within which the excavation is carried out either by hand or by machine. Incorporated within the shield are facilities to allow it to be adjusted to control line and grade. Launch Seal: A mechanical seal, usually composed of a rubber flange that mounted to the wall of the drive shaft. The flange seal is distened by the MTBM as it passes through, creating a seal to prevent water or lubrication inflow into the shaft during tunneling operation. Lubrication: A fluid, normally bentonite, used to reduce jacking loads on the jacking pipe. Muck: Spoil or removal of same. 143 Obstruction: Any, object or feature that lies completely or partially within the cross- section of the microtunnel and prevents continued forward progress. Overcut: The annular space between the excavated hole and the outside diameter of the jacking pipe. PM: See Compression Ring. mt Time Metppg: A multistage method of accurately installing a product pipe to line and grade by use of a guided pilot tube followed by upsizing to install the product pipe. Product Pipe: Pipe used for conveyance of water, gas, sewage, and other products and services. Push Ring Adapter: Mechanical structure mounted on the thrust ring to prevent the thrust ring from coming in contact with the pipe collar and causing damage to the collar. Receiving Shaft: See Reception Shaft. Reception Shaft: Excavation into which the microtunneling equipment is driven and recovered. film: A fluid, normally water, used in a closed loop system for the removal of spoil and for the balance of groundwater pressure during microtunneling. Slurp! Chamber: Located behind the cutting head of a slurry microtunneling machine, a chamber in which excavated material is mixed with slurry for transport to the surface. Slurp! Line: A series of hoses or pipes that transport tunnel muck and slurry from the face of a slurry microtunneling machine to the ground surface for separation. Slurry Separation: A process in which excavated material is separated from the circulation slurry. 144 m: Mechanical structure used to transfer the jacking load from the jacking thrust ring to the pipe and used to accommodate lengths of pipe that are longer than the stroke length of the jacks. SM]; Earth, rock, and other materials removed during installation. Thrust Ring: A fabricated ring that is mounted on the face of the jacking frame. It is intended to transfer the jacking load from the jacking frame to the thrust-bearing area of the pipe section being jacked. Trenchless Technology: Techniques for utility or other line installation, replacement, renovation, inspection, leak location and detection, with minimum excavation fiom the ground surface. Tunneling: A construction method of excavating an opening beneath the ground without continuous disturbance of the ground surface and of large enough diameter to allow individuals access and erection of a ground support system at the location of material excavation. Uncased Bore: Any bore without a lining or pipe inserted, i.e., self-supporting, whether temporary or permanent. water Jets: Internal cleaning mechanism of the cutterhead in which hi gh-pressure water is sprayed from nozzles to help remove cohesive soils. 145 APPENDIX B Duration Data Collected from the Louisiana Tech University Microtunneling Project (Najafi, 1993) A Durations for jacking pipe sections . Start Finish urationl Pipe No. Date Time Time (min) Notes Boring 1100 1130 From 130 to 3'45 pm reconnect adapters machine 6/16/ 1992 ' ° 30 ' . '. . ’ AM AM electnc lrnes and extens1ons. adapters Boring . _ . . machine 6/17/1992 3:45 PM 4: 10 PM 25 Fm“ 3'45 t° 4'10 pm “3mm“ “mg f“ the machrne - adapters 1 6/17/1992 8:50 AM 9:43 AM 53 Boring within clay section 2 6/17/1992 1:35 PM 3:07 PM 92 Boring within clay section 3 6/18/1992 8:18 AM 9:46 AM 88 Boring within clay section 4(with gripper) 6/18/1992 1:07 PM 2:32 PM 85 Boring within clay section Boring within clay section (average duration 5 6/18/1992 3:40 PM 4:52 PM 72 = 74 rrrinutes and average speed = 1.3 inch/minutes) 6 6/19/1992 8: 12 AM 8:46 AM 34 Boring machine began entering inside silt. . 10:23 7 6/19/1992 9.56 AM AM 27 11:20 12:01 8 6/19/1992 AM AM 41 From 2:43 to 2:51 pm machine was stopped because slurry back pressure was high and flow volume was low. From 2:53 to 3:53 pm 9(with gripper) 6/19/1992 2:40 PM 4:34 PM 114 wood pieces in the silt clogged the slurry pump inside pit. Same problem happened from 3:57 to 4:00 and from 4:17 to 4:21 and from 4:26 to 4:28 pm. 10 6/20/1992 8:14 AM 8:39 AM 25 . 10:06 11 6/20/1992 9.39 AM AM 27 10:35 10:53 . . . . 12 6/20/1992 AM AM 18 Bonng wrtlun sand sectron 13 6/22/1992 8:50 AM 9:40 AM 50 9:05 to 9:25 jacking was stopped for crack sealant to dry up. 14(w1th 6/22/1992 11:09 11:45 36 gripper) AM AM 15 6/22/1992 2:08 AM 2:20 AM 12 16 6/22/1992 3:30 AM 3:53 AM 23 17 6/22/1992 4:50 PM 5:09 PM 19 B°mg ”Chmiggt‘i‘gjd Clayey gravel 146 8:26 to 8:35 jacking pressure obstruction 8:40 to 9:08 slurry line obstruction. 9:11 to 18 6/23/1992 8:20 AM 9:57 AM 97 9:30 slurry line obstruction. Note: 28 liters of lubricant (bentonite) used to push this section 1 1:12 1 1:54 . . 19 6/23/1992 AM AM 42 85 lrters of lubrrcant was used. 20 6/23/1992 1:53 PM 2:34 PM 41 93 liters of lubricant was used. 21 6/23/1992 3:33 PM 5:29 PM 116 4:05 t° 4‘43 9‘“ it“ Slurry Pm“? “‘s‘d" the prt clogged. 22 6/24/1992 8:09 AM 9:25 AM 76 Slurry pump inside the pit clogged 10:15 . 10:24 to 10:41 amthe slurry pump inside 23 6/24/1992 AM 1 1.15 60 the pit clogged At 1:53 pm boring machine entered the clay zone. Total jacking force 39 ton. Jacking 24 6/24/1992 1:16 PM 2:21 PM 65 force on the plastic pipe 2 tons. Maximum jacking load on plastic pipe occurred at pipe No.12 and at a load of 3.5 tons. 147 Durations for installation of the pipe section on the guard rail (including installation of cables and hoses and settin up the laser) . Start Finish Duration Prpe No. Date Time Time (min) Notes 1 6/17/1992 8:50 AM 9:43 AM 53 2 6/17/1992 10:00 AM 12:15 AM 135 me 10“” ‘° ”5.0 “.1”.wa“‘“g ‘° 3““ the prpe jomt. At 3:25 pm the desandman was 3 6/18/1992 3:25 PM 4:25 PM 60 discharged. Grinding the joint from 3:28 to 3:31 pm Fitting the pipe joints together from 11:10 . . . _ to 11:38 am Gripper installation inside 4(w1th gripper) 6/18/1992 10.22 AM 11.47 AM 85 plastic pipe from 9:00 to 9:15 am, checking gripper from 9: 16 to 9:30 am . . Laser installation from 3:32 to 3:38 pm. 5 6/18/1992 2'49 PM 33.8 PM 49 Desandman was discharged at 3:30 pm 6 6/18/1992 5:05 PM 5:47 PM 42 Laser was not 1nstalled. Desandman was drscharged. 7 6/19/1992 9:04 AM 9:55 AM 51 Laser installation from 9:46 to 9:55 am 8 6/19/1992 10:36AM 11:20AM 44 9 6/19/1992 1:37 PM 2:40 PM 63 10 6/19/1992 4:52 AM 5:27 AM 35 11 6/20/1992 9:00 AM 9:37 AM 37 12 6/20/1992 10:25 AM 11:30 AM 65 5 minutes for pipe measurements. 13 6/20/1992 12:06 PM 12:42 PM 36 A 3m". 9”“ was mm" When the 1”?" jomts were fitted together. 141““ 6/22/1992 10:05 AM 11:09 AM 64 gripper) . 15 6/22/1992 12:04 PM 12:32 PM 28 16 6/22/1992 2:54 PM 3:30 PM 36 17 6/22/1992 4:08 PM 4:50 PM 42 18 6/22/1992 5:22 PM 5:55 PM 33 Laser to be set up in the morning. i _ . Slurry pump was disassembled and 19 6/23/1992 10.16 AM 10.55 AM 39 checked for obstructions 20 6/23/1992 12:10 PM 12:42 PM 32 21 6/23/1992 2:46 PM 3:32 PM 56 22 6/23/1992 5:38 PM 6:07 PM 29 Laser to be set up in the morning. 23 6/24/1992 9:40 AM 10:15 AM 35 24 6/24/1992 11:27 AM 12:00 AM 33 148 Durations for installation of the casings and grippers inside the plastic pipe (including time necessary to install two slurry pipes, two Jullback rods and check the air grippers) Pipe No. Date 3.2:: 22:23: D333?“ Notes 1 6/16/1992 4:47 PM 4:57 PM 10 2 6/17/1992 9:44 AM 9:57 AM 13 3 6/17/1992 2:02 PM 2:12 PM 10 Gripper installation inside plastic pipe 4(with gripper) 6/18/1992 9:00 AM 9:30 AM 30 from 9:00 to 9:15 am, checking gripper from 9:16 to 9:30 am. 5 6/18/1992 2:15 PM 2:25 PM 10 6 6/18/1992 4:47 PM 4:52 PM 5 7 6/19/1992 8:52 AM 8:58 AM 6 8 6/19/1992 10:07AM 10:14AM 7 9(with gripper) 6/19/1992 11:50 AM 12:05 PM 15 From 11:55 to 12:05 checking gripper 10 6/19/1992 4:00 PM 4:08 PM 8 11 6/20/1992 8:35 AM 8:40 AM 5 12 6/20/1992 9:42 AM 9:50 AM 8 13 6/20/1992 10:40 AM 10:47 AM 7 glfigretrl; 6/22/1992 9:35 AM 9:50 AM 15 10 minutes for checking the gripper 15 6/22/1992 11:40 AM 11:45 AM 5 16 6/22/1992 2:31 PM 2:38 PM 7 17 6/22/1992 3:48 PM 3:55 PM . 7 18 6/22/1992 5:07 PM 5:19 PM 12 19 6/23/1992 9:20 AM 9:26 AM 6 20 6/23/1992 11:52 AM 11:58 AM 6 g 21 6/23/1992 5:00 PM 5:06 PM 6 Wrong pipe loaded with casing 22 6/23/1992 3:53 PM 3:56 PM 3 23 6/24/1992 8:03 AM 8:08 AM 5 24 6/24/1992 10:52 AM 10:57 AM 5 149 Durations for retraction of Jacks (including dismantling of cables and hoses) Pipe No. Date in: F123: 0:32;)“ Notes 1 6/17/1992 9:44 AM 9:55 AM 11 2 6/17/1992 3:10 PM 3:25PM 15 3 6/18/1992 9:47 AM 10:14 AM 27 4(with gripper) 6/18/1992 2:35 PM 2:47 PM 12 5 6/18/1992 4:56 PM 5:04 PM 8 6 6/19/1992 8:47 AM 9:00 AM 13 7 6/19/1992 10:24 AM 10:33 AM 9 8 6/19/1992 1:18PM 1:35PM 17 9(with gripper) 6/19/1992 4:37 PM 4:51 PM 14 10 6/20/1992 8:44 AM 8:57 AM 13 11 6/20/1992 10:15 AM 10:22 AM 7 12 6/20/1992 11:53 AM 12:04 PM 11 Taking off laser fi'om 10:53 to 10:55 am. 13 6/22/1992 9:40 AM 9:55 AM 15 14(with gripper) ‘ 6/22/1992 11:50 AM 12:03 AM 13 15 6/22/1992 2:29 PM 2:45 PM 16 16 6/22/1992 3:58 PM 4:06 PM 8 17 6/22/1992 5:09 PM 5:17 PM 8 18 6/23/1992 10:02AM 10:12AM 10 19 6/23/1992 12:00PM 12:10PM 10 20 6/23/1992 2:35 PM 2:42 PM 7 21 6/23/1992 5:30 PM 5:37 PM 7 22 6/24/1992 9:27 AM 9:35 AM 8 23 6/24/1992 11:17AM 11:25AM 24 N/A N/A N/A ' N/A 150 Summary of Production Rates transit Type of Work Time Required Opening the crates and installation of 3 da all rrucrotunnelrng equ1pment Checkrng the. nucrotunnelrng _ ‘ 1 day equ1pment Average hoisting time 2 min. Average time for installation of 8 8 min. casing inside PVC pipe ' Average time for installation of PVC pipe (with casing) on the guide rails 4 . . . . . 3 mm. (mcludrng connectron of slurry prpes, hoses and cables) Average trme for sett1ng up of laser 10 min. Average time for pushing the pipe Clay 33 mm. (1.3 ir1./min.) Silt 101.6 mrn/min. (4.0 in./rnin.) Sand . 134.6 mm/min. (5.3 in./min.) Clayey Gravel 43.2 mm/min. (1.7 in./min.) Average time for retraction of jacks (including dismantling of cables and hoses) 11.6min. Average cycle time for installation of an 8-ft section of PVC pipe in: Clay 169 min. Silt 97 min. Sand 91 min. Clayey Gravel 130 min. Average time for pulling back of one liner casing and dismantling of all 20 min. (10 min. to retract the slurry pipes, hoses and cables for jacks) each PVC pipe section Drsmantlmg, washing and crating of 2 days equ1pment Loading equipment 1 day 151 APPENDIX C Coding of the Prototype CYCLONE Microtunneling Simulation Model: Input Model Line 1: NAME MICROTUNNELING PROCESS LENGTH 10000 CYCLES 30 Line 2: NETWORK INPUT Line 3: 1 COM 'DISCHARGE & REFILL DESANDMAN' SET 1 PRE 33 18 14 FOL 18 14 24 Line 4: 2 COM 'MIX LUBRICATION' SET 2 PRE 13 22 32 FOL 13 21 22 Line 5: 3 COM 'DISMANTLE CABLES & HOSES' SET 3 PRE 34 14 18 FOL 17 23 14 18 39 99 i I Line 6: 4 COM 'EMPTY SPOIL TANK' SET 4 PRE 31 19 20 FOL 27 19 20 Line 7: 5 COM 'PIPE SECTION INSTALL ON GUARD RAIL' SET 5 PRE 30 18 14 35 24 23 2127 FOL 41 1814 42 Line 8: 6 COM 'LOWER SECTION INTO SHAFT ' SET 6 PRE 29 18 FOL 30 18 Line 9: 7 COM 'ADIUST AIR GRIPPER' SET 7 PRE 13 2614 FOL 13 1415 Line 10: 8 COM 'INSTALL & CHECK AIR GRIPPER' SET 8 PRE 13 25 14 FOL 13 14 43 ' Line 11: 9 COM ’ATTACH SECTION TO CRANE' SET 9 PRE 28 13 17 16 15 FOL 40 13 12 Line 12: 10 COM 'BRING SECTION & INSTALL CASING' SET 10 PRE 11 13 12 FOL 36 13 28 Line 13: 11 QUE 'SECTION ON STORAGE' 152 Line 14: Line 15: Line 16: Line 17: Line 18: Line 19: Line 20: Line 21: Line 22: Line 23: Line 24: Line 25: Line 26: Line 27: Line 28: Line 29: Line 30: Line 31: Line 32: Line 33: Line 34: Line 35: Line 36: 12 QUE POSITION AVAILABLE' 13 QUE 'LABOR A IDLE' 14 QUE SUPERVISOR IDLE' 15 QUE 'AIR GRIPPER READY' GEN 5 16 QUE 'CRANE IDLE' 17 QUE 'CONTROL CRANE' 18 QUE 'LABOR B IDLE' 19 QUE 'TRUCK IDLE' 20 QUE 'BACKHOE IDLE' 21 QUE 'LUBRICATION READY' GEN 4 22 QUE 'BENTONITE READY' ~ 23 QUE 'JACKING SYSTEM IDLE' 24 QUE 'WATER READY' GEN 4 25 QUE 'NEED AIR GRIPPER' 26 QUE 'GRIPPER NEED ADJUST' 27 QUE 'SPOIL TANK NOT FULL' GEN 4 28 QUE 'POSITION OCCUPIED' 29 QUE 'SECTION READY' 30 QUE 'SECTION READY' 31 QUE 'SPOIL TANK FULL' 32 QUE 'NEED LUBRICATION' 33 QUE 'DESANDMAN READY TO DISCHARGE' 34 QUE 'SECTION IN PLACE' 153 Line 37: Line 38: Line 39: Line 40: Line 41: Line 42: Line 43: Line 44: Line 45: Line 46: Line 47: Line 48: Line 49: Line 50: Line 51: Line 52: Line 53: Line 54: Line 55: Line 56: Line 57: Line 58: Line 59: 35 QUE 'CABLE HOSE LASER READY' 36 FUN CON 5 FOL 25 37 FUN CON 4 FOL 32 38 FUN CON 4 FOL 31 39 FUN CON 4 FOL 33 40 NOR 'LIFT SECTION TO POSITION SET 40 FOL 29 41 NOR 'CRANE RETURNS SET 41 FOL 16 42 NOR 'JACK PIPE SECTION SET 42 FOL 34 37 38 43 NOR 'DUMMY' SET 43 FOL 26 15 PROBABILITY .33 .67 99 FUN COU FOL 35 QUA 1 DURATION INPUT SETITR1101215 SET 2 TRI 25 30 35 SET 3 BET 7 33 0.643 3.02 SET 4 TRI 20 30 35 SET 5 BETA 28 80 0.761 1.841 SET 6 UNI 1 2 SET 7 UNI 10 15 SET 8 UNI 10 15 SET 9 DET 2 SET 10 TRI 2 5 15 SET 40 DET 1 SET 41 DET 2 154 Line 60 Line 61 Line 62 Line 63 Line 64 Line 65 Line 66 Line 67 Line 68 Line 69 Line 70 Line 71 Line 72 Line 73 Line 74 Line 75 Line 76 Line 77 Line 78 : SET 42 BETA 12 102 0.854 1.403 : SET 43 DET 0 : RESOURCE INPUT : 30 'PIPE SECTION' AT 11 : 1 'POSITION' AT 12 : 1 'LABOR' AT 13 : 1 'SUPERVISOR' AT 14 : l 'GRIPPER READY SIGNAL' AT 15 : 1 'CRANE' AT 16 : 1 'CRANE CONTROL SIGNAL' AT 17 : 1 'LABOR' AT 18 : 1 'TRUCK' AT 19 : 1 'BACKHOE' AT 20 : 1 'LUBRICATION READY SIGNAL' AT 21 : 1 'BENTONITE READY SIGNAL' AT 22 : 1 'JACKING SYSTEM' AT 23 : 1 'WATER READY SIGNAL' AT 24 : l 'SPOIL TANK NOT FULL SIGNAL' AT 27 : l 'CABLE HOSE LASER READY SIGNAL' AT 35 155 APPENDIX D Coding of the CYCLONE Microtunneling Simulation Model with Soil Condition Enhancement: Input Model Line 1: NAME MICROTUNNELING PROCESS IN DIFFERENT SOILS LENGTH 10000 CYCLES 30 Line 2: NETWORK INPUT Line 3: 1 COM 'DISCHARGE & REFILL DESANDMAN' SET 1 PRE 33 18 14 24 FOL 18 14 24 Line 4: 2 COM 'MIX LUBRICATION' SET 2 PRE 13 22 32 FOL 13 21 22 Line 5: 3 COM 'DISMANTLE CABLES & HOSES 1' SET 3 PRE 34 14 18 FOL 17 23 14 18 51 24 99 Line 6: 44, COM 'DISMANTLE CABLES & HOSES 2' SET 13 PRE 47 14 18 FOL 17 231418 5124 99 Line 7: 45 COM 'DISMANT LE CABLES & HOSES 3' SET 23 PRE 48 14 18 FOL 17 , 231418 5124 99 Line 8: 46 COM 'DISMANTLE CABLES & HOSES 4' SET 33 PRE 49 14 18 FOL 17 231418 50 24 99 Line 9: 4 COM 'EMPTY SPOIL TANK' SET 4 PRE 31 19 20 FOL 27 19 20 Line 10: 5 COM 'PIPE SECTION INSTALL ON GUARD RAIL' SET 5 PRE 30 18 14 35 24 232127 FOL 41 1814 52 Line 11: 6 COM 'LOWER SECTION INTO SHAFT' SET 6 PRE 29 18 FOL 30 18 Line 12:7 COM 'ADJUST AIR GRIPPER' SET 7 PRE 13 26 14 FOL 13 1415 156 Line 13: 8 COM 'WSTALL & CHECK AIR GRIPPER' SET 8 PRE 13 25 14 FOL l3 14 43 Line 14: 9 COM 'ATTACH SECTION TO CRANE' SET 9 PRE 28 13 17 16 15 FOL 40 1312 Line 15: 10 COM 'BRING SECTION & INSTALL CASING' SET 10 PRE ll 13 12 FOL 36 13 28 Line 16 Line 17: Line 18: Line 19: Line 20: Line 21: Line 22: Line 23: Line 24: Line 25: Line 26: Line 27: Line 28: Line 29: Line 30: Line 31: Line 32: 11 QUE 'SECTION ON STORAGE' 12 QUE POSITION AVAILABLE 13 QUE 'LABOR A IDLE' 14 QUE SUPERVISOR IDLE' 15 QUE 'AIR GRIPPER READY' GEN 5 16 QUE 'CRANE IDLE' 17 QUE 'CONTROL CRANE' 18 QUE 'LABOR B IDLE' 19 QUE 'TRUCK IDLE' 20 QUE 'BACKHOE IDLE' 21 QUE 'LUBRICATION READY' GEN 4 22 QUE 'BENTONITE READY' 23 QUE 'JACKING SYSTEM IDLE' 24 QUE 'WATER READY' 25 QUE 'NEED AIR GRIPPER' 26 QUE 'GRIPPER NEED ADIUST' 27 QUE 'SPOIL TANK NOT FULL' GEN 4 157 Line 33: Line 34: Line 35: Line 36: Line 37 : Line 38: Line 39: Line 40: Line 41: Line 42 Line 43: Line 44: Line 45: Line 46: Line 47: Line 48: Line 49: Line 50: Line 51: Line 52: Line 53: Line 54: Line 55: 28 QUE POSITION OCCUPIED 29 QUE 'SECTION READY' 30 QUE 'SECTION READY' 31 QUE 'SPOIL TANK FULL' 32 QUE 'NEED LUBRICATION' 33 QUE 'DESANDMAN READY TO DISCHARGE' 34 QUE 'SECTION IN PLACE 1' 47 QUE 'SECTION IN PLACE 2' 48 QUE 'SECTION IN PLACE 3' : 49 QUE 'SECTION IN PLACE 4' 35 QUE 'CABLE HOSE LASER READY' 36 FUN CON 5 FOL 25 37 FUN CON 4 FOL 32 38 FUN CON 4 FOL 31 50 FUN CON 2 FOL 33 51 FUN CON 3 FOL 50 40 NOR 'LIFT SECTION TO POSITION‘ SET 40 FOL 29 41 NOR 'CRANE RETURNS' SET 41 FOL 16 42 NOR 'JACK PIPE SECTION 1' SET 42 FOL 34 37 38 57 NOR 'JACK PIPE SECTION 2' SET 57 FOL 47 37 38 58 NOR 'JACK PIPE SECTION 3' SET 58 FOL 48 37 38 59 NOR 'JACK PIPE SECTION 4' SET 59 FOL 49 37 38 43 NOR 'DUMMY' SET 43 FOL 26 15 PROBABILITY .33 .67 158 Line 56: Line 57: Line 58: Line 59: Line 60: Line 61: Line 62: Line 63: Line 64: Line 65: Line 66: Line67: Line 68: Line 69: Line 70: Line 71: Line 72: Line 73: Line 74: Line 75: Line 76: Line 77: Line 78: 52 NOR DUMMY 1' SET 44 FOL 53 54 55 56 PROBABILITY .25 .25 .25 .25 53 NOR 'DUMMY SOIL TYPE CLAYEY GRAVEL' SET 45 FOL 42 54 NOR 'DUMMY SOIL TYPE SAND' SET 46 FOL 57 55 NOR DUMMY SOIL TYPE SILT' SET 47 FOL 58 56 NOR 'DUMMY SOIL TYPE CLAY' SET 48 FOL 59 99 FUN COU FOL 35 QUA 1 DURATION INPUT SET 1 TRI 10 12 15 SET 2 TRI 25 30 35 SET 3 BET 7 33 0.643 3.02 SET 4 TRI 20 30 35 SET 5 BETA 28 80 0.761 1.841 SET 6 UNI 1 2 SET 7 UNI 10 15 SET 8 UNI 10 15 SET 9 DET 2 SET 10 TRI 2 5 15 SET 13 BET 7 33 0.643 3.02 SET 23 BET 7 33 0.643 3.02 SET 33 BET 7 33 0.643 3.02 SET 40 DET 1 SET 41 DET 2 SET 42 BETA 26 88 1.075 1.041 159 Line 79: Line 80: Line 81: Line 82: Line 83: Line 84: Line 85: Line 86: Line 87: Line 88 Line 89: Line 90 Line 91 Line 92 Line 93 Line 94 Line 95 Line 96 Line 97 Line 98 Line 99 SET 43 DET 0 SET 44 DET 0 SET 45 DET 0 SET 46 DET 0 SET 47 DET 0 SET 48 DET 0 SET 57 BETA 12 46 0.613 0.793 SET 58 BETA 17 510.989 1.775 SET 59 BETA 19 92 0.781 0.323 : RESOURCE INPUT 30 PIPE SECTION' AT 11 : 1 'POSITION' AT 12 : 1 'LABOR' AT 13 : 1 'SUPERVISOR' AT 14 : 1 'GRIPPER READY SIGNAL' AT 15 : 1 'CRANE' AT 16 : 1 CRANE CONTROL SIGNAL' AT 17 : 1 'LABOR' AT 18 : 1 'TRUCK' AT 19 : 1 'BACKHOE' AT 20 : 1 'LUBRICATION READY SIGNAL' AT 21 Line 100: 1 'BENTONITE READY SIGNAL' AT 22 Line 10 l: l 'JACKING SYSTEM' AT 23 160 Line 102: 1 'WATER READY SIGNAL' AT 24 Line 103: l 'SPOIL TANK NOT FULL SIGNAL' AT 27 Line 104: 1 'CABLE HOSE LASER READY SIGNAL' AT 35 161 APPENDIX E Simulation Results with Prototype CYCLONE Microtunneling model: Simulation Run Times: 30 1 MICROTUNNELING PROCESS 1' " WWPRODUCTIVITY INFORMATION Sim. Time 1C§616WN6 Productrvrty Per Time Unrt 160.4 1 1 0. 006234 " 0.007120 1 W" "0.008899T” 0.010080 1 0.007940 0.007984 ., 0.007794 0.008265 0008442 ' 7' 0. 008367 WWWO 00865TWWW' ” 0. 008929 13 0.009121 '14 0.009353 ' 1 l l mi ' w: 1 'x) ~ 1 | 1 1 \1 01 11:14:. wSN' I 1 l -.._.__...... _.. ~.,‘-._... . \ooo O n—oiu—t N.— l 1 15504 *' 1‘5 WT0009675WW' 16 WW 0.009955 "17067“ W "1T" §W 0. 009961 _ w a... ._.. -.., .... ..-....,........... i l ‘ 18 0009986 1 19 0.009814 1 20 0.009847 2 1 21 ” W“70.0'09'5'49Wm"W' 1 22 0.009265 W. 1"”23 " 0.009195 l 1 l l l l 2.4 1 0.00912T _ ,_ 25 0.009206 26 0.009224 W27' “0009282? " 28 0. 009293 -_........—.. -___._.—.... ...a -.W ....—..___m ..._~.. ...,-...— 29 0009147 30 0.009272 ' 162 1W "WWW'WWWW'WWWWW MICROTUNNELING PROCESS W W 1 PRODUCTIVITY INFORMATION : 1 Total Sim. Time Unit 1 Cycle NO. QW Productivity (per time unit) 3235.4 1 30 0.0092724093 16360385 W CYCLONE ACTIVE ELEMENTS STATISTICS INFORMATION WW Activity NT Name 1 Access Average Maximum Minimum ‘ Type ' 1Counts Duration Duration Duration ' ' DISCHARGE& 1 COMBI 1 REFILL 7 12.3 14.2 10.8 DESANDMAN ”COMBI 12 1M1XLUBRICATIONW1W 7 299W 1 33.5 126.8 ' W WWW~ DISMANTLE r7 COMBI 1 3 1 CABLES &HOSES 1 30 11.6 29.1 7.1 .WWWWW‘W 1 1“ WW W WWW WWWWWWWWW ; . EMPTY SPOIL - 1 1 1 g COMBI 14W 1 TANK 7 28.1 33.2 23.1 PIPE SECTION W COMBI 5 INSTALL ON 30 41.9 77.8 28.4 GUARD RAIL 1 WWW LOWER SECTION 1" “W COMBI 6 1 INTO SHAFT 1 30 1.4 2.0 1.0 E'W WW ADJUST AIR 1 ' COMBI 7 GRIPPER 4 13.2 14.8 1 11.1 WW INSTALL & CHECK WEWWW W COMBI 8 AIR GRIPPER 6 1 12.5 14.8 1 10.3 ATTACH SECTION 1 1 COMBI 9 To CRANE 30 1 2.0 2.0 1 2.0 W BRING SECTION& 1 COMBI 10 INSTALL CASING 30 1 6.6 12.6 2.3 {WWW—WW LIFT SECTION TO W1 .1 W NORMAL 40 POSITION 30 1 1.0 1.0 1 1.0 NORMAL 41 1 CRANERETURNS 1W 30 ”230' 120W 2.0 JACK PIPE 1 ‘ 1 1NORMAL W131 SECTION 1 30 44.3 1 100.7 1 13.3 NORMAL W151 DUMMY 1 6 0.0 1 0.0 1 0.0 ._ 163 r. .... l WWWWWWWWWWW Average Max. Times 1y Total Average UnitSW1 Type .No. Name Units Idle not I d1e Sim Wt at '1 Idle Units empty Time Time end WWW SEWEfiONWWON W 1 WW" WWW QUEUE111 STORAGE 14.6 130 3036.3 93.85 3235.4 737.2 0 r 3,. -. . -133 .... 3-... 1333.3- 3 3.4 ...--.. ..-. ..._. .. . - --H..-..._-~~._ W... .. . lW ' POSITION 1 1 101 a QUEUE 12 AVAILABLE 1 0.0 1 1 0.0 10.00 3235.4 0.0 1 » WW WWWWW LABORA " 1 'WWW WW‘ QUEUE 13 IDLE 1 0.8 1 1 2577717967 3235.4. 33.0 1 '7 I“ 1 1 QUEUE 14 SUPERVISOR: 0.4 1 1 11416.8 43.79 3235.4 18.2 ' 1 IDLE 1 ...-333.3 _3- 1.. 1 1 GEN 15 “1113;111:5131 3.4 1 6 131704 97.99 3235.4 334.2 1 5 1QUEUE1161CRANEIDLE1 0.5 f 1 11..75551542613235.41566 1 WW” CONTROL ‘1 1 1 1QUEUE11 1 CRANE 1 0.0 1 .1157.0 4.85 3235.4 5.1 1 1 1. 1-33.3 3.3-3.1 3.3 1.333 LABORB 1 1 1QUEUE1181 IDLE 1 0.5 1 11502.3 46.43 3235.4 15.3 1 1 1QUEUE119 TRUCK IDLEWEW 0.9 1 1 128352187631323324135414WWEW‘1WW 1QUEUE 20 BACKHOE 1 0.9 1 1 2835.2187.63 3235.4 354.4 1 1 IDLE 1 - 1 1 1.-..3..._3._..3..-- ~~~—-—-’“"--; ------———r-—------~ ‘- ‘1 1—'-“~--~~-~--° ‘——'“ 1 GEN 121 WLUBgEgg'ON 1.6 4 2466.117622132354 160.6 1 2 1 1 1 3 BENTONITE -113_3_---_3_ 1 1QUEUE 22 READY 1 0.9 1 2825.1187.3213235.4 353.1 1 1 “r" r"— 1 ' r JACKING 1 : 1 1 1 QUEUE 23 SYSTEM IDLE1 0.1 1 1289.5 18.95 13235.4 9.3 1 1 WATER 1 1 1 1 GEN .12: READY 1:3” :1-“ 2532.2178.2713235.41 168.5 2 NEED AIR QUEUE 25 GRIPPER 0.1 1 203.616.29 3235.4 33.9 0 33313GRI3PPER 3-3-3-333..- QUEUE 26 NEED ADJUST 0.0 1 0.0 W10.00 3235.4 0.0 1 0 . g.— . SPOILTANK 1 1 GEN 27 NOT FULL 1.7 4 2478517661 3235.4 162.1 2 . WWW 1W POSITION WW" 1 W WWW" 1WWWW1 QUEUE128 OCCUPIED 0.9 1 2914.9 90.09 3235.4 97.2 1 0 3.3333... ______ SECTION - _ 3 3- QUEUE 29 READY 0.0 1 0.0 0.00 3235.4 0.0 0 1'“ ,__.._,__ "_"_' :' SECTION 1 1 QUEUE 30 READY 0.0 1 1 1 0.0 0.00 3235.4 0.0 0 ..____._F___ QUEUE 31 31301113ng 0.0 1 1 1 0.0 0.00 3235.4 0.0 o WOWIWJWEWIWIEWW 32 NEED 1.---.(1-;---1—.__l~-1.403416-$g23541 00 W o 1 LUBRICATION ' 1 ' ° 1 ° ' 1 CYCLONE PASSIVE ELEMENTS STATISTICS INFORMATION 164 sQUEUE§ 33 l 1' I 1 ‘1 I . __-_-L.,___f-._--.. EQUEUE 34 I §_,....-___.. E {QUEUE L 35 .' I- I 1 ' l -~ _- .-. ’ - ~~.v- ...-....-.“ "...—‘nafi '—~-. -....p— .- a - —-— {DESANDMAN ‘ { ; READYTO 5 0.0 g 1 0.0 10001323541 0.0 ' DISCHARGE g i g i Sfié'l‘mileN E ” I Tm“; PLACE i 0.0 { 1 11.7 !O.36 E32354i 04 CABLE HOSE " 1“ " g 1 1:. LASER g 0.1 1 1 289.5 g8.95 3235.4! i READY I 3 1 l f M ' TRXCEINFORMATION" ” " ” Sim Activity Time No. Type Name 1 NWWW’ " --.,..--_____ BRING SECTION& 4.9 10 COMBI INSTALL CASING * XfiACH 6.9 9 COMBI SECTION TO CRANE LIFT SEC'I‘IONE . 7.9 40 NORMAL To POSITION; ..-,-.._-- " LOWER I 9.1 6 COMBI SECTION INTOE SHAFT BRING SECTION& 19.5 10 COMBI INSTALL CASING N FIRE SEETTONFE . 67.3 5 COMBI INSTALL ON GUARD RAIL ' CRANE ’ 69.3 41 NORMAL RETURNS JACK PIPE 143.4 42 NORMAL SECTION . E ..- ' DISMAN'EEE 160.4 3 COMBI CABLES& ' HOSES _ {166.4f 99""l""COUNTE" R“ "NM”:"W" ATTACH 162.4 9 COMBI SECTION TO CRANE ; LIFT SECTION? 163.4 40 NORMAL To POSITION; ' E "— LOWER : 165.4 6 COMBI SECTION INTO? SHAFT j 172 7! [ COMBI { BRING . 165 212.0 ,. --fl--..___. 268.7 280.9 {586.89%}? 214.0 99 l COMBI NORMAL " “REE SECTION“; ’ SECTION 87E INSTALL CASING INSTALL ON GUARD RAIL CRANE RETURNS NORMAL JACK PIPE SECTION COMBI i I DISMANTLE CABLES & HOSES 'I COUNTER 282.9 9 COMBI ATTACH SECTION TO CRANE 283.9 285.7 337.1 - , ~...__......-. ...- ,. .-—.—... -...— ...... 42 40 NORMAL LIFT SECTION TO POSITION COMBI COMBI LOWER SECTION INTO SHAFT ’ . .... _ .....__.. .- ”...,... ..__“_._~,___“ ... BRING SECTION & INSTALL CASING COMBI PIPE SECTION INSTALL ON GUARD RAIL 41 3 NORMAL CRANE RETURNS NORMAL JACK PIPE SECTION ‘ COMBI DISMANTLE CABLES & HOSES I 337.13r 99F COUNTER g - 339.1 9 COMBI ATTACH SECTION TO CRANE 340.1 341.7 ...... F""‘" .. ..- .- 40 NORMAL LIFT SECTION TO POSITION COMBI LOWER SECTION INTO SHAFT 345.4 10 COMBI BRING E SECTION & INSTALL 166 I" Iw " . I345.4E 36 ICONSOLIDATEI r-..__..... -——.~_._.—-._---.~., .... .... --.,—.....-— ... ___—— ....__.. ...-.- .- ._ ......nfi—v. CASING .. «4...... PIPE SECTION I I 371.7 5 I COMBI INSTALL ON E E GUARD RAIL I ’W CRANE I 373.7 41 E NORMAL E RETURNS W WW I " INSTALL& E3827 8 E COMBI CHECK AIR I GRIPPER Z I 382.7I 43 I NORMAL I DUMMY IW'WWWW WW“ W’WWW" "W ‘ I JACK PIPE , I I 389.4E 42 E NORMAL E SECTION I 389.4 I 37 KEONSOLIDATEI - N *w._ I'3'8‘9‘4 I 38 W I WONSOELIIDATE I" I DISMANTLE I I g HOSES I 396.8I 39 ICONSOLIDATEI - IW9'9W " IEWCOUWN'TERWI ‘DISCHARGE & 408.3 1 COMBI REFILL E DESANDMAN CW'WWIW'WW“ I EMPTY SPOIL 415.1 4 COMBI TANK .. " MIX 417.7 2 COMBI LUBRICATIONI " W "W ATTACH 419.7 9 COMBI SECTION TO 5 I CRANE LIFT SECTIONI 420.7 40 NORMAL To PosmONE * LOWER 422.1 6 COMBI SECTION INTOE SHAFT ‘ "W W“ BRING SECTION& . 423.3 10 COMBI INSTALL 1 CASING . I -_ W WWW PIPE SECTION I 499.9 5 COMBI INSTALL ON I GUARD RAIL CRANE 501.9 41 NORMAL RETURNS JACK PIPE 600.6 42 NORMAL SECTION I629.7I 3 I COMBI IDISMANTLE 167 168 I WIW WEWW"W W. CABLES& I I I I HOSES I62917I 99 ' I COUNTER I - W W WW ' ATTACH .. 631.7 9 COMBI SECTION TO CRANE I ILIFT SECTIONE 632.73 40 NORMAL ITOPOSITION‘; r- 1 LOWER 633.8 6 COMBI SECTION INTO SHAFT W W "WERI‘N'GW SECTION& 636.9 10 COMBI INSTALL CASING W W I W W PIPE SECTION 678.3 5 COMBI INSTALL ON GUARD RAIL . CRANE 680.3 41 NORMAL RETURNS W "IW' I“ WW WIXCEPIWPEW 742.0E 42 NORMAL SECTION . I W DISMANTLE 751.5E 3 COMBI CABLES& I HOSES IW751'.5I 99 I COUNTER I - I ATTACH 753.5 9 COMBI SECTION TO CRANE j ~ --~~-~ - -- r—wm-wé LIFT SECTION; 754.5 40 NORMAL To POSITION _ WW I LOWER I E 755.7 6 COMBI SECTION INTO I SHAFT ' W BRING SECTION& , 757.5 10 COMBI INSTALL CASING . _ PIPE SEC'I‘IONI 808.5 5 COMBI INSTALL ON GUARD RAIL -m--- ...... CRANE . 810.5 41 NORMAL RETURNS 2......“ .. 1“me 886.9 42 NORMAL SECUON DISMANTLE 898.1 3 COMBI CABLES& HOSES ..-r... I898W.1‘IWWW9W9W I COUNTER - I: " ' ’ W I ATTACH ; 900.1 9 COMBI I SECTION TO I CRANE 901.1 40 NORMAL Egggcrrrfilgg LOWER 902.2 6 COMBI ISECTION INTO 1 SHAFT ‘ W W WWW WWWWWWWW BRING 903.4 10 COMBI SFNCSTTIEEL‘Y‘ CASING . W W W PIPE SECTIONI 935.0 5 COMBI INSTALL ON GUARD RAIL 937.0 41 NORMAL RETURNS JACK PIPE 959.7 42 NORMAL SECTION IW9 9.7 IW37W ICONSOLIDATEI - W I 959.7I 38 'ICONSOIWIDATEI ’ 4 I I DISMANTLE 967.9: 3 COMBI CABLES& ‘ I I I HOSES I 967.9I 39 ICONSOLIDATEI - I 967.9 I" 99 I COUNTER I - ;. DISCHARGE&§ 982.1 1 COMBI REFILL DESANDMAN 992.9 4 COMBI EMPIFXNSIEOILI W MIX 993.3 2 COMBI LUBRICATION ATTACH .3 995.3 9 COMBI SECTION TO CRANE W W LIFT SECTION . 996.3 40 NORMAL To POSITION LOWER 997.3 6 COMBI SECTION INTO SHAFT W ' " BRING SECTION& 1003.4 10 COMBI INSTALL CASING . _~—_—-_._— . . ...,".-. - I1W00314WWI 36W ICONSOWLWIDWATEIWWW - 169 1031.3 COMBI PIPE SECTION INSTALL ON GUARD RAIL 1033.3} ’ NORMAL CRANE RETURNS 1046.1 COMBI INSTALL & CHECK AIR GRIPPER [1046.11 NORMAL 1056.5 1 NORMAL 1057.2’ ‘1 COMBI 1066.1 COMBI DISMANTLE CABLES & HOSES 1066.1 99 COUNTER f _ 1068.1 {I651 I 40 COMBI NORMAL ATTACH SECTION TO CRANE ‘ ’ifiéfiéfiiCfi TO POSITION 1070.8 COMBI LOWER SECTION INTO SHAFT 1071.7 COMBI BRING SECTION & INSTALL CASING 1120.9 COMBI PIPE SECTION INSTALL ON GUARD RAIL [1122.9 | 41 [ NORMAL CRANE RETURNS 111ml 42 NORMAL JACK PIPE SECTION 1195.2 COMBI DISMANTLE CABLES & HOSES 1195.2 99 [ COUNTER 1 - 1197.2 COMBI ATTACH SECTION T0 CRANE 1198.2 40 NORMAL LIFT SECTION TO POSITION ' 1 199.3 COMBI LOWER SECTION INTO SHAFT 170 —-,-.._. WWW.——.‘. BRING SECTION& 1203.8 10 COMBI INSTALL CASING 1 ‘ --. __-_,__.____.--____._._ PEESECI'ION 1234.4 5 COMBI INSTALL ON GUARD RAIL CRANE 1 1236.4 41 NORMAL RETURNS "M“ mm“ JACK PIPE 1261.8 42 NORMAL SECHON DISMANTLE 1271.2 3 COMBI CAELES& E HOSES ' _ “--.“.-- ..-...__.......___.---__-....__-.. “--.... ..-.-.1 11271.2( 99 I COUNTER [ - WW I ATTACH 1273.2 9 COMBI SECTION TO CRANE j 1 - LIFT SECTION; 1274.2 40 NORMAL TOPOSITION: ""7“ ‘ .-..-_..__.._-__.. LOWER 1275.7 6 COMBI SECTION INTOE SHAFT .. . , BRING 2.. SECTION& 1279.4 10 COMBI INSTALL CASING "PIPE SECTION; 1309.1 5 COMBI INSTALL ON g GUARD RAIL g CRANE L 1311.1 41 NORMAL RETURNS JACK PIPE 1335.6 42 NORMAL SECHON 11335.6( 37 [CONSOLIDATE }“ - ' [1335.61 38 ICONSOLIDATEI - I 1 I DISMANTLE 1 1343.9 3 COMBI CABLES& 1 HOSES [1343.9 [”39" iCONSOLIDATE] - 11343.91 99 I COUNTER I - DISCHARGE&% 1357.3 1 COMBI REFILL ~ DESANDMAN VEMPTY SPOIL ; 1367.0 4 COMBI TANK 3 1367.7 2 COMBI ”IRRIGATION: 171 1 " ATTACH 11369.7 9’ COMBI SECTION TO 1 CRANE ; IMM M ’ LIFT SECTION: 1370.7 40 NORMAL 1 mm. TOPOSITION 1 LOWER 1372.1 6 COMBI SECTION INTOf SHAFT ‘ ”MM MMM " MM M BRING ' SECTION& 1379.0 10 COMBI INSTALL CASING 1 PIPE SECTION1 1401.7 5 COMBI INSTALL ON ; GUARD RAIL MM" M CRANE 1403.7 41 NORMAL RETURNS W... , _ ”J‘ACK‘P'IPEI 1417.9 42 NORMAL SECTION 1 DISMANTLE 11425.2 3 COMBI CABLES& 1 , HOSES 11425.21 99 1 COUNTER 1 - .. _ ATTACH 1427.2 9 COMBI SECTION TO CRANE j LIFT SECTION; 1428.2 40 NORMAL To POSITION; LOWER 1430.0 6 COMBI SECTION INTO? SHAFT BRING SECTION& 1437.1 10 COMBI INSTALL CASING : 11437.11 ”36' [CONSOLIDATE 1 - 1 ' PIPE SECTION; 1460.3 5 COMBI INSTALL ON GUARD RAIL CRANE 1462.3 41 NORMAL RETURNS INSTALL& 1474.5 8 COMBI CHECK AIR ; GRIPPER 11474314? ‘1' NORMAL 1 DUMMY JACK PIPE 11478.21 42 1 NORMAL SECTION ? 11489.3 1"— 7 1 COMBI 1 ADJUST AIR 172 ; 1 1 . GRIPPER ; i i 1 ISISMANTLE 31496.9 3 i COMBI 1 CABLES& g 5 g HOSES i1496.9{ 99 i COUNTER { - ; ATTACH . 1498.9 9 COMBI SECTION TO CRANE " WWW ’ LIFT SECTIONi 1499.9 40 NORMAL To PosmONg .. .. .. 13 {£1.1qu , SECTION& 1501.2 10 COMBI INSTALL CASING LOWER . 1501.7 6 COMBI SECTION INTOE SHAFT j WW PIPE SECTION 1530.1 5 COMBI INSTALL ON g GUARD RAIL i ‘ CRANE ‘ E1532.1 41 NORMAL RETURNS : . ...... WIACEPIPEW 1543.4 42 NORMAL ‘ SECTION I " DISMANTLE 1550.4 3 COMBI CABLES& ' HOSES 1,1550TZ‘F 99 i COUNTER [ - " ATTACH 5 1552.4 9 COMBI SECTION TO CRANE j " W " LIFT SECTION": 1553.4 40 NORMAL To POSITION; " LOWER f 1554.4 6 COMBI SECTION INTO.§ SHAFT ' BRING SECTION& 1563.8 10 COMBI INSTALL CASING WWW " PIPE SECTION; 1583.8 5 COMBI INSTALL ON % GUARD RAIL 1585.8 41 NORMAL RETURNS JACK PIPE ! 1600.0 42 NORMAL SECTION {1600.0 F37 "'{CONSOLIDATE { - ' 173 $1600.0[ 38 [CONSOLIDATEJ - W W W ' ‘ WWW "DISMANTLE 1607.3 3 COMBI CABLES& HOSES 1607.3l 39 CONSOLIDATEI - {1607.3 99 I COUNTER l - DISCHARGE & 1619.7 1 COMBI REFILL DESANDMAN 1 ,. EMPTY SPOIL l16292l 4 { COMBI I TANK W MD( [16304 2 COMBI 'LUBRICATION ATTACH 1632.4 9 COMBI SECTION To CRANE LIFT SECTION 11633.4 40 [ NORMAL lTOPosmON LOWER 1635.3 6 COMBI SECTION INTO SHAFT BRING SECTION& 1638.2 10 COMBI INSTALL CASING PIPE SECTION 1667.4 5 COMBI INSTALL ON GUARD RAIL CRANE 1669.4 41 NORMAL RETURNS JACK PIPE 1699.3 42 NORMAL SECTION DISMANTLE 1706.7 3 COMBI CABLES& HOSES 1706.7 99 COUNTER - ATTACH 1708.7 9 COMBI SECTION To CRANE LIFT SECTION 1709.7 40 NORMAL To POSITION LOWER 1711.0 6 COMBI SECTION INTO SHAFT BRING SECTION& 1712.6 10 COMBI INSTALL CASING 174 --w— .. .-.—-.. g PIPE SECTION E17502 1 5 COMBI INSTALL ON 1 GUARD RAIL E1752. 2 41 NORMAL , E RETT JRNS . E E ' “" WW ‘" " WiAEIE‘EffiE" E1793 0 E 42 NORMAL SECHON E WE" W W DISMANTLE E1802. 5 3 COMBI CABLES & E E HOSES ‘18023 E 99 E COUNTER E - E " ' ATTACH 1804 5 9 COMBI SECTION TO CRANE " W LIFT SECTION 1805.5 40 NORMAL To POSITION W LOWER 1806.6 6 COMBI SECTION INTO SHAFT _..-_ , - ._- - BRING SECTION & 1807.3 10 COMBI INSTALL CASING E 1807.3 E W 36 ECONSOLIDATE - W PIPE SECTION 1857.9 5 COMBI INSTALL ON GUARD RAIL 1859.9 41 NORMAL Rgmmlfms WWW INSTALL & 1870.7 8 COMBI CHECK AIR E GRIPPER E1870.7‘E ' 43 ' E NORMAL DUMMY 1884.9 7 COMBI Aggggfizm JACK PIPE 1921.6 42 NORMAL SECTION WW W DISMANTLE 1936.0 3 COMBI CABLES & HOSES E19360 E 99 E COUNTER E - . ATTACH 1938.0 9 COMBI SECTION TO CRANE . W LIFT SECTION 1939.0 40 NORMAL To POSFHON .. LOWER . 1940.1 1 6 COMBI SECTION INTOE 175 “T1“ ‘1 sum _ " " " BRING 1 SECTION& 1948.8 10 COMBI INSTALL CASING E W WW " WPWIPWE SECTION E 1979.8 5 COMBI INSTALL ON E , GUARD RAIL WWW W W CRANE 1981.8 41 NORMAL RETURNS W W JACK PIPE W 2020.8 42 NORMAL SECTION E2620L8E " ' 37 ECONSOEIDATE E - . E20208E 38 ECONSOLIDATEE - E ‘W ' DISMANTLE 12031.1 3 COMBI CABLES& E HOSES " E2031.1E 39 ECONSOLIDATEE - E2031.1WE 99 E COUNTER E - 1 DISCHARGE &E 2043.1 1 COMBI REFILL DESANDMAN WWWWE W W EMPTY SPOIL 2048.7E 4 COMBI TANK E _. WWW.-- WWWWWWWW; 2050.4 2 COMBI LUBRIIVHXCATION ATTACH Q 2052.4 9 COMBI SECTION TO CRANE LIFT SECTIONE 2053.4 40 NORMAL To POSHION E LOWER E 2055.2 6 COMBI SECTION INTO SHAFT .-.,.--“ . BRING SECTION& 2062.8 10 COMBI INSTALL CASING . PIPE SECTIONE 2111.0 5 COMBI INSTALL ON E GUARD RAIL E CRANE i 2113.0 41 NORMAL RETURNS . WWW WW JACK PIPE 2178.3 42 NORMAL SECTION : W W W WWDWIWEMAWNTLE 2199.3 3 COMBI CABLES& E HOSES 176 .. v - - ._ -..—.--v ... . 5199.3"? 99 {W COUNTER : - . --.- “ATTACH 12201.3 9 COMBI SECTIONTO CRANE ‘ ‘ LIFT SECTION 2202.3 40 NORMAL TOPOSITION LOWER 2204.1 6 COMBI SECTION INTO: SHAFT ‘ -..--..-.- - BRING SECTION& 2205.4 10 COMBI INSTALL CASING . ’ PIPE SECTION; 2270.5 5 COMBI INSTALL ON GUARD RAIL g 2272.5 41 NORMAL RETURNS JACK PIPE 2359.0 42 NORMAL SECTION DISMANTLE 2374.4 3 COMBI CABLES& HOSES i §23‘74.4{ 99 l‘ COUNTER [ — ATTACH 2376.4 9 COMBI SECTION TO CRANE ‘ LIFT SECTIONS; 2377.4 40 NORMAL ToposmONE “W LOWER f 2378.5 6 COMBI SECTION INTO§ SHAFT W BRING SECTION & 2379.0 10 COMBI INSTALL CASING . PIPE SECTION~§ 2428.7 5 COMBI INSTALL ON GUARD RAIL CRANE 2430.7 41 NORMAL RETURNS JACK PIPE 2486.2 42 NORMAL SECTION WW DISMANTLE 2501.4 3 COMBI CABLES& g HOSES {2501.4[ 99 [ COUNTER I - 3 {2503.4 9 W '[ COMBI i ATTACH WE 177 WEWWWEWWW SECTION TO 1 E CRANE E25044E 40 NORMAL figgfiggSE . WW W LOWER E E25055 i 6 COMBI SECTION INTO =' E SHAFT ' E-..--__-.--- E.-.-__----, - ... BRING E : SECTION& E25086, 10 COMBI INSTALL E CASING E25086 E 36 ECONSOLIDATE - .- PEPE SECTION? 2557.4 5 COMBI INSTALL ON GUARD RAIL E CRANE 2559.4 41 NORMAL RETURNS INSTALL& 2569.5 8 COMBI CHECK AIR GRIPPER 25695E WE NORMAL E DUMMY 1 _ . - E SE ADJUST AIR E2582.E 3 E COMBI GRIPPER 1W W ‘E JACK PIPE E26207E42 E NORMAL E SECTION E2620. 7 W3 37 ECONSOLIDATEE - E26207E ECONSOLIDATEE W E E DISMANTLE 2629 IEW E COMBI CABLES & E E E E HOSES E2629.1E 39 ECONSOLIDATEE - E2629. WTE 99 E COUNTER E - DISCHARGE& 2639.9 1 COMBI REFILL DESANDMAN , EMPTY SPOIL 2643.9 4 COMBI TANK W W W MIX 2647.5 2 COMBI LUBRICATION ‘ E ' ' ATTACH 2649.5 9 COMBI SECTION TO CRANE W LIFT SECTION 2650.5 40 NORMAL To POSITION LOWER 2651.8 6 COMBI SECTION INTO SHAFT 178 E“ WE BRING E SECTION& 2661 2 E 10 COMB1 INSTALL E E CASING E E E ‘ ~§I~PE SECTIONE E2684 3 5 COMBI INSTALL ON E GUARD RAIL ..E. .-_.___.._. -..-.... CRANE .... E26863 41 E NORMAL RETURNS "WW" W ’ JAC‘IZIM’EEW 2706.9 42 NORMAL SECTION DISMANTLE 2715.5 3 COMBI CABLES & HOSES E2715.5E 99 E COUNTER E - 1 E ' ATTACH E27175 9 COMBI SECTIONTO E CRANE E E 1 LIFT SECTION; E27185 40 NORMAL To POSITION E" W LOWER E 2720.4 6 COMBI SECTION INTO Z SHAFT -; _ WBRING ‘ SECTION& 2721.6 10 COMBI INSTALL CASING E PIPE SECTION E 2754.9 5 COMBI INSTALL ON GUARD RAIL 1 E"—‘ 1 CRANE 2756.9 41 NORMAL RETURNS JACK PIPE 2810.7 42 NORMAL SECTION " ' ' DISMANTLE " 2818.7 3 COMBI CABLES & HOSES E2818.7E 99 E COUNTER E - _ ATTACH 2820.7 9 COMBI SECTION TO CRANE E W LIFT SECTION E 2821.7 40 NORMAL To POSITION E E ' LOWER E 2822.8 6 COMBI SECTION INTO; SHAFT ‘ BRING 2826.5 10 COMBI SECTION & 179 180 " W "WWW”WW WWW CASING 1 ' W 'W W W _ PIPE SECTION 2854.2 5 COMBI INSTALL ON GUARD RAIL ._. W NE ..... 2856.2 41 NORMAL RECITURNMS W - JACK PIPE 2883.2 42 NORMAL SECTION ¥ W DISMANTLE 2908.8 3 COMBI CABLES & HOSES I2908.8I 99‘ I COUNTER I - I W ATTACH g2910.8 9 COMBI SECTION TO I CRANE LIFT SECTIONI 2911.8 40 NORMAL To POSITION W W” WW I ” LOWER I 2913.1 6 COMBI SECTION INTO SHAFT BRINGW SECTION& 2921.0 10 COMBI INSTALL CASING I I PIPE SECTION; 2985.6 5 COMBI INSTALL ON GUARD RAIL W CRANE ' 2987.6 41 NORMAL RETURNS W W W JACK PIPE 3005.7 42 NORMAL SECTION I3005.7I 37 ICONSOLIDATEI - : I.3005 7I 38 ICONSOLIDATE I - ’ 3‘ DISMANTLE 3013. 0 COMBI CABLES & I HOSES I30130I 39 ICONSOLIDATEI WW I3013.0I 99 I COUNTER I - DISCHARGE&§ 3024.6 1 COMBI REFILL ‘ DESANDMAN IWW' ' W " EMPTY SPOIL 3031.9 4 COMBI TANK I .,____-____._._ _. MIX 3034.3 2 COMBI LUBRICATION I3036.3I 9 I COMBI I ATTACH ”WW" W3 SECTION TO 3 3 CRANE ’ W WW”— ‘ WEIFFSECI'IOIZIW 3037.3 40 3 NORMAL To POSITION 3 LOWER 3039.1 6 3 COMBI SECTION INTO 'f 3 3 SHAFT ; 3 BRING ,. SECTION& 3041.5 10 COMBI INSTALL CASING 33041.5 3 36 ECONSOLIDATE - 3 ’ ' PIPE SECTION; 33068.3 5 COMBI INSTALL ON 3 , GUARD RAIL 3 CRANE ' E3070.3 41 NORMAL RETURNS 3 INSTALL& _ 3078.7 8 COMBI CHECKAIR ; GRIPPER ' 33078.73 "43 3" "NORMAL 3 DUMMY _ _ ----“...,..- _ _. W‘WJWACIZ'PIPE .. 3163.3 42 NORMAL SECTION .1 DISMANTLE 3170.4 3 COMBI CABLES& ' HOSES 23170.43 99 3 COUNTER 3 - -. .... XfiXCfi ,. 3172.4 9 COMBI SECTION TO CRANE ; --——————- LIFI‘ SECTION 3173.4 40 NORMAL TomsmoM LOWER f 3174.7 6 COMBI SECTION INTO§ SHAFT " PIPE SECTION; 3203.1 5 COMBI INSTALL ON * GUARD RAIL 3205.1 41 NORMAL RECITURN‘AS 3218.7 42 NORMAL JACK PIPE SECTION DISMANTLE 3235.4 3 COMBI CABLES& ' HOSES 33235? [WPEIWCWOUNTERW ' 3' WW i 181 Simulation Results with CYCLONE Microtunneling Model with Soil Factor Enhancement: Simulation Run Times: 30 I APPENDIX F .fiIWCROTWI-JNNW fiftfié PROCESS INISIFFERENT S6113" PRODUCTIVITY INFORMATION l i W Sim Time ; Cycle No. [ Productivity Per Time [Init ;' 155.7 1 ; 0.006421 { 303.5 2 0.006589 [ 441.6 3 0.006793 i 550.5 4 {7 0.007267 { 702.9 5 1 , 0.0071 13 {WEEK'S—WW W "BWWWWWW 0.007215 W """"""" { 934.6 1 7 W ~i 0.007490 [ 1042.2 8 1"” 0.007676 ["Wifi—{STWW "if—WT WW 0.007852 { 1246.1 10 1 0.008025 _ 1' 1345.6 _ 11 1' 0.008175 { 1403.1 W WHEWWWKWW ‘ 0.058553 " W [ 1482.3 13 . 0.008770 W W ' _ { 1616.2 14 W37 0.008662 W 3" 1691.3 15 1 0.008869 [ 1762.8 16 i 0.009077 1 1887.1 17 { 0.009009 1‘ 1980.0 18 { 0.009091 1 2129.9 19 6 0.008921 i 2230.7 20 f 0.008966 { 2372.3 W 21 {r' 0.008852 [ 2546.8 22 g 0.008638 { 2679.9 23 0.008583 1 2822.2 24 1‘" W 0.008504 [ 2926.7 25 3 0.008542 2 3063.1 26 f 0.008488 ' 1‘ 3175.8 27" i 0.008502 ’ § 3304.1 28 '1’ 0.008474 { 3456.5 5 29 3' 0.008390 { 3541.3 30 i 0.008471 W ' 182 m_' EW MICROTUNNELING PROCESS IN DIFFERENT SOILS E PRODUCTIVITY INFORMATION E E Total Sim. Time Unit Cycle No. Pmdmm’“? (per ”me i E E umt) E 3541.3 30 E 0008471404967265655 E MICROTUNNELING PROCESS IN DIFFERENT SOILS E CYCLONE ACTIVE ELEMENTS STATISTICS INFORMATION f ActiWVity Access AVWcWranWe Maximum E MmImumW No Name Type Counts Duration Duration E Duration WWW DISCHARGE & E COMBI 1 REFILL 7 12.3 14.2 E 10.8 DESANDMAN WW WWWW MIX 1W WWWW COMBI 2 LUBRICATION 7 29.9 E 33.5 26.8 W WW DISMANTLEWWWWW COMBI 3 CABLES & 11 12.3 29.1 ‘ 7.2 HOSESI WWWWWWWWWWWW WWW EMPTY SPOIL W W COMBI 4 TANK 7 28.1 33.2 E 23.1 EWWW PIPE SECTION f E COMBI 5 INSTALL ON 30 41.9 77.8 28.4 E GUARD RAIL E E ‘ E LOWER W W 'W WW W W WWW; COMBI 6 SECTION INTO 30 1.4 2.0 1.0 SHAFT E E E .._._._._ ADIUST AIR ..... ... E ... _ - , COMBI 7 GRIPPER 4 13.2 14.8 . E 11.1 E W INSTALL & . W E E COMBI 8 CHECK AIR 6 12.5 14.8 10.3 GRIPPER = E ATTACH E' E ; COMBI 9 SECTION To 3o . 2.0 2.0 § 2.0 ? CRANE ! ___i- g WW BRING SECTION W W W E W W W W COMBI 10 & INSTALL 30 6.6 E 12.6 2.3 CASING . E E LIFT SECTION E E i NORMAL 40 To POSITION 30 E E 1.0 EWWWEWWWW CRANE W " W NORMAL 41 RETURNS 30 2.0 OEW 2.0 . 2.0 WWW JACK PIPE E E NORMAL 42 SECTION] 11 56.4 E 83 3 E 28.6 ENORMAL E43 E DUMMY 6 E 0.0 E o.W0WWW WWonoWWWW 183 EWWWWWWWWWWWEWWWW DISMANTLE E f ECOMBI E44 CABLES& E 8 E 12.7 29.1 7.2 E E HOSES2 E E E W E W E DISMANTLE E E E COMBI 45 CABLES& E 2 14.6 17.0 12.2 E 3 HOSES3 E E WWWWW E DISMANTLE E E COMBI ‘46 CABLES& E 9 12.3 29.1 7.2 E E HOSES4 E E ‘1 EWNWOWRMALEW 52E DUMMYl E 30 I 0.0 E 0.0 0.0 WWWWWW WWWW DUMMY SOIL ' NORMAL 53 TYPE CLAYEY 11 0.0 0.0 0.0 GRAVEL EWWW DUMMY SOIL WWWWWW'EW W WE NORMAL E 54 TYPE SAND 8 0.0 0.0 0.0 E DUMMY SOIL NORMAL 55 TYPE SILT 2 0.0 0.0 0.0 5 WWW DUMMY SOIL ‘ WWWWE {NORMAL 56 TYPE CLAY 9 0.0 0.0 . 0.0 E WWWWWWWWWWW W W JACK PIPE WWWWWW W - 1W W ENORMAL 57 SECTIONz 8 31.4 46.0 12.4 1 E JACK PIPEW . . ENORMAL E 58 SECTION 3 2 36.1 39.3 2 32.9 E EWWW JACK PIPE ENORMAL E 59 SECHON 4 9 71.9 92.0 24.1 MICROTUNNEITING PROCESS 1N DIFFERENfidifig‘“ - .. CYCLONE PASSIVE ELEMENTS STATISTICS INFORMATION W W WWWW Average Max. Times (V Total Average Units? Type No. Name Units Idle not I dWlWe Sim Wt at Idle Units empty Time Time end --.. SEWCTWIWOWNWWONW WW... .___..-___.. W... _. ._ QUEUE 11 STORAGE! 14.4 30 3323.5 93.85 3541.3 799.5 0 E... POSITION E QUEUE 12 AVAILABLE 0.0 1 0.0 0.00 3541.3E 0.0 1 WWW”... r..- __ “E---“ QUEUE 13 “$23". 0.8 1 2863.7 80.87 3541.3 367 1 ... --.... “HEW“..- ...,-"W -_ ._ -..- __ E OUEUE 14 SUPSWWRVISOR 0.5 1 1693.2 47.81 3541.3 21.7 E 1 IDLE E W W AIRGRIPPER "" E GEN 15 READY 3.5 6 3456.5 97.60 3541.3 372.3 1 5 EWWUWWWEUWEWEW1W6WECRANEIDLE E 0.6 E 1 E1996.8E56..38E35413E 64.4 W WW1WWWW EQUEUEEWE (33113113? E 0.0 E 1 E1391 E3.93E3541.3EWWW 45 E 1 184 EWWWWWWWWWWE LABORB WWWE WWWWEWWWWWWE ‘W E EQUEUEE 1WW8WE IDLE 0.5 E 1 E17788E5023W E35413E 182 E 1 EUBUBE19 TRUCKIDLE EWW 0.9 E 1W E3122.3E88.1.7E35413E 390.3 a 1 QUEUE 20 “Egg” E 0.9 ‘ 1 3122.3 88.17 3541.3E390.3 1 E . E W [WW F r i 1 LUBRICATION E GBN E21 READY E 1.6 4 2657.2 75.03 3541.3.! 167.5 2 EWWWWWWWWWEWWW W EWW—WWW WWWWWW‘WW-WEW WWW—l QUEUEEZZ BESETESETE 0.9 1 3112.3 87 88 E35413 389.0 1 --._.__..._...__.._.r---.... JACKING .. N--- .. .wm EWW . _E- -. QUEUE 23 SYSTEM IDLE 0.1 1 316.4 8.93 3541.3E 10.2 E 1 ‘w I'm “‘T"”"" r “ “"7 QUBUB 24 $155 0.1 E 1 230.4 6.51 3541.3E 6.1 E 1 WWWWWWWW NEED AIR E W E - E QUEUE 25 GRIPPER 0.1 E 1 180.6 5.10 3541.3E 30.1 E 0 ---... .. E“ GRIPPER .. ._ ... E QUEUEE26 NEED ADJUST 0.0 E 1 0.0 0.00 3541.3E 0.0 E 0 WWW E SPOIL TANK W E E GEN E27 NOTFULL 1.6 4 2669.6 75.38 3541.3E 168.9 E 2 E“ I POSITION E QUBUBE E 28 OCCUPIED 0.9 1 3201.0 90.39 3541.3E 106.7 0 WWWWEWWWW SECTION WWWWW E E OUBUBE29 READY 0.0 1 35.3 1.00 E35413E 1.2 0 WE SECTION“- E _- ._._ .___,-._--_.-_ - E __ . ._ .. .--.-- QUEUEE 30 0.0 1 9.5 0.27 3541.3E 0.3 0 ‘ E-—~—~ RBADY E E QUEUE 31 SP 01:53?“ E0 1 0.0 0.00 3541.3 0.0 0 W WWWWWWW NBBD E . W E QUEUE 32 LUBRICATIONE 0.0 1 0.0 0.00 3541.3 0.0 E 0 E .... DESANDMAN _ -..... ....... EWW . . QUEUE 33 READY To 0.0 1 0.0 0.00 3541.3; 0.0 0 . DISCHARGE E E‘-"“ r SBCTIONIN E E QUBUB 34 0.0 1 0.0 0.00 35413 0.0 0 ...—~— PLACB1 V E E CABLB HOSE QUBUB 35 LASBR 0.1 1 316.4 8.93 3541.3 10.2 1 RBADY WWW SBCTIONIN QUBUB 47 PLACB2 0.0 1 0.0 0.00 3541.3 0.0 0 QUBUB 48 Siflggf 0.0 1 0.0 0.00 3541.3 0.0 0 QUBUB 49 Siflggm 0.0 1 0.0 0.00 3541.3 0.0 I 0 185 ' MICROTUNNELING PROCESS IN ' " ' i I l ) DIFFERENT SOILS ; TRACE INFORMATION Sim” Activity " Time NO. Type Name . m , BRING . SECTION& 4.9 10 COMBI INSTALL CASING ATTACH ; 6.9 9 COMBI SECTION TO ' CRANE ' LIFT SECTION 7.9 40 NORMAL To POSITION LOWER 9.1 6 COMBI SECTION INTO i SHAFT ‘ BRING ' SECTION& 19.5 10 COMBI INSTALL CASING * ”.-..-.” ”WW W PIPE SECTION 67.3 5 COMBI INSTALL ON GUARD RAIL [67.3 I 52 I NORMAL [ DUMMYI W-..“ ... -.D SOIL 67.3 53 NORMAL TYPE CLAYEY GRAVEL 69.3 41 NORMAL RECITURNMS JACK PIPE 138.7 42 NORMAL SECTION] DISMANTLE 155.7 3 COMBI CABLES& HOSESI {155.7f 99 I COUNTER [ - ATTACH . 157.7 9 COMBI SECTION TO CRANE j LIFT SECTION 158.7 40 NORMAL To PosmON r LOWER 160.7 6 COMBI SECTION INTO§ SHAFT ' -----.m. - . -. BRING SECTION& 168.0 10 COMBI INSTALL CASING 186 I I I PIPE SECTION; 32073 I 5 I COMBI INSTALL ON I I I GUARD RAIL 52207.3" I" 52 I NORMAL I DUMMYI ' DUMMY SOIL 207.3 56 NORMAL TYPE CLAY I" W CRANE 209.3 41 NORMAL RETURNS I JACK PIPE 1286.5 59 NORMAL SECTION 4 I * DISMANTLE I 303.5 46 COMBI CABLES & I HOSES4 I303.5 I 99 'I COUNTER I - I ' ATTACH I 305.5 9 COMBI SECTION TO , CRANE I“ W F LIFT SECTION I 306.5 40 NORMAL To POSITION I LOWER 1 308.3 6 COMBI SECTION INTO E ’ SHAFT BRING SECTION& 313.0 10 COMBI INSTALL CASING . PIPE SECTION , 337.4 5 COMBI INSTALL ON .. GUARD RAIL I3374 I 52 I NORMAL DUMMYl I ...- DUMMY SOIL 337.4 56 NORMAL I TYPE CLAY {L i CRANE 339.4 41 NORMAL RETURNS JACK PIPE 429.4 59 NORMAL SECTION 4 W " WW DISMANTLE 441.6 46 COMBI CABLES & HOSES4 I I441.6I 50 ICONSOLIDATEI - I4416 I 99 I COUNTER I - ...,--.me -.. L ATTACH - 443.6 9 COMBI SECTION TO _ ~ CRANE " LIFI‘ SECTION : “4'6 4O Nom'mL TO POSITION I449.9 I 10 I COMBI I BRING I 187 188 IW I I WI SECTION & I I I CASING {4499 I 36 rCONSOLIDATE; - ; D1SCHARGE&; 453.1 1 COMBI REFILL ; DESANDMAN 7 LOWER ; 454.6 6 COMBI .SECTION INTOI I SHAFT 7 ‘7 INSTALL& I 464.2 8 COMBI I CHECK AIR I GRIPPER I464.2 I 43 I7 NORMAL I DUMMY 2 I I PIPE SECTION I I494.2 5 COMBI INSTALL ON I . I GUARD RAIL I I494.2 I 52 I NORMAL I DUMMYI I DUMMY SOIL 494.2 i 55 NORMAL TYPE SILT 496.2 I 41 NORMAL 51m“ ‘NES I 7 JACK PIPE 533.4 58 NORMAL SECHON3 . B33147 37 ICONSOLIDATEI - I533. 4 I ICONSOLIDATEI - I I DISMANTLE I550.5 45 COMBI I CABLES& ‘ I . I HOSES 3 5505 I 99 I COUNTER I - I--- - . ...,...“ -- ---..._._.. 559.2 4 COMBI EMITIANKWOIL 2 MIX 5 561.7 2 COMBI LUBRICATION ATTACH 563.7 9 COMBI SECTION TO CRANE I "7777 LIFT SECTION 564.7 40 NORMAL To PosmON I LOWER , 566.2 6 COMBI SECTION INTO SHAFT ' BRING 567.3 10 COMBI SfinggEL‘g‘ CASING I I644.0 I 5 I COMBI IPIPE SECTION .. WWW- ...—”.....- ..- I. . ....-- l I INSTALL ON I . I . I I IGUARD RAIL I 644.0 I 52 ' I NORMAL I DUMMYI : DUMMY SOIL 644.0 54 NORMAL “TESIHE -. 7 W CRANE 646.0 41 NORMAL RE“ I“ Is " JACK PIPE 685.9 57 NORMAL SECTION 2 .m I , WW... "DEM‘AWNTLE 702.9 44 COMBI CABLES& ‘ HOSES 2 I 702.9 I 51 ICONSOLIDATEIW . I 702.9 I 99 I COUNTER I - IWW" """ - ATTACH I 704.9 9 COMBI SECTION TO 1 CRANE I " LIFT SECTION . 705.9 40 NORMAL To POSITION ‘ LOWER I 707.0 6 COMBI SECTION INTO SHAFT '77 7' 7 ' BRING SECTION& 710.1 10 COMBI INSTALL CASING ‘ PIPE SECTION 751.5 5 COMBI INSTALL ON GUARD RAIL 751.5 I 52 I NORMAL DUMMYI DUMMY SOIL 751.5 53 NORMAL TYPE CLAYEY . GRAVEL ' ‘ CRANE 753.5 41 NORMAL RETURNS -.." --.. . JACK PIPE i819.4 42 NORMAL SECTION 1 7 DISMANTLE 831.6 3 COMBI CABLES& . . HOSESl I 831.6 I 99 I COUNTER - ..-._.___..._ I. _. ._ ATTACH I 833.6 9 COMBI SECTION TO CRANE I LIFT SECTION? 834.6 40 NORMAL To POSITION I I835.8I 6 I COMBI I LOWER 189 " ' " " M" W MHFSEETION INTO SHAFT ‘ i " " ’ “ BRING 1 SECTION& 837.7 10 COMBI INSTALL ; CASING ' ”PDESECTION g $888.6 5 COMBI INSTALL ON § GUARD RAIL {—888.6T ' 52 [ NORMAL [ DUMMYl . r““"*"r‘"'“’“‘"’* ""“ 3 i, DUMMY SOIL % 888.6 54 NORMAL TYPE SAND 1 §._....._..-.._. ...- _ W... . ...WW..___._-.-. r‘mMC—‘m‘Efl-vé 3 890.6 41 NORMAL RETURNS "WWW” ___-“ ...- JACK PIPE . i922.3 57 NORMAL SECHONZ. l’ T DISMANTLE ; 934.6 44 COMBI CABLES & ‘ i HOSES 2 % 5934.6 { '99 ’ T COUNTERM'I' W ' ' " mm ' """ATTACI‘IW 936.6 9 COMBI SECTION T0 CRANE i LIFT SECTION 937.6 40 NORMAL To POSITION i LOWER 938.7 6 COMBI SECTION INTO ? SHAFT ’ 1‘ BRING SECTION & 939.9 10 COMBI INSTALL CASING ‘ ‘ PPIPESECEENH 971.5 5 COMBI INSTALL ON GUARD RAIL 1971.5 [ 52 { NORMAL l DUMMYI ' DUMMY SOIL 971.5 53 NORMAL TYPE CLAYEY GRAVEL CRANE 973.5 41 NORMAL RETURNS JACK PIPE 1035.0 42 NORMAL SECTION] [1035.0 F37 |CONSOLIDATE I - |1035.o[ 38 [CONSOLIDATE{ - WW- -- W ‘DISMA B 1042.2 3 COMBI CABLES& I HOSESI _ .. . . ..-” ... .... 190 E10212T2'EW 51 ECONSOLIDATEE - E10422 E '99 E COUN‘ TER i - E10422§ W50 ECONSOLIDATEE - 7W“- W" DISCHARGE & E1056.4E 1 COMBI REFILL ; 3 ‘1 DESANDMAN E " EMPTY SPOIL TANK £10685 2 COMBI LUBRICATION i ATTACH g1070.5 9 COMBI SECTION TO 1 CRANE l 1 .1 ...... .— {WW—h . 31068.2E 4 COMBI ~.. _ .— . ~.4-._..._-_ -..1 1' LIFT SECTION"; E10715 40 NORMAL ToposmON : LOWER 3 E10726 6 COMBI SECTION INTO ' E SHAFT 7 BRING E10786 10 COMBI SECTION‘g‘ 1 INSTALL i CASING 1078.6E 36 ECONSOLIDATEE - _ ' PIPE SECTION INSTALL ON E GUARDRAIL E : COMBI 11106.6 5 1r ...“ . 1.. -—-——.--.—~- A i i . I E11066] 52 E NORMAL E DUMMYl . " WE DUMMY SOILié 1106.6 1 53 NORMAL TYPE CLAYEY E E GRAVEL CRANE RETURNS INSTALL& 1121.3 8 COMBI CHECKAIR GRIPPER E11213E43 [WNORMAL E DUMMY W ADJUST AIR GRIPPER 1108.6 41 NORMAL 1 132.4 7 COMBI "W" W JACK PIPE 1138.8 42 NORMAL SECHON 1 DISMANTLE 1146.2 3 COMBI CABLES & HOSES I .. ...- - . ... ...—........-..-.-.A....-......-.....-...."......" ........,... ......fl...._..._......... . -... .... .... ......4....._...... .. -... uh .......... ...-..“ ATTACH COMBI . SECTION TO ' E CRANE = . .... .... .. . .. , ._ "...,. ___,__.. . ...,. . .-. -..—-....—....--——..~.—-. .. ....-._. ...,. --..— .- -- --. V... ...-W-..- M....._ ... ....-l E1146.2E 99 E COUNTER . ...-...1 1 ,1148.2{ 9 191 WWWW' W WWWWWWWWW W'LIFT SECTIONWE E11492 40 E NORMAL To POSITION W W ‘ LOWER E1150.8 6 E COMBI SECTION INTO i SHAFT W' E ' WWWW BRING SECTION& E11518 10 COMBI INSTALL E CASING W W W PIPE SECTIONE {1201.0 5 COMBI INSTALL ON E E ' GUARD RAIL EW2WW10EW 52 E NORMAL F DUMMYI E ' DUMMY SOIL E12010 55 NORMAL TYPE SILT EWWWWW W W CRANE E12030 41 NORMAL RETURNS ‘WWWWW WW W WW JACK PIPE E12339 58 NORMAL SECTION 3 E ” W DISMANTLE E1246.l 45 COMBI CABLES& E E HOSES3 E1246.1E 99 E COUNTER E - E W W WWW WW ATTACH f 1248.1 9 COMBI SECTION TO LIFT SECI‘IONE 1249.1 40 NORMAL To PosmON E W LOWER 1250.2 6 COMBI SECTION INTO 1 SHAFT ‘ ' W‘ W ' W W BRING ' E SECTION& 1254.7 10 COMBI INSTALL CASING PIPE SECTIONW 1285.3 5 COMBI INSTALL ON GUARD RAIL E1285.3E 52 E NORMAL E DUMMYI W DUMMY SOIL 1285.3 53 NORMAL TYPE CLAYEY GRAVEL ‘ E ..W... ___mmflmu CRANE 1287.3 41 NORMAL RETURNS JACK PIPE 1316.5 42 NORMAL SECHONE WWWW DISMANTLE 1345.6 3 COMBI CABLES & 192 NORMALWWWW EWWIWJWUMMY 1 ' E W E" _ WE WWWW EWWWWIWiOWSWESWWIWWWWW E1345.6E 5W1 ”ECONSOLIDATEE - EW1W345.6E 99 E COUNTER E - WW ATTACH 1347.6 9 COMBI SECTION TO CRANE ' 'WWWWWW WLIFT SECTIOWNWE 1348.6 40 NORMAL To POSITION: WWWWWW E WWWLWOWWWERWWWWE 1350.1 6 COMBI aSECI‘ION INTOE E SHAFT “ WW W BRING SECTION& 1353.8 10 COMBI INSTALL . CASING E r PIPE SECTIONE 1383.5 5 COMBI INSTALL ON GUARD RAIL “m” ___-....-. DUMMY SOIL 1383.5 54 NORMAL TYPE SAND . CRANE 1385.5 41 NORMAL RETURNS ............ --....“ JACK PIPE 1395.9 57 NORMAL SECHONZ 11395-9E 37 ECONSOLIDATEE - E13959E 38 ECONSOLIDATEE - E ' DISMANTLE 1403.1 44 COMBI CABLES& E HOSE82 ‘ E1403:1E 99'WE' ””COWUNTERW E W - EMPTY SPOIL 1427.3 4 COMBI TANK 1 MIX 1 1427.9 2 COMBI LUBRICATIONE ATTACH 2 1429.9 9 COMBI SECTION TO CRANE E LIFT SECTIONE 1430.9 40 NORMAL ToposmON s LOWER . 1432.3 6 COMBI SECTION IN'I‘OE SHAFT E BRING . SECTION& 1439.3 10 COMBI INSTALL CASING 193 194 i i; 1 1 1 1 1 PIPE SECTION 114619 5 1 COMBI INSTALL ON 1 1 GUARD RAIL 1146191 52 1 NORMAL F DUMMY 1 1 DUMMY SOIL 1461.9 54 NORMAL TYPE SAND CRANE 1463.9. 41 NORMAL RETURNS .._____-____._.1____ JACK PIPE 1474.9 57 NORMAL SECTION 2 1 -- w DISMANTEEWE 1482.3 44 COMBI CABLES & HOSES 2 11482. 31 99 ”'1'_COUNTER 1 - 1 ATTACH 1 1484.3 9 COMBI SECTION TO CRANE 1 1..- --.,-.. W L 1 LIFT SECTION 1485.3 40 NORMAL To POSITION - 1 . .‘ __ -... -- .- ”LOWER I1487. 1 6 COMBI SECTION INTO 1 , SHAFT ' 1 1 1 BRING SECTION & 11494. 2 1o COMBI 1 INSTALL 1 1 CASING H494. 2 13 36 1CONSOLIDATE 1 - 1 1 1 M .....- PIPE SECTION 1 11517.4 .. COMBI INSTALL ON f 1 151 GUARD RAIL 11517.41 52 1 NORMAL 1 DUMMYI 1 DUMMY SOIL 1517.4 56 NORMAL TYPE CLAY . CRANE 1519.4 41 NORMAL , RETURNS ’ ' ‘ INSTALT: & ' 1531.5 8 COMBI CHECK AIR GRIPPER 11531.51 43 1 NORMAL 1 DUMMY . ‘ ADIUST AIR 1546.3 7 COMBI GRIPPER .... WWW" " " JACK PEE' 1609.0 59 NORMAL SECHON 4 DISMANTLE 1616.2 46 COMBI CABLES & HOSES 4 11616.21 50 1CONSOLIDATE1 - 1 11616.2 1 11618.2 99 1 COUNTER 1 COMBI I' I 'WXTTACTI " 2 SECTION TO CRANE 11619.2 40 1 NORMAL LIFT SECTION TO POSITION 1620.5 COMBI BRING SECTION & INSTALL CASING 1629.6 COMBI DISCHARGE & REFILL DESANDMAN 1631.4 COMBI LOWER SECTION INTO SHAFT 1659.8 COMBI PIPE SECTION INSTALL ON GUARD RAIL 1659.8 52 NORMAL 1 DUMMYl 11659.8 56 1 NORMAL DUNE/TY SOIL TYPE CLAY 1661.8 41 NORMAL CRANE 1683.8 59 NORMAL JACK PIPE 1 1 RETURNS 1 SECTION4 1691.3 46 COMBI DISMANTLE CABLES & HOSES 4 1691.3 99 COUNTER 1693.3 COMBI ATTACH SECTION TO CRANE 1694.3 40 NORMAL LIFT SECTION TO POSITION 1695.3 COMBI LOWER SECTION INTO SHAFT 1704.6 COMBI BRING SECTION & INSTALL CASING 1724.6 COMBI PIPE SECTION INSTALL ON GUARD RAIL 1724.6 NORMAL 1 DUMMYI 11724.6 1 53 NORMAL DUMMY SOIL TYPE CLAYEY 195 ..., j GRAVEL 1 1 " ; CRANE 1172661 41 NORMAL 1 RETURNS 1 I * JACK PIPE 11753.31 42 1 NORMAL SECTIONI 11753.3 1”. 37 1CONSOLIDATE1 - 11753.3W1' 38 1CONSOLIDATE1 - 1 1 DISMANTLE 1762.8 3 COMBI CABLES& 1 , HOSESI 11762.81 51 1CONSOLIDATE1 - 11762.81 99 1 COUNTER 1 117628151CONSOLIDATE1 ’ - DISCHARGE& 1775.2 1 COMBI 1 REFILL DESANDMAN EMPTY SPOIL 1782.5 4 COMBI TANK . 1783.6 2 COMBI LUBRICATION1 ATTACH ‘ 1785.6 9 COMBI SECTION TO CRANE LIFT SECTION 1786.6 40 NORMAL To POSITION 3--.“... ... LOWER 1788.5 6 COMBI SECTION INTO SHAFT "W WW BRING SECTION& 1791.4 10 COMBI INSTALL CASING PIPE SECTION 1820.6 5 COMBI INSTALL ON GUARD RAIL 11820.61 52 1 NORMAL DUMMYI " DUMMY SOIL 1820.6 56 NORMAL TYPE CLAY CRANE 1822.6 41 NORMAL RETURNS JACK PIPE 1858.0 59 NORMAL SECTION 4 - DISMANTLE 1887.1 46 COMBI CABLES& HOSES4 1 11887?le 99 '1 COUNTER - 196 1893.0 ”*— 1930.6 COMBI ATTACH CRANE NORMAL COMBI COMBI 1 ”LOWER SHAFT BRING SECTION & INSTALL CASING SECTION TO LIFT SECTION TO POSITION 5 COMBI 11930.61 52 1930.6 54 NORMAL NORMAL 1DUMMY1 TYPE SAND 1932.6 1950.9 1980.0 . . "...—”...-..— y 41 NORMAL 57 44 NORMAL Fem... .COMBI CRANE RETURNS SECTION 2 CABLES & HOSES 2 11980.01 99 COUNTER 1982.0 9 COMBI I 1 - 1 ATTACH CRANE 1983.0 40 NORMAL LIFT SECTION TO POSITION 1 1984.1 COMBI LOWER SECTION INTO SHAFT 1984.7 10 COMBI BRING SECTION & INSTALL CASING 11984.71 36 1CONSOLIDATE 1 — 2035.4 126334” 152 5 COMBI 1 INSTALL ON 1“”‘NO'RM‘A‘L1 1DUMNIYT PIPE SECTION GUARD RAIL JACK PIPE * 1"DISMANTEE" SECTION TO 1 1 1 1 I I I I I I I 1 é ,1 DUMMY SOIL 2035.4 53 NORMAL TYPE CLAYEY ' GRAVEL CRANE 2037.4 41 NORMAL RETURNS 197 1 SECTION INTO PIPE SECTION INSTALL ON GUARD RAIL DIM 3? SOIL” 1 1 1 INSTALL& 12048.2 8 ' COMBI CHECK AIR 1 1 1 GRIPPER , 120148121143"?111—NORMAL 1 DUMMY ”"1"" ADJUST AIR 12062.3 7 COMBI GRIPPER . 2118.7 42 NORMAL SECIEICNE DISMANTLE 2129.9 3 COMBI CABLES& 1 HOSESI 1212991991 COUNTER - MW" " ..- ATTACH 2131.9 9 COMBI SECTION TO CRANE 1 LIFT SECTION1 2132.9 40 NORMAL W“ ”___..-” .. TO POSITION 1 LOWER 1 2133.9 6 COMBI SECTION INTO§ SHAFT 1 1 . ”BRING 2142.6 10 COMBI 85312:? CASING PIPE SECTION; 2173.7 5 COMBI INSTALL ON GUARD RAIL 12173.71 52 1NORMAL 1 DUMMYl 1 DUMMY SOIL1 12173.7 53 NORMAL TYPE CLAYEY; 1 GRAVEL ' 1 12175.7 41 NORMAL RECAUfis 2222.5 42 NORMAL g‘ggglggl‘i 12222.51 37 1CONSOLIDATE1 - 1 12222.51 38 1CONSOLIDATE1 - ' DISMANTLE 2230.7 3 COMBI CABLES& ' HOSESI 12230.71 51 1CONSOLIDATE1 - 12230.71 99 1 COUNTER 1 - ' 1230.71 50 1CONSOLIDATE1 - 1 DISCHARGE&; 2242.8 1 COMBI REFILL 1 DESANDMAN; 12250.41 4 1 COMBI 1EMPTY SPOIL1 198 TANK LUBRICATION COMBI ATTACH SECTION TO CRANE 2264.5 2312.7 NORMAL TO POSITION t LIFT SECTION 3 COMBI COMBI LOWER SECTION INTO SHAFT‘ 1 SECTION & INSTALL 1 CASING COMBI PIPE SECTION INSTALL ON 1 12312.71 2312.7 2314.7 1 NORMAL GUARDRAIL1 1 DUMMYI 1 DUMMY SOIL TYPE CLAY RETURNS 2362.8 JACK PIPE SECTION 4 2372.3 12372.3 1” 99 COMBI 1 COUNTER DISMANTLE CABLES & ' HOSES 4 -1 - 2374.3 COMBI ATTACH 1 SECTION TO CRANE 2375.3 40 NORMAL LIFT SECTION TO POSITION 2377.1 10 COMBI COMBI LOWER SECTION INTO 1 SHAFT BRING SECTION & INSTALL CASING 1 I COMBI PIPE SECTION INSTALL ON GUARD RAIL 52 1 NORMAL 1 DUMMYI 56 41 1 NORMAL ”NORMAL DUMMY SOIL TYPE CLAY 1 CRANE 199 5' E W{ E RETURNS E . I ,. , "'JXCRPIPE 32535.6; 59 NORMAL SECTION4 {WWW W DISMANTLE I2546.8I 46 COMBI CABLES& ‘ l I HOSES4 3337168 {W50W1CONSOLIDATE i - 32546.“ 99 [ COUNTER. { - [WW ' ATTACH g2548.8 9 COMBI SECTION TO 1 CRANE . {WWW W W LIFT SECTIONE 32549.8 40 NORMAL To POSITION : BRING ’ SECTION& 2551.3 10 COMBI INSTALL CASING W' 'W W ' DiSCHARGE&E 2557.6 I COMBI REFILL DESANDMAN "W W WWW WWLOIX/ERW 2558.7 . 6 COMBI SECTION INTO ; SHAFT ; PIPE SECTIONE 2608.9 5 COMBI INSTALL ON ; GUARD RAIL 5&3??in NORMAL { DUMMYl WWWWWW W ” WISUMMWYWSWOIII E 26089 53 NORMAL TYPE CLAYEY GRAVEL ' WW CRANE . 2610.9 41 NORMAL RETURNS JACK PIPE ‘ 2670.9 42 NORMAL SECTION] .. DISMANTLE 2679.9 3 COMBI CABLES& ‘ HOSESI E2679.9E 99 [ COUNTER i - W ATTACH 2681.9 9 COMBI SECTION TO CRANE LIFT SECTION 2682.9 40 NORMAL To POSITION 'W LOWER 2683.9 6 COMBI SECTION INTO SHAFT ..... ; BRING 2687.1 10 COMBI SECTION & 200 INSTALL WWW 3 3 CASING 32687.1 3 36 3CONSOLIDATE‘ - WW ‘PIPE SECTION ‘ 2735.8 3 5 COMBI INSTALL ON E '1 GUARD RAIL 32733. 38 52 3 NORMAL 3 DUMMY 1 3 W W ' DUMMY SOIL 32735. 8 53 NORMAL TYPE CLAYEY 3 GRAVEL 12737 8 41 NORMAL RECITURNMS 3W INSTALL & 32747. 9 8 COMBI CHECK AIR 3 GRIPPER 32747 9 3 43 3 NORMAL 3 DUMMY W ADIUST AIR ‘2760. .7 E 7 COMBI GRIPPER 3 WWW JACK PIPE E2807.6E 42 NORMAL SECTION 1 32807.6 3W 37 3CONSOLIDATE 3 - 32807.6 3 38 3CONSOLIDATE 3 - . ' W W W i DISNWIWANTWLEW 2822.2 3 COMBI CABLES & 3 HOSES 1 32822. 2 3 99 3 COUNTER 3 - WW WWW WW'WW EMPTY SPOIL 2830.8 4 COMBI TANK 2834.4 2 COMBI LUBRIMWCAWTION . ATTACH 2836.4 9 COMBI SECTION TO CRANE LIFT SECTION 2837.4 40 NORMAL T0 POSITION LOWER 2838.7 6 COMBI SECTION INTO SHAFT BRING SECTION & 2848.1 10 COMBI INSTALL CASING PIPE SECTION 2871.2 5 COMBI INSTALL ON GUARDRAIL 32871.2 3 52 3 NORMAL 3 DUMMY 1 32871.2 3 54 3 NORMAL 3DUMMY SOIL 201 v- 41.....- ...... 202 3 3 3 3 TYPE SAND 32873.2 41 NORMAL RETURNS 3 JACK PIPE 32917.2 57 NORMAL SECTION2 3 DISMANTLE 32926.7 44 COMBI CABLES & 3 3 HOSES 2 32926.73 51 W 3CONSOLIDATE3 - 32926.7 3 W 99 " 3 COUNTER 3 - I ATTACH 2928.7 9 COMBI SECTION TO CRANE 3 LIFT SECTION 3 2929.7 40 NORMAL To PosmON 3 WW LOWER ’ 2931.6 6 COMBI SECTION INTO SHAFT WW BRING . SECTION& 32932.8 10 COMBI INSTALL CASING 3 PIPE SECTION 32966.1 5 COMBI INSTALL ON 3 3 GUARD RAIL 32966.13 52 3 NORMAL DUMMYI .............. ,. ‘ DUWMWMYWSOILW 32966.1 56 NORMAL TYPE CLAY CRANE 2968.1 41 NORMAL ”mm Is JACK PIPE 3054.9 59 NORMAL SECTION 4 DISMANTLE 3 3063.1 46 COMBI CABLES & ‘ HOSES4 33063.13 50 3CONSOLIDATIWEW3 - 33063.13 99 3 COUNTER 3 - WW ATTACH 3065.1 9 COMBI SECTION TO CRANE LIFT SECTION 3066.1 40 NORMAL . To POSITION 3 BRING SECTION& 3070.9 10 COMBI INSTALL CASING 33074.7 3 1 3 COMBI 3DISCHARGE & 3 I I MMI REFILL , IIDESANDMANQ I'M ' 'M ’ M LOWER I3075 8 6 COMBI SECTION INTO I SHAFT I ’ M M PIPE SECMTION I3107.2 5 COMBI INSTALL ON I GUARD RAIL I31072I 52 I "NORMAL DUMMYI . I MPMM DUMMY SOIL 3107 2 53 NORMAL TYPE CLAYEY I . GRAVEL ' I3 109. 2 41 NORMAL RECTURNMS I JACK PIPE I3166.5 42 NORMAL SECHON 1 I I DISMANTLE 3175.8 3 COMBI CABLES & I I HOSESI I31175. 8I 99 I COUNTER I - I ' " M " M MAHAEI’IMM 3177.8 . 9 COMBI SECTION TO CRANE ; LIFT SECTION 3178.8 40 NORMAL To POSITION ' LOWER 1 3180.2 6 COMBI SECTION INTO SHAFT I BRING I3188.1 10 COMBI Sgggf‘ CASING I PIPE SECTION 3252.7 5 COMBI INSTALL ON GUARD RAIL I3252.7IM52 I NORMAL I DUMMYl . I3252. 7 54 NORMAL DTYPUWE“; £131?“ I .. __ __....__._....__._. E I3254' .7 41 NORMAL Rfiélmhu IS I JACK PIPE 23292' .9 57 NORMAL SECHON 2 I3292.9I 37 ICONSOLIDATEI - I3292.9I 38 ICONSOLIDATEI - I DISMANTLE 33304.1 44 COMBI CABLES & ‘ I ,. 1 HOSES 2 203 M MMIM COUNTER “PM...“ “W ~u—. - uv..- -I-‘m .' I I - I I I 1 EMPTY SPOIL I331.9 1 4 COMBI I TANK . MIX 3 3321.5 2 COMBI LUBRICATION ATTACH 3323.5 9 COMBI SECTION TO CRANE I " LIFT SECTION 3324.5 40 NORMAL To POSITION I LOWER ; 3326.3 6 COMBI SECTION INTO SHAFT ' BRING SECTION & 3328.7 10 COMBI . INSTALL CASING I3328.7 I 36 ICONSOLIDATE I - I PIPE SECTION I3355. 5 5 COMBI INSTALL ON I I GUARD RAILI I3355.5 I M 52 ” I NORMAL I DUMMY i DUMMY SOIL 3355.5 56 NORMAL TYPE CLAY ' CRANE 3357.5 41 NORMAL RETUF] IS MM " M MM "'INSTALL—“E" 3365.8 8 COMBI CHECK AIR .. GRIPPER I3365.8 I I NORMAL I DUMMY " JACK PIPE 3447.5 59 NORMAL SECUON 4 DISMANTLE 3456.5 46 COMBI ~ CABLES & . HOSES 4 I3456.5 I 99’ I COUNTER I - ATTACH 3458.5 9 COMBI SECTION TO CRANE , LIFT SECTION 3459.5 40 . NORMAL To POSITION I.____.__- ._ . LOWER 3460.7 6 COMBI SECTION INTO SHAFT M PIPE SECTION 3489.2 5 COMBI INSTALL ON GUARD RAIL 204 I I3489.2 54 I NORMAL NORMAL I I BUMMYSOIL DUMMY 1 TYPE SAND I3491.2 41 NORMAL CRANE RETURNS I I3533.1- I I $35413 — —~.—u‘q ..-_ . ._ ......A. - ..- 57 44 NORMAL JACK PIPE SECTION 2 COMBI DISMANTLE CABLES & HOSES 2 ,533‘41‘3 I51 ICONSOLIDATE I I3541.3I 99 I " COUNTER I 205 BIBLIOGRAPHY Abbott, D. (2005) “UCT Microtunneling Workshops for Municipalities and Engineers” Underground Construction Technology Conference Presentation, Houston, TX, Jan 2005. Abd Al-Jalil, Y. Q. (1998) “Analysis of Performance of Tunnel Boring Machine-Based Systems”, Ph.D. Dissertation, The University of Texas at Austin, Austin, TX. Abdelharnid Tariq. (2004) “Course Material for Lean Construction”, Michigan State University, East Lansing, MI. AbouRizk, S.M. Greenwood, C., Knowles, P., Ruwanpura, J.Y., Van Tol, A., Jancewicz, S., Appleton, B. and Farrar, J. (2000). “Measuring and Improving Construction Productivity — Case Studies of Three Edmonton Projects.” Proceddings of the Seventh Canadian Construction Research Forum, Edmonton, AB, 53-75. AbouRizk, S, Ruwanpura, J.Y, Er, KC. and Fernando, S. (1999). “Special Purpose Simulation Templates for Utility Tunnel Construction.” Proceeding of the Winter Simulation Conference, Pheonix, AZ, 948-955. AbouRizk, S. and Hajjar, D. (1998). “A Framework for Applying Simulation in Construction”, Canadian Journal of Civil Engineering, 25, 604-617 AbouRizk, S., Manavazhi, M. and Dozzi, P. (1997). “Analysis of Productivity on a tunnel operation using computer simulation.” Proceedings of the ASCE Construction Congress V. Minneapolis, MN, 382-3 88 AbouRizk, SM. and Halpin, D.W. (1991). “Probabilistic Simulation Studies for Repetitive Construction Processes.” Journal of Construction Engineering and Management, ASCE, 116(4), 575-594 Abraham, D., and Gokhale, S. (2002). Development of a Decision Support System for Selection of Trenchless Technologies to Minimize Impact of Utility Construction on Roadways. FHWA/IND/JTRP-2002/7, SPR—2453, National Technical Information Service, Springfield, VA. Allouche, E. N., Ariaratnam, S. T., and Macleod C. W. (2003). “Software for Planning and Cost Control in Directional Drilling Projects”. Journal of Construction Engineering and Management, Vol. 129, No. 4, July/August 2003, pp. 446-453. American Society of Civil Engineers (ASCE) (2001). Standard Construction Guidelines for Microtunneling. CI/ASCE Standard 36-01, Reston, VA. 206 Atalah, A. and Hadala, P (1996). “Microtunneling Database For The USA And Canada From 1984 To 1995”. Proceedings of the 1996 Specialty Conference on Pipeline Crossings, p 332-339, 1996. Atalah, A. and Hadala, P. (1996). “Microtunneling Database for the USA and Canada from 1984 to 1995”. Proceedings of the Pipeline Crossings, 1996, Burlington, VT, June 1996, ASCE, Reston, VA. Banks J. and Carson II, J .S. (1984). Discrete-Event System Simulation, Prentice-Hall, Inc. New Jersey. Baumert, M. E. and Allouche, E. N. (2003). “Real-Time Monitoring for Quality Delivery of Directional Drilling Installations”. Journal of Infrastructure Systems, Volume 9, Issue 1, pp. 35-43 (March 2003). Bennett, R.D., Guice, L. K., Khan, 8., and Staheli, K. (1995) Guidelines for Trenchless Technology: CIPP, FFP, Mini-HDD, and Microtunneling. Construction Productivity Advancement Research (CPAR) Program Technical Report. US. Army Corps of Engineers. Washington, DC. Bruce, M. H. (2003). “Design and Inspection of Microtunneling”. UndergrOund Construction Technology Conference Presentation, Houston, TX, Jan 2004. Construction Technology Centre Atlantic, Inc. (1997). Investigation and Study into Research in Construction. Report submitted to Industrial Research Assistance Program (IRAP), Fredericton, N. B. Canada. Er K.C., Fernando, S. and Ruwanpura, J .Y. (1999). “Application of Special Purpose Simulation Modeling for Tunnel Construction.” Proceedings of the 6” Canadian Construction Research Forum, Edmonton, AB, 1-9 Hajjar, D., and AbouRizk, S. (1999). “Simphony: An Environment for Building Special Purpose Construction Simulation Tools.” Proceedings of the 1999 Winter Simulation Conference, Phoenix, AZ. 998-1006 Hair, D. J. (1996). “New sofiware helps estimate trenchless job costs. Part 2.” Pipeline and Gas Industry, 41—44, August 1996. Halpin, D. W. and Woodhead. R (1998) Construction Management. 2nd Ed. John Willey & Sons, Inc. New York, NY. Halpin, D. W. and Riggs, LS. (1992) Planning and Analysis of Construction Operations. John Willey & Sons, Inc. New York, NY. Halpin, D. W. (1977). “CYCLONE: Method for Modeling of Job Site Processes.” 207 Jounal of the Construction Division, ASCE, 103(3), 489-499 Herrenknecht AG, Schwanau, Germany. (http://www.herrenknecht.com). Ioannou, P.G. (1989a). UM-CYCLONE User 's Guide. Department of Civil Engineering, The University of Michigan, Ann Arbor, MI Iseley, T. and Gokhale, S. (1997). Trenchless Installation of Conduits Beneath Roadways. Synthesis of Highway Practice 242, Transportation Research Board, National Academy Press, Washington, DC. Iseley, T., Najafi, M. and Tanwani, R. (1999) T renchless Construction Methods and Soil Compatibility Manual. Trenchless Technology Committee, National Utility Contractors Association (NUCA), Arlington, VA. Iseley, T., Najafi, M., and Tanwani, R. (1999). Trenchless Construction Methods And Soil Compatibility Manual, 31rd Ed., National Utility Contractors Association, Arlington, VA. , Kerr Construction Inc., Palmetto, FL. (http://www.kerrconstruction.com). Kirby, M. J ., Kramer, S. R. Pittard, G. T., and Mamoun, M. (1997). “Design guidelines and procedures for guided horizontal drilling, Part II, No-Dig Eng, 3 (4), pp 13-15. Lawson, G (2003)”. Water & Sewer Construction With Horizontal Directional Drilling. The Charles Machine Works, Inc./ Ditch Witch, Perry, OK. Lee, S. and Chang, L (2004). “Bid-markup determination for microtunneling projects”. T unnelling and Underground Space Technology v19, n2, p 151-163, March, 2004. Martinez, J. and Ioannou PG. (1994). “General Purpose Simulation with Stroboscope.” Proceedings of the Winter Simulation Conference, Orlando, FL, 1159- 1 166 . McCabe, B. (1998). “Automated modeling approach for performance improvement.” Proceedings of the 5”I Canadian Construction Research Forum, Edmonton, AB. 43-53 Najafi, M. (2005). T renchless Technology - Pipeline and Utiltiy Design, Construction, and Renewal, McGraw-Hill, New York, NY. Najafi, M. and Gunnink, B. (2002). “Ground Displacement Monitoring During Horizontal Directional Drilling & Other Trenchless Intallations. Part of: Pipelines 2002” — Beneath Our Feet: Challengers and Solutions. By George E, Kurz, (E.). Najafi, M. ,(2000) “Current Issues in Horizontal Directional Drilling”, Utility Contractor, Vol. 24, No. 4, April, 2000. 208 Najafi, M. (1993). “Evaluation of a New Microtunneling Propulsion System”, Ph.D. Dissertation, Louisiana Tech University, Ruston, LA. . Nido, A. (1999). “Productivity Projection Model for Microtunneling Operations based on a Quantitative Analysis of Expert Evaluation.” MS Independent Research Study, School of Civil Engineering, Purdue University, West Lafayette, IN. Nido, A. A., Knies, C. J ., and Abraham, D. M. (1999). “Role of operation simulation in the analysis and improvement of microtunneling projects”. . T unnelling and Underground Space Technology, v14, pp 1-19, 1999. Ostwald, P. F. (1992). Engineering cost estimating, 3rd Ed., Prentice-Hall, Englewood Cliffs, N. J. Rush, J. W. (2004). “Microtunneling In The USA. 20 Years And Counting”. T renchless Technology Magazine, May 2004. Ruwanpura, J. Y. (2001) “Special Purpose Simulation for Tunnel Construction Operations” Ph.D. Dissertation, University of Alberta, Edmonton, Alberta, Canada. Salazar, GP. and Einstein, H.H. (1987). “SIMSUPERS: tunneling construction simulation.” Proceedings of the 4” conference on Computing in Civil Engineering, ASCE, Boston, MA, 461-467 Salem, 0., Galani, N. and Najafi, M. (2003). “Productivity Analysis of Auger Boring Trenchless Pipe Installation Using Simulation. Pipelines 2003”. New Pipeline Technologies, Security, and Safety International Conference on Pipeline Engineering and Construction 2003, July 13—16, 2003, Baltimore, Maryland. Sedjo, A (2002). “Microtunneling Poised for Grth in US. Market”. T renchless Technology Magazine, May 2002. Shao, Jun (2003), Mathematical Statistics, second edition, Springer. - Simicevic, J. and Sterling, R. L. (2003). “Survey of Bid Prices for Trenchless Technology Methods”. Trenchless Technology Center, Louisiana Tech Univeristy, Jan 2003. Simulation Home Page, Division of Construction Engineering and Management, Purdue University, West Lafayette, IN. (https:”engineering.purdue.edu/CEM/People/Personal/Halpin/Sim/index html, April 22, 2005) . Soltau Microtunneling, Erkelenz, Germany. (2002). (http://www.microtunneling.com/soltau/index.htm) 209 Staheli, K. and Hermanson, G. E. (1996). “Microtunneling, When, Where, and How to use it”. Water Environment and Technology 8(3), 31-36. Alexandria, VA. Tanaka, Y. (1993). “Cycle Time Simulation of Shield-Tunneling Operation.” Proceedings of the Fifth International Conference on Computing in Civil and Building Engineering, ASCE, Anaheim, CA, 1386-1389. Touran, Ali and Asai, T. (1988). Simulation of Tunneling Operations, Journal of Construction Engineering and Management, ASCE, 113(4): 554-568. Ueki, M. (1999). A Decision Tool for Microtunneling Method Selection. MS Thesis, University of Texas at Austin, Austin, TX. Ueki, M., Haas, C. T., and Seo, J. (1999). “Decision Tool for Microtunneling Method Selection”. ASCE Journal of Construction Engineering and Management. 1252, March/April 123-131. Ulgen, O.M., Thomasma, T., and Otto. N. (1991). “Reusable Models: Making Your Models More User-Friendly.” Proceeding of the 1991 Winter SimulatiOn Conference, 554—562 Wilson, J .R. (1984). “Statistical Aspects of Simulation.” Operation Research ’84, Proceedings of the 10'” Annual International Conference on Operational Research, J .P. Brans, ed., Elsevier Science Publishes B. V., Amsterdam, The Netherlands, 921- 937 Zimmerman, R. and Cusker, M. (2001). “Bringing Information Technology To Infrastructure: A White Paper For A Research Agenda. Background paper for Bringing Information Technology to Infrastructure — A Workshop to Develop a Research Agenda” held by ICIS, June 25-27, 2001 in Arlington, VA. 210