SUPPLEMENT! Sy MATERIA. IN BACK OF BOOK €3 52 “Ce 2: v7 ON ™ ee Cr oyveN . ve 77 YT Trey i nie a wm, - ‘- da ! Dub abs Wo Le wate ty dT ow LDL eae “ONT A a Q ‘No po: a\euirt «se wl] oo ent 4 dteads wo @ Ak TYTN TAY TINY tT re ebwdon 2 ica a. ht ned ean gvenenren f @nesis submitted to the Faculty ofthe wichisan acsricultural Collese for tre v* 1 vecvree OF NIU. THESIS yy CONTE = Vide o sde a Do otatement of Corditiors,.---—— selection of “Squipuent------ ovecifications —-------—---—~ ovecial Construction ------- LSstimreted Cost ---- _ Ok kak ok ok 400224 Tie following Thesis is a consideration of the prob- lem of handlin3s sas coal at a certain Sus rlamt, with the 2 operation of which he writer was at one time conrected. Tie plant is used for the manufacture of illwsinatings ¢ 2 G2S for a city of forty-two thousand population( 1014). The Beas produced is mixed coal and carburete¢ water sas of 600 B.t.u. and 15 candle power. The original installation put into service some Lhirty years ago made water gas only. Vunen it became evi- dent that coal gas was cheacer to vroduce, two coal cas cenches were installed and found to be satisfactory. Then four more bencnes vere installed and the old water Cas plant was abandoned . As the comand increased, coal gas benches were added until the present (1014) installation of eleven benches of six retorts,each 14"x 28"x O', was complete. about 1910 tne load became so variable that it seemed advisable to install a water gas machine to carry the peak loads. a V'-6" United Gas Improvement Co. water Sas machine with scrubber and wash box was installed. This equip&ment gave a maximum cavacity of 1,250,000 cubic feet per <4 hours with continual operation of the water Gas machihe and medium quality yield. The coal $5as benches were run on four hour heats and the usual churze per retort was S00 lbs. This gives a daily coal consumntion of 71 tons for gas makin= purposes. It was customary to use the same kind of coal for bench fuel at an average con- sumption , including waste of about 3c5 lbs. of fuel per ton of coal carbonized. Tnis sums up to ll tons of bench fuel per 24 hours. Total coal consumption per 24 hours was then 2 tons of 2000 lbs. each. This coal was usually 3,/4 lunp vest Virginia cas coal, tho occasionally Youghiozheny coal was purchased. It was delivered by the rail-road in all kinds of cars on the comvany's siding,as shown on drawing No. 1. Crdin- ~ arily it was possible to fet the coal delivered in bottom dump cars. Coal for immediate use could be dumred from fhe bottom of the cars onto a brick pavemert at the south end of the retort house( marked coal dock). When so unloaded it was possible for the stokers to get their supply by shovelling,.from the Ground pavement into the charging was- oms. It was necessary to have one man on each shift to trim the coal in the car, and to clean up and close the pvockets. Figured on a basis of charging all of the stokers' time to stoking and none to coal unloading( as was customary in thot by the works management) it cost only 32.50 per 50 tons to unload or five cents per ton. It was impossible however to unload,even 20; of the total coal in this man- ner, because of the irregularity with which thw shipments arrived. It was common for ten to fifteen cars to come at one time, and then none for a week. To obviate payament of demurrace charzes it was necessary to unload this coal in to the coal sheds adjoinins tiie retort house on the east Ci and on the west.This was done by snovelling from the cars into wheel barrows placed on vlank runvays on top of the cars. The coal was wheeled into the shed arc dumped. Che man on tie wheel barrow and two to shovel from the car in the barrow were necessary. This method averased a cost of 20 g per ton to unload. During a veriod of two weexs to two months each year it was to be expected that coal shioments might be held up entirely. This necessiated taking the daily coal supply from the stock pile. Tne stock pile,containinzg about 3000 tons was located several hundred feet west of the retort house,with structures intervening( see drawins lio. 1). The price of stocking coal in that pile by means of men and wheel barrows averaged 30¢ per ton. To reclaim that coal by means of horse drawn wagons and men, handling by hand and delivering to the front of the retort house averaced a cost of 51.25 per ton. Cn the average during a years time twenty per cent of the coal would be unload<:d direct from the cars ata cost of 5¢; 10°53 would be stocked and reclaimed from the large pile at a total cost of 51.25 per ton; and 70> would be taken from the coal sheds at a cost of 25¢ per ton. During the year then the following would be spent for nandling coal from the cars to the charsing wagon,- bd 365 a: ys xX Se tons 30,020 tons per year. 20;, 5986 tons t 5¢ per ton %299.30 1073 2093 tons ©31./5 " 1" 4627.15 70,3 20850 tons & Z5¢ 5212.50 Total per year 3/0140.95 This ampunt varied somewhat but there was always the possibility of ti.e arrival of such conditions as existed in the winter of 1916-1917, when all of the stock pile was used up, tho during the preceding summer there had been an unusually large one. The actual average cost then to unload coal was 33.86¢ per ton. The costs as outlinedabove were for the year 1914 when the cost of labor was 32.00 and’ 2.05 per day for common labor, and $2.50 for a wagon driver, and 21.50 per day for a team of horses. Since 1914 the labor conditions have suffered considerable chan;je. Now common labor receives 32.50 to $32.75 per © § hour day and the stokers 33.00 per 1l hour day. In spite of the high wases laborers are scarce and diffteult to control. The stokers refuse to handle coal from different unloading places,and object to going out of doors in tne winter tine. Jita all it scems very cesirable to lessen the hand labor required, both because of high cost, end because of the possibility of strikes and the discontinuance of opsration. “ith labor costs about 25° hicher in 1017 than in 1¢14 the yearly cost to unload cecal required in 1914 would be #12 675 or 4&Z.3 per ton. In 1912 the daily send out averaged 500,000 cu.ft. in the summer and 700,000 cu.ft. per <4 hours in the winter. Since then the increased use of gas for industrial purposes and the normal increase due to growth in population has given an average daily sendout of 1,000,000 in 1014 and 1,500,000 cu. ft. in L916. In Feburary 1917 the sendout vas around 2,000,000 cu.ft. per <4 hours. These figures plotted as in Fig. 1. indicate a load of about 3,000,000 cu.ft. per cay in 1018. It is difficult to prophesy what it will be in 1020. If the rate of increase remains con- stant the sendout will be 4,500,000 cu. ft. per cay. The population is increasing so ravidly that the building op- crations, including installation of gas services, have not kept pace. Hence it is reasonable to assume , that the gas sold will increase at the present rate and possibly faster. Tne nopulation in 1916 was estimated at 65000 or 70000. see Fig. 2 for increase in population in recent years. The capacity of the plant showed sisns of needing an increase as far back as 1913. Certain plans were then being fornu- lated to replace some of the then present equipment with more modern and efficient types, and to enlarge the works capacity to care for the probable future needs as autlin- ed above. It was planned to install in the very near fut-—- ure @ new water sas machine to run in connection with the one already in use; and also to put in the necessary addi- tional scrubbin, and condensirg apdvaeratus.a new nolcer of 1,000,000 cu.ft. capacity was contracted for erection in 1615. A new retort house of inclingu oven retorts was pro- Sosed to replace the old house of stop end retorts, six per ba Me tt Be ee le ee I ) bench. This installation would briny the coal gas capacity of the plant to 2,750,000 cu.ft. daily, 2/3 of this to be installed row ard 1/3 later(see Grawirng Ko. 2).. J/ith a yield of 5.00 cu.ft. of gas per 1b. of coal this would de- mand «7S tons of coal per <4 hours. If coal is used for furnace fuel, there will be 41 more tons required, or a possible total of 316 tons per 24 hours. To handle this coal by the old-time hand methods would have cost 3122.00 per day pr 344,550 per ;ear, a cost which is obviously pronibitive. Hence the necessity for a coal handlincs sys- ten. referring to drawing Io. 2, the extersions alreacy Dlanned are shown in diagram. These are the new purifying bosses to care for the new autput capacity; the new water cag macnine; and the new boiler to furnish steam for it. The new governor and booster room is shown and will remove those articles from the basement of the office, where they have been a source of danger. South of this is tne new con- denser and exhauster room. Tne proposed new retort nouse is shown just east of the 300,000 cu.ft. nolder Assimiing that the working hours in such industrial plants will soon be on an eight hour day basis, it becomes advisable to ve able to unlcad, crush and store in bunkers for use in the retort house at least one days supply in the working time of eight hours. It will be also wise to we 2 re) have coal handling ca»acity sufficient to unload reserve coal and place it in the stock pile. In my judgement there ~J should be a coal storaze of at least 200 tons in connec-— tion with the retort house, yreferably an overhead bun- ker, because the oven retorts are charged at the top end coy sravity from travelling weighing larries; also it should be possible to unloud ard stock 6 to 7 carloads ver day besliiles the daily consumption. This makes 13 car- leads per day to be handled, or about €50tons ,to handle which, a capacity of about 80 tons per hour will be neces- sary. In case of excessive demand above this amount, the resort to overtime of to two shifts would solve the pro- blen. To furnish two montns reserve coal in the stock pile it would be necessary to store 20,000 tons. then the problem reduced to its simplest terms con- sists of designing a systemtthat will (1) stock about 20,000 tons of coal at the rate of 325 tons per day, and reclaim it at the same rate when needed; and (2) that will at the same time unload, crush, and deliver to over- head bunkers 325 tons per day for current use. This sys- tem should do its work wil& a minimum of total cost and be so gesigned that future growth will be possible. Tne second requirement will be taken up first. From the nature of the ovens, which are inclined and charsed from the top it seems advisable to build an overhead hovper type of coal bunker. The coke storage space is between tne retort house and the river, and therefore tie ovens ought to be so placec tnat the cischarzing side of the oven stack will te on the north. The plan is to convey the coke to quenching rockets and then to tne east end of tne oven stack, and from there transfer by travell- ing crane and buckets,eitner to a crusner and ecreens,or to tne yard storaze of run of oven coke. The charging side of the ovens is then on the south so that the coal bunker must be there also. ( A consideraticn relative to future extension is taken up later). The charges will be distributed thruout the day at sufficient,intervals, so that the quality of gas will not vary too Sreatly. sence the coal burker ought to hold encugh coal to last fron the end of one eight hour cay to the beginnirg of the -- next, or an 1% hour suodly equal to <00 tons. For this purvese I have chosen an elevated hovper type bunker made of steel and lined with concrete to protect th steel from corrosion. See crawin; lo. 3 for size and refer to specifications for further details. The coal for use in the ovens musf pass an 1," screen, and since it is not always economical nor possible to buy this size at the mine, nor wise because of breakase and consequent waste, it is tnerefore necessary to in- gtall a coal crusher. The coal can be bousnt to be deliv- ered in hosver bottom cars which will permit of unload- ing by gravity into a track hopper. CO To handle the coal for daily conswaiption then the following eyuinment must be provided for a capacity of 40 to 50 tons per hour,- a track hopper, feeder, crusner, conveyor elevator, coal bunker. These pieces of apparatus will handle the coal with the least amount of hand labor and with minimum cost for main- tenance. In the future if additional cavacity is needed @ new Stack of ovens will be necessary. It is impossible to extend the »resent oven stack,because it borders the road- way on one end and the larger holder on the other. Hence this coal handling apparatus is designed for the maximum capacity of this oven stack,includir; tne one third more to be added to that now beins built. Later on I have taken up the matter of additional ovens and the coal handling plant for then. LC LAvCUT CF OYSTuL: cel + mo 2D so ali: @ The only available locaticn for railroad side track for delivery of ccal to the north side of the oven stack, and for shipment of coke is between the river and the S00, COO cu. ft. holder. All other ways of approach are estopped by buildings already in ;lace. by reference to drawing No. ce it is aprarant that it is possible to brings a track fron the main line of the Grand Trunk Railway along the river , northpf the holder and up to the north side of the oven stack. This track will traverse tie large triangular open space west of the nolder and provide yard storage space for coal stock. This property was owned by the Railway Co. in 1€135 but has recently been purchased by the Gas Co. this track will than be brot to and cver a track hopper on the nortn side of the oven stack,and extended ceyond as far as possible to provide switching space for empty cars. In the future another stack of ovens might well be provided for. The proposed loeetion for this stack is shown in heavy desh lines on drewing ho.4. The charging side of this future stack will face the charging side of the present stack, and make a firingpisle run- i ning east and west between the two stacks. Tne coal for the new stack gan be brot in on the same track and unload-—- ed by a Similar arrangement. To provide szace for this possible future installation the present track hovtver and il bunker have been located to the west of the center of the oven stack, Tae new installation can be placed acjacent to it and just east of the center line. The csereral lay- out 1s snown on arawings to. 5 and 4, and is described in the specifications. to liandle from cars te stock pile a aaily amount of 525 tous of coal, or to de able to reclain the same mount, will require a cavcacity of 40 tons per nour. The cheapest method both in first cost and in operation to handle such coal( 3/4 lunp) to and from open stcruse on the cround is by means of the locomotive crane and “rab bucket. For this purpose agoton eight wheel truck steam locomotive crane wilh s3ft. radius and 2 yd. bucket las been selectec. a system for track arrangement is shown on drawin; No.4 , whereby practically all of tne open groung svace Will be available for coal stora ‘se and within reach of the crane.f¢oncrete pitthus been located so that coal f from hopper cars can be unloaded ty gravity and dus from the pit by the grad bucket. sll places in the yurec can- not be reached by tie crane, wnen taking coal from the coal pit, without the construction of too many sits, and so it is planned that for storase in such slaces Bhe grab bucket will take coal directly from the cars. “nen the cars ure nearly emoty they can be pushed over the pit and dumped to completely empt: jhhen. The locomotive crane ) oud will also te of special value to move cars in the yard, and thus be independent of the Railway yarc men. Drawings 0.4 and 5 indicate the track arrancement, location of the cecal pit and a typical cress section of the storase yard, showing certh of coal piles, the track distances, and relative location of crane end coal pit. Drawing No.5 snows cetails of construction fcr the coal pit. Fora description of tne apparatus ard its installation see the specifications. For future growth it will be possible to place the tracks on low trestles and thus make possible higher storage piles. If this is done, and the reclaininz sveed is to be increased, it will be necessary tc have eitner a second locomotive crane, or a larger one, or to operate the one during two shifts. If deeper piles are used, it probably would be advisable tc separate tne yard into unit pockets by concrete retainins walls, so that in case of snontaneous combustion tlhe fire could be isolated and the condition remedied, 13 ASAT NN TOE srnolr?lOwricis specifications for a Coal Mendling System of ¢GJO Tons per 24 hours Canr2acity to be installed for the o Galintu.sL DUSCRIPTION. these svecifications with the accompanying crawings and plans contemplate the comolete installation of coal sandling machinery and all fixtures and structures meces- sary or desirable for the.prenver ard economical hardlings of coal to be used by the Gas Co. The part of the cas plant which will use the coal consists of an installation of lo inclined ovens,located as shown on drawing lio. 2 oO 3 on ° and furnishea and erected by The sas itachinery Co. of Cleveland, Chio. The ovens will use a maximum of 35<5 tons of coal per 24 hours for fuel ard gas coal combined. The coal will be delivered by the Grand Trunk Railway on a side track adjacent to the stack of ovens or to the yard for storare. The storage is to provide for a stock pile of 62,000 tons, stored on the ground in uncovered piles. Coal for 7 immediate use is to be dumned from 2tp 20 Sotto. stl ey ecars(eiti.e > U7 xt dir aw et frou tne mines or loaded locally from tne storazje pile) into track ho»nsers. "rom tinese nopoers tne coal is to be conveyed by an inclined anpron conveyor into a coal crusher which will reduce tne size to taat suitable for charzins in the ovens. From tne crusher tne coal will pass by gravity into a nivoted buck- - > et elevator and conveyor, and be taxen up over and across tne ton of the ovens and cdelimered into the storage bin. From tnere the coall will vass by gravity into travelling weighins lerries and thence into the inclined ovens in charges of about 5,500 lcs. fhe epnsratus nerein svecified G2 will take the coal from railway cars end celiver it to aS at one og yn . ‘ . ~~ Nw, ame my N Ae "s m_ "A ve ot 7 on 1 x : 7 ~ . storace bin over the ovens. Yhe travellins weishins larrie 7) ~~ —_ oo) is not inclufzed in tnrese svecifications. handlea witn a @ The coal in storaze piles is to b Nits. This crane U2 locoi:otive crane fron ears or frou track aot Will also be used as a switcnin5 engine in tine yard. The concrete founcations, walls and excavations are to be mace by the Ovners according to cetailed pluns furnished by the contractor for the apoaratus. There is a railway siding available for bringin: mwverial and suovlies. Yhe location cf tris track is snown on drawings Lo.s. MIT 7 mel wi- vo iaad All material is to be new and of first class and is to be furnished by tue comvractor except, 2S nover,, forponcrsts work. fhe tmiaterial is to be erected in a wortucan-like manner and to the satisfaction of the con- sulving erisgineer. 110 molt, 3 piase, SO cycle electric current is available for power, and all mechinery, is to be rman by when the system is completely installed, tue con- tractor is to »ut it into operation and suverintend its Vy t NNT wo + + . te oy os aa aad - sel leg oe Op,cration for one weex , or as lon5 as rec Maxlng 9 4 d 3 «- all necessary adjustuents and alterations until cc .jletely satisfactory). Diu Lia 3 as a nart of tnese svecificcticns there are subnitted five drawinss whiecn show the of present and fuvire structures in relation to tae coal hanclin,s systveu. These to be followed. The contractor shall submit detailed and shor dravw- incs for the inssection and sanction of tne consultiz¢ euxginecr befor Solio .ahead with tne work; and shall leave a Witn him two complete cobies of the Cravings finally used. r —~So wom wel. way Li.G wll steel and iron work is to be veirnted in the shion 4 4 with one coat of red lead in oil and afterverection with two coats of graphite and oil. Lo paint shall be ajzplied w+ 4 + over rust spots or scale . all such imperfections shall be removed before oair.tin ey TON on] (Roca Tan 7 Coe aL LS OF OrOpere wannee STC ae e The tracx hopper to ve installed on the nortn side of the oven stacx snall be a letx 1lé' steel hoprer, either Link selt Co.'.c.. Or eyual. This nopper shall be in stalled complete including rails aid rail supports, ex- “9° e 44 =. f Te cent excavation and concrete work. + “ow *3 PUNT TUP TST. “ar. CCL sve 2 The apron conveyor end feeder shall be a ©" pitch, OO" wide, Link selt So's., 1.0. eseor equal, with a capa- city to handle with sase 40 tons per nour, set so that the maxinuum depth of excavation shall not be sreater than shown on the drawing, and so that the distance of rail Siding from the oven stack shall be approximately as ™~™ shown. this conveyor is to be installed complete with a driving motor, which motor will also drive the crusher, set adjacent, if desiraple. Tne conveyor shall have side boards to prevent scillins of coal, and shall be provided with adjustable besrinss at one end to care for slack in the chains. a yep COaL LU Debs. t The crusner shall be of the two roll tyne with spring release of rolls for large pieces of foreisn matter. L? tne rolls shall be Ge" dyqueter x 24" wide, and with a apacity to crush 40 tons per hour of 3/4 lump gas coal QO to pass an l ¢" screen. Tne crusher shall be Link selt Co's. type "..", or equal. the feeding hopoer and outlet Chute of the crusher shall be meade of 1/4 " steel plate securely riveted and provcerly supoorted. The crusher is to be driven, preferably by the motor which drives the apron feeder. “Ay rapa TAN aor RPITITIN ITN DLAVATCR fadv CCH vu VCR Tne elevator ard conveyor shall be of the pivoted dDucket tyne, <4"x 64" size, and a so called "reck Carrier” manufactured by the Link Selt To., with a casacity ata Qu moderate speed, of 40 tons per hour. This conveyor is to receive tne coal from the ermisher on the lower run, el- evate it high enough to clear the tcp of the ovens, con- vey it over the oven top, and discharge into the top of the hopper type storage bin. The bin is 35ft. long. The conveyor is to deliver the coal eight feet above the top of the bin, so that the coal will pass by gravity to both ends and to the middls of the bin. These shall be a sta- tionary tripper over the storase bin to cause the coal to be dumped into the chutes, which are provided to guide it to all parts of the bin. all necessary sprocket wheels, idlers, guides and driving mechanisms shall be provicec, ~~ or! together with an electric motor at the criving corner. this motor shall be furnished with ‘distant control located Lé on the char reing floor as shall be directed by the Cwners. All stecl frame work and housins for the conveyor gnall be provided. Yhe conveyor shall be aapl3y protected from the weather, especially from ice and snow, and shall be Guipoed with stairs and ladders conveniently located for inspection and repairs. In brief, a standard reck Carrier is called for, installed as may be recomiended by the Link i. rn mts ~ belt cc. Of Cnicazo, Ill. oy fir T™ over ”“ rte rey NB Tm Oust Wid Ai.) a OUL:. atéea broad the contract the con- aS soon as nossibdle after, takings tractor shall furnish tne Cvmers with detaile. plans an instructions for excavating and for placin; the founcation for every piece of apparatus and structure. arn roe 7 TMT oe iw Dat the storage bin shall be of the hopper type, made of 3/8 " steel plate properly riveted and lined on the inside with reinforced concrete 3 1/2 inches thick. It shall be about 25 ft. long, 15 ft. wide and about 17 ft. dees, and shall hold 20O tons when heaned full of Sas coal crushed Q2 >) to pass an 11/4 " screen. The bottom of the delivery spout must be 40 ft. above the grad- line of the railway Side track of tov of the track hopper. The bin shall be suptortec on steel columns the clearance dimensions for which are shown on drawing ho.3. The nerth rovi of support— LO ins columns will rest on svcecial cross sirders over the tops of the ovens, as provided for and shown on drawings co of the ovens by the Gas itachinery Co.The bin shall be covered with a suitable roof as shown on drawing No.3. The conerete lining shall be placed by the contractor and snall be mece of well mixed concrete of the follow-— ins pronortions,- Portland cement, 1 part, sharp sand 2 1/2 parts and broken stone not larser than 3/4" in diameter Oo parts. BCOCCNOCTIVE SRANZ OC aw £ Vag wJartads su The locomotive crane shall > be a Link Belt Cots. (or equal) standard steam locomotive crane, with an eignt Wheel truex, standard rallway Gugqof 4'-6 l/z", 55 ft. radius and 2 yurd grab bucket for use in handlins coal. Tne minimum clearance height of bucket at 50 ft. radius when fully loaded shell be ez ft. This crane shall be self propelling and provided with stancerd couplers on each end, so that it can be used to handle railway curs in the yard. It shall be fully housed to protect the op- rator in the winter time. GiuwI b--4 sa e COAL pI? + @ LT eatule Le.¥ LiiG The Owners will do all grading and fillings; will construct the concrete coal pit for the yard storace system,and oe responsible for the laying of all railway tracks. 20 COVERT CViR SOCHVEYOR AND CRUSHER. Tae contractor shall provide a reinforced concrete covering over all apparatus between the track hopper and the oven stack. This covering shall be strong enough and Suitable for general floor use and be a proper protection from the weather for the ancaratus beneath. 2 oofecial construction to be done by the Cwners. The conerete digging pit for coal in the storage yerd is shown on drawing lo.5. It should be constructed io] 3 of well mixed corcrete of the following proportions,- irortland cement 1] surt, clean sharn sand 2 parts and medium acsrecsatve 4 parts. me I beam supports for the railway track should be set level and true and according to the instructions of the railway track foreman. Tne I beams rest on the wells of the coal pit for supoort and are incased in con- crete to vrevent corrosion. the digging vit is surrounded on three sides by a wall two feet above grade line to prevent tne inclusion of foreign matter with the coal and to prevent accid:nts to the opsratcrs. Tne storaze vard hes been filled in until it is prac- tically level. The Cwners will arrange with the Railwa; Co. for the laying of the necessary; tracks thruout the yard and for any necessary grading. the track sl.ould be well laid and of substanthal weight, say rails of about 80 lbs. per yard. Yen fillings the storage yard tne outer edses should be filled first and then the space toward the center, pro- vided it is planned to completely fill the yard. when com- pletely full only the princival yard track would be left uncovered with coal. Over this track the coal for daily Uu 6) e and any shipments of ccke can be passed. If only a part of tis storase svace is to be filled then the cir- cular storaze track snould be used. Coal dunved into the Giscting bit can casily be handled from cers to the storarce Nile by the locomotive crane. suid wien reelsination is a wo essary it is most easily accomylisned from the cir- © ne cular sile. The Circular Yrack system of storing coal, as putlined on drewing Lo. 4, has been patented by the Link belt Co. of Chicaso, Ill. and the Cwners will make arrarcement with that Company for the risht to use it in this layout. The estimated cost of the ecuivnent, as outlined and listed in the specifications, completely installed is as follows,- POR? STCPAIT - n Dara r tus Locomotive ersne ------~---------- SlE 000.00 conerete diccting nit in yard------ 500 .CO Vailvey track thruout the yard,?Q,, charsed to coal handling and half of that to storacse yard, ------- 1 00C.CO Total direct 1G 500.00 g “Enfineering expense -------10,.-- 1 65C.CQ Total---- 312 150.00 FOR COznL LARDLING, Dally Track hopper and pit by ovens -- 51 000.00 Coal crusne Yq ne «~ 000.00 apron feeder ----------——---—---—— » 000.00 mopper type storage bin -------- 4 000.00 oO Pivoted bucket elevator and carrier 000.00 Railway track, half of total to coaljl 000.00 Total — $320 000.00 000.00 CD mnginesrins expense --10/.------ Total 28 000.00 Total cost of installation for both store H> wv) Yi Te — VPRwW’ se wT IT -~ a Tes (N37 w™~ ff orae adnd bh dacocd cas Ce Lu YW Dall’ COA DINO e il Cha RalL at let operating cost for bucket carrier &.4,,/ton ro overate tne coal handling system for daily suopvly will recuire l man &32.75/ day or - 6084, " Total investment, exclusive of bucket carrier, is 314 000.CO. If 15; is charzsed for depreciation, interest and repairs that sives 32 100.00 per year or----- 1.7in0 " Total cost to handle, per ton ------ 4A.wAG y AN Yr ON ote ; IAT ON whoaosis LU Oo PCRs Cn an assumed anount of 50 CCO tons > C7 per ,car to storase this equals ------- 5.45 _/ ton lman € %2.75 per day Doeed fpr 350 tons -----—--- 1.85 y/ton Fuel cost, 50 h.p. --—------------- 1.00 ¢ " rotal cost per ton to place in storase-- 8.30 y " It will cost about the same to reclaim from the storacse pile and celiver to the ovons. when coal ls stored in the yard and later used in the ovens twice this umount must be added to the cost to handle at the oven stack or a total amount, per ton of -—---<0.8467 If more than the assumed 50 000 tons per year be pus in and out of storare the cost per ton would decrease _— A somewnat. Mor instance if 100 OOO tons were to be handled ver year the cost would be about 5.55 ¢ per ton as against 8,00¢ for tne smaller amount. rrr enw “TD doin ail. I 3 93 03075 535 THANG ._ a