2 LIIMNIININLIN THS COST OF HANDLING COAL IN STEAM POWER STATIONS A Thesis Submitted To The Faculty of a MICHIGAN AGRICULTURAL COLLEGE By W. H. Betts U. Utley Jee Candidates for the Degree of Bachelor of Science June, 1916, THESIS OBJECT OF THESIS, The object of the investigations was to make a careful study of the coal handling system in each of three power plants and to deter mine the cost of handling both coal and ashes in each plant. STATIONS INVESTIGATED, The following stations were investigated; Municipal Power Plant, Lansing, Michigan, M. A. C. Power Plant, East Lansing, Michigan, Consumers Power Co., Wealthy Ave. Station, Grand Rapids, Michigan. The following stations were visited but no investiu gation made; | Michigan Power Co., Lansing, Michigan, Michigan Central Round House Coaling Station, Grand Rapids, Michigan. SCOPE OF THESIS. The investigation was to include a study of the apparatus, measurement of power consumed in its operation, the determination of labor costs, and a record of the time required for the various steps of the transfer of the coal and ashes. 94061 \ Cost of handling was to be divided as follows; Cost of unloading cars, Cost of conveying to bunkers, Cost of feeding to furnaces, Cost of removing ashes. These costs were not to inolude wear and tear and ‘depreciation of machinery. METHOD OF PROCEEDURE. The first step in each case was to sceure permis= sion from the proper authorities to carry on the investigation in their plants. A half day was then spent in looking over the plant, noting the type of syetem used, its arrangement and operation. Following this study a method of running a test was devised. Later, at a time when the plant was oarrying as nearly as possible an average load, a 24 hour test was made, In all cases the motive power was electrical motors; henoe, the power con- sumed was measured by cutting meters into the motor circuits, The amount of coal fed to the furnaces thre the 24 hours was considered to be the amount handled by the system during that period, In all cases the coal fed to the furnaces was weighed by means of a weighing — car before being passed to the furnace hoppers. The weights were recorded and totaled, The handling of the ashes in only one case allowed of accurate weights being kept. In the other two cases average weights per car or load were obtained and account kept of total cars dumped. Data as to the capacity of the plant, wages of fire= men, operators, helpers, and laborers was ob= : tained from the Chief Engineer of each plants Sufficient measurements were made to enable a dia- gramitio sketch of each plant to be made, . Photographs of each plant, systen and objects of interest were taken. REMARKS, | The writers feel that the value of the work done cannot be adequately expressed in this report. The data obtained, in itself, is of value only as relating to the period of year and load carried during the test day. The greatest value was in the experience gained by coming into actual contact with power plant operation; by getting into overalls and jackets and thoroly examining the various plants; by talking to the operators, firemen, and laborers, thereby getting first hand information as to the advantages and disadvantages of the systems used; in fact, by getting a knowledge of power plants such as can be odtained only by practical experience, The methods of running the tests were original with the writers, altho the method of dividing the costs was obtained from *Steam Power Plant En= gimeering* by Gebhardt. : Some difficulties were encountered but successfully overcome. Trouble was experienced in two cases due to difficulty in securing proper sized meters. At the Municipal Plant, it was required to keep the ash hopper locked during the period of the test to prevent the public hauling the ashes away. It was also required that the ashes be hauled to the city scale to be weighted , CONCLUSION. The writers are indebted to Messrs. Mefford and Keech, of the Consumers Power Company; Crane and Childs of the Municipal Plant; Bissell and Newell, of the College Plant, for courtesy shown in allowing the investigations and kindness in giving the required information during the tests, MUNICIPAL PLANT Lansing, Michigan. APPARATUS: 34° apron elevator from hopper heneath track to crusher. Coal crusher, | 24" bucket elevator, 1s* x 6* distributing conveyor with sliding wearing s shoes. Reinforced concrete coal storage bin with down spouts tb » Weighing car, and also to Storage room. Gu 400 HP. Wickes vertical boilers with Dutch oven . furnaces. Vacuum system for removing ashes. GENERAL DESCRIPTION. ) The Municipal Plant is located on a spur of the L.S. & M.S. Railroad having connection also with the Pere Marquette and Michigan Central Railroads. MShis assures good service in getting. the coal to the plant. It is required that the coal be shipped in hopper sottom cars, The coal is dumped from the cars into a hopper below the tracks from which it is fed to the crusher by means of a 324" apron elevator. After leaving the crusher, it drops into the buckets of an elevator and is raised about 50feet to the dis- tributing conveyor, by which it is carried to the storage bin. It then passes thru down spouts to the weighing car, and after being weighed is dumped into the fhrnace hoppers. The ashes drop from the grate into ash pite below When the furnaces from which they are hoed and dropped into the suction pipe of the ash removing sydtem, A suction of 6 to 8 oz. per square inch is ree quired to move the ashes. The ashes pass thru a mixing chamber where they are thoroly soaked with water and then dropped into the storage hopper. The ashes are placed at the disposal of the public, wagons being driven under the hopper and when the valve is opehed the ashes fall into the wagon. it is desired to place coal in storage, valves in down spouts leading to the storage room from the storage bin are opened and the coal allowed to drop into the storage room. When required for use, it is passed thru openings in the floor onto the reclaiming conveyor which dumps it into the bucket elevator for hoisting to the distributing conveyorte The services of two coal passers and two firemen are required. The coal passers work a ten hour day. There are three shifts of eight hours each for the firemen. The usual practice at this plant is to have the coal shipped in such quantities that it may be put into the storage bin and used directly from that, Much time is required for unloading a car bex« cause the opening in the bottom of the hopper beneath the tracks is not of sufficient size to keep the apron elevator loaded. RESULTS OF 34 HOUR TEST, Daten 11:30 A. M., April 13 to 11230 A.M., April 13, 1916. Operating Conditions. - | We selected Wednesday afternnon and Thursday morning as the time for the tests because, in the opinion of Mr. Childs, Chief Engineer, the plant was opere ating under a most nearly average load, : Data, Total amount of coal fed to furnaces 47.3 Tons ‘Total amount of ashes removed | 8.36 « COST OF UNLOADING CARS, COAL BEING PLACED IN STORAGE BIN. Test on car #33398 C. & 0. Weight of coal- 111000f= 55.5 Tons Time required 3¢ hours. Power coste Crusher Elevator Meter readings- Final 24.4 KWHr. 7108.9 KWHr. Initial at 7094 eo KWHr. ef KWHr. Total . 28.0 KWHr. Estimated cost of power .75¢ per KWHr.- Mr. Childs Power cost per ton of coal handled= Spies. = .35¢ Labor cost. - Wages Chief helper 35¢ per hour 3 assistants 33,5¢ " * (each) Total 70¢ * * Labor cost per ton of coal Bandled- TORE go9= 4.1¢ Total cost per ton of coal handled-— 4.1¢ + .35¢ = 4.45¢ Test on car f------ Wt. of coal- $34009= 41.7 Tons Time required= 1 Hr. 11 Nin.= 1.18 Hr. Power cost. Crusher Elevator Meter readings— Final 7083.0 KWHr. 5.4 KWHr. Initial 7075.5 0,0 @ KWHr. @ KWHr. Total 13.9 KWHr. Power cost per ton of coal handiled- 13.95.7598 = .83¢ Labor cost. Wages—- Chief helper 35¢ per hour Assistant _23,5¢° * Total 47.59" °* Labor cost per ton of coal handled- SDeGp RARE = 1.259 Total cost per ton of coal handled 1.35¢ + .32¢= 1.57¢ COST OF FEEDING COAL TO FURNACES. Sd a firemen required 3 shifts of & hrs. per day Estimating that 4/5 of the time spent in handling coal and 1/5 in handling ashee. Labor cost. Wages— Chief fireman 38.8¢ per hour | Second "= 234.7% * * Total 53.5¢ " * Labor cost per ton of coal handled= 4/5 x PAF Pee = 21 ay COST OF REMOVING ASHES. Labor cost. Per ton of ash handled- 1/5x ““¥°¥2°f- 30.74 Power cost. Suction fan Meter readings- Final 0012.0 KWHr. Initial 0003.9 8.7 KWHr, Per ton of ash handled= &,7x .7 0759 ’ » Total cost per ton of ash handled= 31.4¢ TABULATION OF COSTS= Per Ton, Unloading cars 4.5¢ " " 1.69 Feeding furnaces 31.89 Removing ashes 31.49 wee me ema Gerwra/ V~1i€ J OF PY ITF City Light and Water Plant COAL TICKET Date 191__ FIREMAN A.M. P.M. COAL LBS. COAL LBS. CONSUMERS POWER CO., Wealthy Avenue Station, Grand Rapids, Michigan. APPARATUS? Shaw electric traveling yard crane with single motor, Clutch operated type trolley handling a two» cubic yard Brownhoist clamshell bucket, , Linkbelt, 18*® four roller belt conveyor running above & storage bins, each with a down spout controlled by a simplex valve. Weighing car, | Sa600 HP. Stirling boilers, equipped with Foster superheaters and Green chain grates. Ash handling car. GENERAL DESCRIPTION. Coal is received at this plant over a spur from the Coal main line of the Michigan Central Railread, the Cars being run directly beneath the crane run= way. The coal is removed from the cars by means of the clamehell bucket and either dropped into the conveyor hopper or placed in storage. The services of a helper are required for cleaning up the oar, from the conveyor hopper is carried by the belt and discharged into the storage bins by means Of a movable tripper actuated by power from the belt. From the storage bins, the coal is fed thru down spouts to the weighing oar and after the weight is registered it is spread along the hopper arranged above the furnace, The correét weight of each car of coal is registered on a printed ticket whioh is punched by the movement of a lever on the scale weight. The ashes drop from the grates into a sheet metal hopped from which they are allowed to drop into the ash car below by the operator. The ashes, while in the car, are soaked with water and then dumped into the ash pit outside the building, from which they are removed by the crane and dropped into an ash hopper at the opposite side of the runway. From here they are hauled away as desired, The pliant is coaled up ordinarily four times a day, at 7230 and 10230 A.M, and at 1230 and 5¢30 P.M, The capacity of the storage in the yard under the Crane is about 15000 tons. The one objection noted to the system is that the speed of the bucket hoist is not sufficient for the speeds of the bridge and trolley. This necessitates a delay both in unloading cars and in filling the hopper, ~ RESULTS OF 34 HOUR TEST. Dates 3215 P,.M., April 37 to 2:15 P.M., April 328. Operating Conditions. Data. This plant is one of a number of steam and hydro- electric plants forming a chain about the state. Due to high water in the rivers and @ consequent carrying of the load by the hydro=electric plants, this plant was running at about one-half normal capacity. Total amount of coal fed to furnacesg—-- 73.03 fons Total amount of ashes removed" | 10,95 # COST OF CONVEYING COAL 70 BUNKERS AND REMOVING ASHES. Power=- Crane Conveyor Meter reading, Final 00038 KWHr. 33519 KWHr. Initial 00000 #3815. KWHr. . KWHr. Total $3 KWHr. Estimating the cost of power at .7¢ per KWHr., Power cost & 32 X .7¢ & 32.4¢ for 24 hourse Estimating that 9/10 of the power was consumed in handling coal and 1/16 in handling ashes, Cost per ton of coal handleda 9/10x es, & 239 Power cost per ton of ash removedsl/10x 3304. w 03¢ Labor= Wages Crane Operator 30¢ per hour | Helpers | 24¢ per hour Ash passer= Day man 23¢ per hour . Night * 1g.5¢ * * Handling coal, Estimating that the orane operator spent 9/10 of the time handling coal and 1/10 of the time handling ashes, Operator and helpers worked 10 hours per day. Wage coste Operator 8/10x10x30 9x 270¢ " Helpers 3x 20 x atge 4806 Total | 7509 Cost per ton of coal band led=-yfGg7 10,49 Handling ashes. Wage cost Operator 1/10xl0x30g = 30¢ Ash passers 1123392 aaa Total “Bi Cost per ton of ash handled= ose 46.59 Total cost of conveying coal to bunker and Fenoving ashese Coal Ashes Power o5¢ ea Labor 10,44 46.54 Total 10.0% 46.7¢ COST OF FEEDING COAL TO FURNACES. COST (1} (3) The exact wage rate of the firemen could not be obtained. We estimate it to be 23¢ per hour, There are two shifts; four men during a day of eleven hours, and three men during a night of thirteen hours, Wagew= Day shift 4x 11 x 32¢ = 968¢ “Wight © 3x 13 x 229 = 858¢ , . Total - Cost per ton of coal fed= »rS86_ = 35.3 OF UNLOADING CARS, Test on car $#20393- Hocking Valley, Weight of coal~ 107800#= 53.9 Tons Time requited 40 minutes= 3/3 hours. Power consumed 6.5 KWHr. Power cost per Ton= $3 te =. o9¢ 3x24 - 94 Se oe Potal 1.6¢ Test on car #18311 = 0, I. & 8. Weight of coal 97100¢= 48.55 Tons Time required 29 minutes= 048 hours - Labor cost per Tone 3/3z 0 Power consumed 7 KWHr. Power cost per fon= - ol¢ Labor cost per Ton= 48 x - sof agxee = 11s. Total 1.3% TABULATION OF COSTS Per Ton. Unloading cars e a Filling bunkers Feeding furnaces Removing ashes 1.39 1.6¢ 10.79 25.39 46.7¢ OS f 14 GO4/ 7 aa) kForpever ag get i ape . ME] | 4 | - rw a = a Wie (7 Or ABal PROONG otk 2~ GRAN RGPMASE, ATCA. ¢ | ge ot ial i} . | Consumers Fower lo, Grand hapids: S414. THIS EDGE UP. PRINTED SIDE TOWARD BEAM. | | | 0 | 200 | 400 | 600 | 800 | 1000 | 1200 | 1400 | 1600 | 1800 | 200 180 160 140 120 100 80 60 40 20 fo} | @ e e e e e e 1 e e e | LesvaDevsasunalsonabivvslevclocrlsodicalimlilin tintin tulialilialil ind | i ~ A erryp/1y Coal Fo SKoraze. DOL} y ASMOCS. 3 figeneer Crancovserator Bets § eecs. A. CO. PLANT East Lansing, Michigan. GENERAL DESCRIPTION. The College Power Plant is located on a spur of the This Pere Marquette Railroad, this spur being joined to the main line at Trowbridge, where the Port Huron to Chicago division of the Grand Trunk Railroad crosses the Grand Rapids to Detroit division of the Pere Marquette. This affords convenient facilities for transporting coal to the plant. plant furnishes heat, light, and water for all buildings on the Campus. Both exhaust steam and live steam are used for heating purposes. The boiler equipment includes; 4 Scotch Marine Boilers, 150 H.P. each; 1 -350 HP. Freeman Combination Boiler; and 1 150 HP. Horizontal Tubular Boller, all equipped with Jones underfeed stokers. The coal is shoveled by hand from the cars to a storage shed, having a capacity of 1000 tons. When the shed is full, the remaining coal is shoveled into piles outside along the track wherever it is con- v venient. An electrically driven elevator is located in the middle of the storage shed, on the side oppo- site the spur. It is driven by a 15 H.P. D,. CO. Motor, and has a capacity of 3O000F~ The coal in the shed is shoveled by hand into a chute which empties into a l-ton car standing on tracks on the elevator. Provision was made for using a crusher whéch would empty into the chute, but it has never been installed. When the car is filled with coal, it is raised by means of the elevator to the level of an overhead track, which extends from the elevator shaft to the storage hoppers at the top of the boiler room, The car is pushed by hand onto scales set in this track. After being weighed it is pushed to the hoppers and dumped. From the hoppers it drops by gravity thru down spouts to the stoker hoppers. After unloading the coal into the storage hoppemthe car is pushed back to the elevator and lowered to the level. of another track, located directly beneath the first track and pargllel to it and extending thru the ash tunnel below the boiler room floor. Here the car is loaded with ashes which drop down from hoppers in front of the boilers. The car is then pushed back, elevated, weighed, and dumped into the ash hopper, Coal from the outdoor piles is wheeled in barrows or wagons to a reclaiming hopper above the ash tunnel, It drops from here into the car below. One man is required to handle the cars of coal and ashes, At least two men are needed in the storage shed. These men work ten hours a day, seven days in the week. The method of conducting the test was as follows; A wattwhour meter was calibrated and cut into the motor Cirbuit. Readings at the end of each of two 34 hour pericds were taken. Total weights of coal and ashes for the same 24 hour periods were obtained from the scale records. RESULTS OF 34 HOUR TESTS. Dates 5:00 P.M., April 19 to 5:00 P.M., April 81, 1916. Data— Totalsamount of coal fed to furnaces- lst 34 hours 48640¢ Bnd 34 hours 410204 “SO7608= 45.4 tons Total amount of ashes removed= lst 34 hours 7900¥ and 324 hours 6140 0408- 7 tons COST OF CONVEYING COAL TO BUNHERS AND REMOVING ASHES. Power= . Elevator Meter reading, Final 0274,9 KWHr Initial avl Se KWHr. Calibration of meter with shunt Formulas meter watts x Rev, x 3600 time in seconds | 10 revolutions of disk in 58 seo. 20 = 3500 = 631 meter watts Testing circuit was held at 300 volts and 325 amps. a00 x 25= 5000 true watts } Correction Factor = Seer sect x 3.7 5 39.8 KWHr. used in 48 hours. Approximate cost of current at time of test- 75¢ per KWHr. -Mr, Newell Power cost ” | 29.6 x .75¢ = 32.4¢ Estimating that 4/5 of the power is consumed tn handling coal end 1/5 in handling ashes. Cost per ton of coal handled- 4/5x er “49 Cost per ton of ash handled- 1/5 x 22s4- .7¢ Labor Cost, Wages— Coal passer- Chief | 25¢ per hour Assistants 23.59 . 8 Estimating that one assistant spent @ hours per day handling coal and 3 hours handling ashes. Wage cost- Chief SBx10x25¢ = 500¢ lst Assistant 2x10x22.5¢= 450¢ andi? 4/5x3x10x23.5¢=_360¢ Cost per ton of coal handled- 2=f = 28.8¢_ Cost per ton of ash handled- | 1/5x28x10x38,5¢ - 13% COST OF FEEDING FURNACES. Wage- Firemen 26¢ per hour Estimating that 4/5 of the time is spent in handling coal and 1/8 in handling ashes, Cost per ton of coal fed- ‘ Sx8x84x25 - 21.2¢ Cost per ton of ash removed—2/522%54x8 = 34.29 COST OF REMOVING ASHES, Power and labor «coal passers o7¢ — 13.0¢ Firemen 34,3¢ Total 47.09 TABULATION OF COSTS Per Ton Conveying cozl to bunkers 13.4¢ Feeding coal to furnace 31.2¢ Removing ashes 47.99 COST OF UNLOADING CARS. Data obtained from Mr. Newell Result of test made April 14, 1906 263.3 tons of coal unloaded at cost of 9.74¢ per ton Coal taken from car and carried to back of shed Average cost from car to shed 7¢ = 74¢ per ton Average cost from care to ground to storage- 25¢ = 30¢ per ton | Average cost from car to shed= handling frozen coal 2a5¢ = 30¢ per ton This latter figure is usually taken as the cost of handling the coal during the months of December, January and February. HN OPP EP BA Z{eC4AT OP TD